TimeLine Details
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
Proposal received date at each stage of flow.
A.
General Details
(i). Proposal No. :
FP/AR/TRANS/43704/2020
(ii). Name of Project for which Forest Land is required :
Pareng Transmission Line
(iii). Short narrative of the proposal and Project/scheme for which the forest land is required :
132KV S/C transmission line of 10.23 kms for pareng 14.5mw SHP.
(iv). State :
Arunachal Pradesh
(v). Category of the Project :
Transmission Line
(vi). Shape of forest land proposed to be diverted :
Linear
(vii). Area of forest land proposed for diversion(in ha.):
11.82
B.
Time Line
Proposal No.
Submitted by User Agency
Query for Shortcoming(if any) by Nodal Officer
Resubmission of Proposal by User Agency
Query by Nodal Officer for submitting Hard Copies
Uploading(by U.A.) of copies of receipt received from DFO & DC
Division
Circle
Nodal Office
State Government
Regional Office
Stage-I Approval on
Stage-II Approval on
FP/AR/TRANS/43704/2020
02/01/2020
06/01/2020
04/02/2020
05/02/2020
18/03/2020
Sagalee Forest Division, Sagalee
:
11/05/2020
C. Essential Details Sought History
 
Communication between Regional Office & State Government
Communication between State Government & Nodal Officer
Communication between Nodal Officer & Circle
Communication between Circle & Division
Communication between Division & User Agency
Query raised by DFO (Sagalee Forest Division, Sagalee) on:
13/07/2021
NOTE:-
Proposal is pending at
DELISTED (due to non-reply of EDS by UA within 90 days)
due to EDS raised by
DELISTED
.
Close(X)
Close(X)
Please wait ...
EDS History
×
EDS History
×
Proposal No.-
Sno.
From
Status
To
EDS Date
EDS sought/Replied
EDS Letter
1
DFO (Sagalee Forest Division, Sagalee)
EDS
User Agency (vikramaggarwal@virtuaal.in)
13/07/2021
kindly withdraw the proposal
EDS History(Stage-II)
×