Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Bhojpur)
|
EDS
|
User Agency (patna@nhai.org)
|
17/01/2023
|
In relation to Project Proposal No. FP/BR/ROAD/157408/2022 for diversion of 1.964 ha, the Following documents are necessary to be submitted in order to process Part II/Site Inspection at DFO level.
1. Tree Enumeration list is not submitted. Because of which, site inspection could not be done
2. Tree Protection Plan is not submitted. Because of which Translocation Plan could not be finalised.
3. Typical Cross Section of proposed road is not submitted because of which actual area to be diverted could not be assessed/matched with area proposed to be diverted.
4. FRA Certificate is not submitted.
5. Absenteeism on part of user agency in participating during site inspection/meeting conducted on 30/09/22 and 12/10/22.
Above mentioned EDS has been communicated to the user agency vide thi
|
|
2
|
User Agency (patna@nhai.org)
|
REPLY
|
DFO (Bhojpur)
|
23/03/2023
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Patna)
|
EDS
|
User Agency (patna@nhai.org)
|
22/06/2023
|
Some qurey
|
|
4
|
User Agency (patna@nhai.org)
|
REPLY
|
DFO (Patna)
|
12/02/2024
|
The correction have been made as per the instruction received
|
|
5
|
DFO (Patna)
|
EDS
|
User Agency (patna@nhai.org)
|
09/10/2024
|
kindly submit the joint inspection report of trees as per letter number 2507 dated on 08/10/2024 so that further processing can be done.
|
|
6
|
User Agency (patna@nhai.org)
|
REPLY
|
DFO (Patna)
|
25/10/2024
|
The correction have been made as per the instruction received
|
|