  (i). Proposal No. : FP/AR/TRANS/35448/2018              (ii). Name of Project for which Forest Land is required : Construction of 132kV T/L from Namsai to Miao under Comprehensive Scheme for Strengthening of Transmission and Distribution in Arunachal Pradesh              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : The Proposed 132 kV TL from Namsai to Miao is a Sub Project which is conceived under the Govt of India ambitious project namely Comprehensive Scheme for Strengthening of T&D system in Arunachal Pradesh ( A central sector project funded by GoI and being implemented by POWERGRID)              (iv). File no. : 3-AN-A -112/2019-SHI              (v). State : Arunachal Pradesh              (vi). Category of the Project : Transmission Line              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 110.817
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onCompliance Report Submitted by State onStage-II Approval on
FP/AR/TRANS/35448/201830/08/201814/09/2018   28/09/2018   03/10/2018   27/10/2018

Nampong Forest Division,Jairampur :29/10/2018


Namsai Forest Division,Namasi :29/10/2018

Eastern Arunachal Circle,TEZU:
  14/09/2021 (Namsai Forest Division,Namasi)

Southern Arunachal Circle,DEOMALI:
  12/07/2022 (Nampong Forest Division,Jairampur)

Arunachal Pradesh:
12/07/2022
Arunachal Pradesh:
12/07/2022
Guwahati:
12/07/2022
25/02/2022
By :Regional Office
Arunachal Pradesh
11/11/2022
16/02/2023
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Guwahati) on:13/07/2022  
Replied by State Government(Arunachal Pradesh) on:29/07/2022  
Query raised by Regional Office (Guwahati) on:03/08/2022  
Replied by State Government(Arunachal Pradesh) on:18/08/2022  
D. Essential Details Sought History (Stage-II)
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & User Agency
Query raised by Regional Office (Guwahati) on:08/12/2022  
Replied by State Government(Arunachal Pradesh) on:13/02/2023  
NOTE:- Stage-II Approval accorded by : Regional Office .