Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
Nodal Officer
|
EDS
|
CF (Rajahmundry)
|
09/04/2021
|
Proposal not feasible to consider
|
|
2
|
CF (Rajahmundry)
|
EDS
|
DFO (Kakinada)
|
14/07/2021
|
Re-examination of the proposals
|
|
3
|
DFO (Kakinada)
|
REPLY
|
CF (Rajahmundry)
|
02/05/2022
|
Incompliance to the instructions issued, the re-verification report is submitted herewith.
|
|
4
|
CF (Rajahmundry)
|
REPLY
|
Nodal Officer
|
04/05/2022
|
Proposals not recommended as per the report of DFO, Kakinada
|
|
5
|
Nodal Officer
|
EDS
|
CF (Rajahmundry)
|
22/11/2022
|
Request the user agency to upload withdraw letter
|
|