TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/AP/ROAD/40711/2019              (ii). Name of Project for which Forest Land is required : for Providing BT to the Road from NR Puram ( Anantagiri Mandal of Visakhapatnam District) to Eguvakonda Parthi of Vizianagaram District              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Diversion of 3.09 ha. land for Providing BT to the Road from NR Puram ( Anantagi Mandal of Visakhapatnam District) to Eguvakonda Parthi of Vizianagaram District in Pedakonela beat,Vizianagaram Range, Vizianagarm Division in favor of Executive Engineer, PR(PIU) Division, Vizianagaram under FC Act 198              (iv). File no. : G.O.Ms.No.10              (v). State : Andhra Pradesh              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 3.09
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentStage-I Approval onStage-II Approval on
FP/AP/ROAD/40711/201901/07/201922/07/2019   19/09/2019   19/09/2019   15/11/2019 Vizianagram :15/11/2019Visakhapatnam:
  30/11/2019 (Vizianagram)

Andhra Pradesh:
26/12/2019
Andhra Pradesh:
28/01/2020
26/05/2020
By :State Government
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
  
NOTE:- Stage-I Approval accorded by : State Government .