TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/AS/RAIL/7657/2014              (ii). Name of Project for which Forest Land is required : New BG Railway line from New Maynaguri to Jogighopa              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : To provide an alternate route to Guwahati via Naranarayan setu across river Brahmaputra and to connect the important cities like Tufanganj, Boxirhat, Bilasipara and Chapar of West Bengal and Assam with Railway line.              (iv). File no. : 3 AS C 028/2015-SHI              (v). State : Assam              (vi). Category of the Project : Railway              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 29.855
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/AS/RAIL/7657/201413/11/201427/11/2014  25/11/2014   27/11/2014  25/11/2014   27/11/2014   28/11/2014 Parbatjhora:  28/11/2014
Dhubri:  28/11/2014
Aie Valley:  28/11/2014
C.F Lower Assam Social Forestry Circle, Bongaigaon:
  01/02/2015 (Dhubri)

C.F Lower Assam Social Forestry Circle, Bongaigaon:
  11/02/2015 (Aie Valley)

Western Assam Circle, Kokrajhar:
  12/02/2015 (Parbatjhora)

Assam:
30/04/2015
Assam:
05/05/2015
Guwahati:
07/05/2015
21/07/2015
By :Regional Office
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by Nodal Officer (Assam) on:03/04/2015  
Replied by Circle(Western Assam Circle, Kokrajhar) on:28/04/2015  
Query raised by Nodal Officer (Assam) on:03/04/2015  
Replied by Circle(C.F Lower Assam Social Forestry Circle, Bongaigaon) on:30/04/2015  
Query raised by Circle (C.F Lower Assam Social Forestry Circle, Bongaigaon) on:17/04/2015  
Replied by DFO (Parbatjhora) on:27/04/2015  
Query raised by Circle (Western Assam Circle, Kokrajhar) on:24/04/2015  
Replied by DFO (Dhubri) on:27/04/2015  
Query raised by Circle (C.F Lower Assam Social Forestry Circle, Bongaigaon) on:27/04/2015  
Replied by DFO (Dhubri) on:27/04/2015  
Query raised by Circle (C.F Lower Assam Social Forestry Circle, Bongaigaon) on:27/04/2015  
Replied by DFO (Dhubri) on:27/04/2015  
Query raised by Circle (C.F Lower Assam Social Forestry Circle, Bongaigaon) on:29/04/2015  
Replied by DFO (Aie Valley) on:30/04/2015  
Query raised by Circle (C.F Lower Assam Social Forestry Circle, Bongaigaon) on:29/04/2015  
Replied by DFO (Dhubri) on:30/04/2015  
Query raised by Circle (C.F Lower Assam Social Forestry Circle, Bongaigaon) on:30/04/2015  
Replied by DFO (Aie Valley) on:30/04/2015  
NOTE:- Stage-I Approval accorded by : Regional Office .