  (i). Proposal No. : FP/AR/TRANS/40221/2019              (ii). Name of Project for which Forest Land is required : Revised proposal for diversion of 48.987 ha Forest land for construction of 132 kV D/C Transmission Line from Biswanath Chariali to Itanagar.              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Revised proposal for diversion of 48.987 ha Forest land applied in place of already approved 48.147 ha forest land for the same project. Narrative of proposal is enclosed in additional documents.              (iv). File no. : 3-ANC 082/2019-SHI              (v). State : Arunachal Pradesh              (vi). Category of the Project : Transmission Line              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 48.987
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/AR/TRANS/40221/201913/05/201915/05/2019   15/05/2019   20/05/2019   21/05/2019 Banderdewa Forest Division,Banderdewa :21/05/2019Western Arunachal Circle,BANDERDEDEWA:
  04/07/2019 (Banderdewa Forest Division,Banderdewa)

Arunachal Pradesh:
04/07/2019
Arunachal Pradesh:
08/07/2019
Guwahati:
08/07/2019
23/09/2019
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Guwahati) on:19/07/2019  
Replied by State Government(Arunachal Pradesh) on:16/08/2019  
Query raised by DFO (Banderdewa Forest Division,Banderdewa) on:30/05/2019  
Replied by UA on :01/06/2019  
NOTE:- Proposal is pending at Pending at DFO for verifying Compliance of Conditions .