TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/AR/HYD/24836/2017   (ii). Name of Project for which Forest Land is required : Nyukcharong Chu Hydro Electric Project (96 MW)   (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Nyukcharong Chu HEP (96 MW)is proposed on Nyukcharong Chu, under S.F Division Tawang in Arunachal Pradesh. 22m high&74.20m long barrage,1271m long HRT & U.G Power House are proposed. The bare minimum Forest land required for the project is 38.46ha. The estimated annual generation is 466.12 GWh.   (iv). State : Arunachal Pradesh   (v). Category of the Project : Hydel   (vi). Shape of forest land proposed to be diverted : Non Linear   (vii). Area of forest land proposed for diversion(in ha.): 38.46
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeROHQ, New DelhiStage-I Approval onStage-II Approval on
FP/AR/HYD/24836/201708/03/201710/03/2017   14/03/2017   22/03/2017   06/05/2017 Tawang SF Division. Tawang :20/03/2019
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
  
NOTE:- Proposal is pending at DFO .