Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
Regional Office
|
EDS
|
State secretary
|
13/04/2022
|
CA, SoI map etc.
|
|
2
|
State secretary
|
EDS
|
Nodal Officer
|
04/05/2022
|
enumeration list should be corrected
|
|
3
|
Nodal Officer
|
EDS
|
CF (Central Arunachal Circle,PASIGHAT)
|
10/05/2022
|
enumeration list should be corrected
|
|
4
|
CF (Central Arunachal Circle,PASIGHAT)
|
EDS
|
DFO (Aalo Forest Division, Aalo)
|
10/05/2022
|
enumeration list should be corrected
|
|
5
|
DFO (Aalo Forest Division, Aalo)
|
EDS
|
User Agency (ahijitroy@gmail.com)
|
10/05/2022
|
Employments generation should be corrected & fresh Undertaking of CA & NPV should be uploaded. Proposal No. FP/AR/DEF/46450/2020 is withdrawn or not.
|
|
6
|
User Agency (ahijitroy@gmail.com)
|
REPLY
|
DFO (Aalo Forest Division, Aalo)
|
10/05/2022
|
The correction have been made as per the instruction received
|
|
7
|
DFO (Aalo Forest Division, Aalo)
|
REPLY
|
CF (Central Arunachal Circle,PASIGHAT)
|
10/05/2022
|
correction have been made as per instructed
|
|
8
|
CF (Central Arunachal Circle,PASIGHAT)
|
REPLY
|
Nodal Officer
|
10/05/2022
|
correction have been made as per instructed
|
|
9
|
Nodal Officer
|
REPLY
|
State secretary
|
10/05/2022
|
correction have been made as per instructed
|
|
10
|
State secretary
|
REPLY
|
Regional Office
|
10/05/2022
|
correction have been made as per instructed
|
|
11
|
Regional Office
|
EDS
|
State secretary
|
19/05/2022
|
Uploading on Parivesh Portal
|
|
12
|
State secretary
|
REPLY
|
Regional Office
|
19/05/2022
|
Reply
|
|
13
|
Regional Office
|
EDS
|
State secretary
|
26/05/2022
|
Shape/kml file of CA area, Inviolate, DSS report etc.
|
|
14
|
State secretary
|
EDS
|
Nodal Officer
|
14/06/2022
|
IRO letter is attached herewith.
|
|
15
|
Nodal Officer
|
EDS
|
CF (Central Arunachal Circle,PASIGHAT)
|
14/06/2022
|
IRO letter is attached herewith.
|
|
16
|
CF (Central Arunachal Circle,PASIGHAT)
|
EDS
|
DFO (Aalo Forest Division, Aalo)
|
14/06/2022
|
IRO letter is attached herewith.
|
|
17
|
DFO (Aalo Forest Division, Aalo)
|
EDS
|
User Agency (roitanagarnhidcl@gmail.com)
|
14/06/2022
|
Clarify the reason for uploading the proposed area in favour of CPWD despite the change of User Agency to NHIDCL.
|
|
18
|
User Agency (roitanagarnhidcl@gmail.com)
|
REPLY
|
DFO (Aalo Forest Division, Aalo)
|
24/02/2023
|
The correction have been made as per the instruction received
|
|
19
|
DFO (Aalo Forest Division, Aalo)
|
REPLY
|
CF (Central Arunachal Circle,PASIGHAT)
|
02/03/2023
|
Correction have been made as per direction
|
|
20
|
CF (Central Arunachal Circle,PASIGHAT)
|
REPLY
|
Nodal Officer
|
02/03/2023
|
Correction have been made as per direction
|
|
21
|
Nodal Officer
|
REPLY
|
State secretary
|
02/03/2023
|
Correction have been made as per direction
|
|
22
|
State secretary
|
REPLY
|
Regional Office
|
02/03/2023
|
EDS Reply
|
|