TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/AR/TRANS/148319/2021              (ii). Name of Project for which Forest Land is required : Construction of 132 kV S/C on D/C Tower from Along to Kambang under Comprehensive Scheme for Strengthening of Transmission and Distribution System in Arunachal Pradesh.              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : The proposed 132kV S/C on D/C Tower from Along to Kambang TL is a sub-project conceived under Govt. of India‚Äôs ambitious project namely, 'Comprehensive Scheme for Strengthening of Transmission & Distribution System in Arunachal Pradesh.              (iv). State : Arunachal Pradesh              (v). Category of the Project : Transmission Line              (vi). Shape of forest land proposed to be diverted : Linear              (vii). Area of forest land proposed for diversion(in ha.): 95.4
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/AR/TRANS/148319/202111/10/2021aa26/10/2021   28/10/2021 Aalo Forest Division, Aalo :02/11/2021Central Arunachal Circle,PASIGHAT:
  28/05/2022 (Aalo Forest Division, Aalo)

Arunachal Pradesh:
09/11/2022
Arunachal Pradesh:
09/11/2022
Guwahati:
09/11/2022
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Guwahati) on:21/11/2022  
NOTE:- Proposal is pending at State Government due to EDS raised by Regional Office .