TimeLine Details
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
Proposal received date at each stage of flow.
A.
General Details
(i). Proposal No. :
FP/AR/HYD/16208/2015
(ii). Name of Project for which Forest Land is required :
Attunli Hydro Electric Project (680 MW)
(iii). Short narrative of the proposal and Project/scheme for which the forest land is required :
Government of Arunachal Pradesh (GoAP) decided to develop Attunli HEP in the Private Sector / Joint Sector on Build, Own, Operate and Transfer (BOOT) basis. Hydro Power Development Corporation of Arunachal Pradesh Limited (HPDCAPL), a public sector undertaking set up by GoAP for development of Hydro
(iv). State :
Arunachal Pradesh
(v). Category of the Project :
Hydel
(vi). Shape of forest land proposed to be diverted :
Non Linear
(vii). Area of forest land proposed for diversion(in ha.):
261.53
B.
Time Line
Proposal No.
Submitted by User Agency
Query for Shortcoming(if any) by Nodal Officer
Resubmission of Proposal by User Agency
Query by Nodal Officer for submitting Hard Copies
Uploading(by U.A.) of copies of receipt received from DFO & DC
Division
Circle
Nodal Office
State Government
MoEFCC,New Delhi
Regional Office(SIR)
Stage-I Approval on
Stage-II Approval on
FP/AR/HYD/16208/2015
26/10/2015
13/11/2015
10/11/2015
07/06/2019
12/11/2015
02/08/2019
03/08/2019
Anini SF Division, Anini
:
05/08/2019
C. Essential Details Sought History
 
Communication between MoEFCC,New Delhi & State Government
Communication between State Government & Nodal Officer
Communication between Nodal Officer & Circle
Communication between Circle & Division
Communication between Division & User Agency
NOTE:-
Proposal is pending at
DFO
.
Close(X)
Close(X)
Please wait ...
EDS History
×
EDS History
×
Proposal No.-
Sno.
From
Status
To
EDS Date
EDS sought/Replied
EDS Letter
No Record Available
EDS History(Stage-II)
×