TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/AP/ROAD/49639/2020              (ii). Name of Project for which Forest Land is required : Rehabilitation and Upgradation to two lane with paved shoulder configuration of Koyyuru to Paderu section from Km 120/000 to Km 260/100(Design chainage Km Km 120+000 To Km 253+974) of NH-516Ein the state of Andhra Pradesh              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Rehabilitation and Upgradation to 2L+PS configuration of Koyyuru - Chaprathipalem - Lambasingi - Paderu section (Km 120+000 to Km 253+974) of NH-516E in the state of Andhra Pradesh under Green National Highways Corridor Project (GNHCP) with the loan assistance of World Bank on EPC Mode              (iv). State : Andhra Pradesh              (v). Category of the Project : Road              (vi). Shape of forest land proposed to be diverted : Linear              (vii). Area of forest land proposed for diversion(in ha.): 60.06
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/AP/ROAD/49639/202016/09/202011/01/2022  23/10/2020   01/02/2022  29/12/2021   04/02/2022   12/02/2022

Narasipatnam :17/02/2022


Paderu :17/02/2022

Visakhapatnam:
  12/08/2022 (Narasipatnam)

Visakhapatnam:
  16/08/2022 (Paderu)

Andhra Pradesh:
07/09/2022
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by Nodal Officer (Andhra Pradesh) on:06/10/2022  
Replied by Circle(Visakhapatnam) on:23/11/2022  
Query raised by Circle (Visakhapatnam) on:18/08/2022  
Replied by DFO (Narasipatnam) on:19/08/2022  
Query raised by Circle (Visakhapatnam) on:21/08/2022  
Replied by DFO (Narasipatnam) on:06/09/2022  
Query raised by Circle (Visakhapatnam) on:15/10/2022  
Replied by DFO (Narasipatnam) on:05/11/2022  
Query raised by Circle (Visakhapatnam) on:14/11/2022  
Replied by DFO (Narasipatnam) on:15/11/2022  
Query raised by DFO (Narasipatnam) on:10/03/2022  
Replied by UA on :31/05/2022  
NOTE:- Proposal is pending at Nodal Officer .