TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/AS/Others/120624/2021              (ii). Name of Project for which Forest Land is required : Dergaon - Dimapur Natural Gas Pipeline Project              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Spur line from Guwahati - Numaligarh Natural Gas Pipeline to supply Gas Demands of North East.              (iv). File no. : FNO-3 ASA 075/2021/GHY              (v). State : Assam              (vi). Category of the Project : Others              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 79.5284
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/AS/Others/120624/202115/02/202107/04/2021  03/03/2021   13/04/2021  25/03/2021   27/04/2021   03/05/2021 Golaghat :06/05/2021C.F. E.A.C, Jorhat:
  09/12/2021 (Golaghat)

Assam:
20/12/2021
Assam:
21/12/2021
Guwahati:
23/12/2021
09/05/2022
By :Regional Office
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Guwahati) on:29/12/2021  
Replied by State Government(Assam) on:21/01/2022  
Query raised by Regional Office (Guwahati) on:07/02/2022  
Replied by State Government(Assam) on:28/03/2022  
NOTE:- Stage-I Approval accorded by : Regional Office .