TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/BR/ROAD/157408/2022              (ii). Name of Project for which Forest Land is required : Construction of 4/6 Laning of Arrah-Sasaram-Patna road section of NH-119A from Km 00+000 to Km 34+800 (Ring Road) under Bharatmala Pariyojana (Lot-7/Package-2) in the State of Bihar (Package-III)              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Diversion of 1.964 Ha forest land for Construction of 4/6 Laning of Arrah-Sasaram-Patna road section of NH-119A from Km 00+000 to Km 34+800 (Ring Road) under Bharatmala Pariyojana (Lot-7/Package-2) in the State of Bihar (Package-III)              (iv). File no. : FP/BR/ROAD/157408/2022              (v). State : Bihar              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 1.964
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/BR/ROAD/157408/202224/06/202202/07/2022   15/07/2022   28/07/2022   30/08/2022

Patna :11/10/2022


Bhojpur :11/10/2022

Patna:
  23/11/2024 (Bhojpur)

Patna:
  28/11/2024 (Patna)

Bihar:
28/11/2024
Bihar:
28/11/2024
Ranchi:
15/01/2025
26/01/2025
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by DFO (Bhojpur) on:17/01/2023  
Replied by UA on :23/03/2023  
Query raised by DFO (Patna) on:22/06/2023  
Replied by UA on :12/02/2024  
Query raised by DFO (Patna) on:09/10/2024  
Replied by UA on :25/10/2024  
NOTE:- Stage-I Approval accorded by : Regional Office .