TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/AR/TRANS/29908/2017              (ii). Name of Project for which Forest Land is required : 132 KV Transmission Line Single Circuit Of 28.947 Kms Length From Dikshi Power House To Existing Gridline Balipara-Khuppi, Near Nichupu.              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : The above 132 KV single Circuite Transmission Line is proposed for evacuation of power from Dikshi HEP(24 MW) to the existing Gridline Balipara-Khuppi line near Nechiphu. The entire transmission line is passing through Bomdila and Shergaon              (iv). File no. : 3-AN-B-109/2019-SHI              (v). State : Arunachal Pradesh              (vi). Category of the Project : Transmission Line              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 4.6
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/AR/TRANS/29908/201727/10/2017aa08/02/2018   16/05/2018

Shergaon Forest Division,Rupa :16/05/2018


Bomdila Forest Division,Bomdila :16/05/2018

Western Arunachal Circle,BANDERDEDEWA:
  07/06/2022 (Bomdila Forest Division,Bomdila)

Western Arunachal Circle,BANDERDEDEWA:
  07/06/2022 (Shergaon Forest Division,Rupa)

Arunachal Pradesh:
07/06/2022
Arunachal Pradesh:
07/06/2022
Guwahati:
07/06/2022
22/08/2022
By :Regional Office
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Guwahati) on:24/06/2022  
Replied by State Government(Arunachal Pradesh) on:29/07/2022  
Query raised by Regional Office (Guwahati) on:03/08/2022  
Replied by State Government(Arunachal Pradesh) on:17/08/2022  
Query raised by DFO (Shergaon Forest Division,Rupa) on:21/05/2018  
Replied by UA on :22/05/2018  
NOTE:- Stage-I Approval accorded by : Regional Office .