TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/AP/OFC/38865/2019              (ii). Name of Project for which Forest Land is required : Laying of Under Ground Optical Fiber Cable (OFC)              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Laying of Optical Fiber Cable (OFC) along the Road within the existing Right of Way (RoW) passing through forest under Nellore division for 1.27 Ha. for providing 4G communications in the state of Andhra Pradesh as per the License granted by Govt. of India.              (iv). State : Andhra Pradesh              (v). Category of the Project : Optical Fibre Cable              (vi). Shape of forest land proposed to be diverted : Linear              (vii). Area of forest land proposed for diversion(in ha.): 1.27
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/AP/OFC/38865/201911/02/2019aa01/03/2019   05/03/2019 Nellore :12/03/2019Guntur:
  30/12/2019 (Nellore)

Andhra Pradesh:
08/01/2020
Andhra Pradesh:
27/02/2020
Vijayawada:
08/12/2023
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Vijayawada) on:16/04/2024  
Replied by State Government(Andhra Pradesh) on:28/10/2024  
Query raised by Regional Office (Vijayawada) on:13/01/2025  
Query raised by State Government (Andhra Pradesh) on:22/06/2020  
Replied by Nodal Officer (Andhra Pradesh) on:21/09/2023  
Query raised by State Government (Andhra Pradesh) on:24/04/2024  
Replied by Nodal Officer (Andhra Pradesh) on:01/10/2024  
Query raised by State Government (Andhra Pradesh) on:16/01/2025  
Query raised by Nodal Officer (Andhra Pradesh) on:06/07/2020  
Replied by Circle(Guntur) on:10/11/2022  
Query raised by Nodal Officer (Andhra Pradesh) on:16/12/2022  
Replied by Circle(Guntur) on:28/06/2023  
Query raised by Nodal Officer (Andhra Pradesh) on:30/06/2023  
Replied by Circle(Guntur) on:21/07/2023  
Query raised by Nodal Officer (Andhra Pradesh) on:03/08/2023  
Replied by Circle(Guntur) on:09/08/2023  
Query raised by Nodal Officer (Andhra Pradesh) on:06/05/2024  
Replied by Circle(Guntur) on:06/09/2024  
Query raised by Circle (Guntur) on:07/07/2020  
Replied by DFO (Nellore) on:03/11/2022  
Query raised by Circle (Guntur) on:19/12/2022  
Replied by DFO (Nellore) on:27/06/2023  
Query raised by Circle (Guntur) on:30/06/2023  
Replied by DFO (Nellore) on:20/07/2023  
Query raised by Circle (Guntur) on:03/08/2023  
Replied by DFO (Nellore) on:05/08/2023  
Query raised by Circle (Guntur) on:16/05/2024  
Replied by DFO (Nellore) on:21/08/2024  
Query raised by Circle (Guntur) on:03/09/2024  
Replied by DFO (Nellore) on:03/09/2024  
Query raised by DFO (Nellore) on:03/12/2020  
Replied by UA on :29/09/2022  
NOTE:- Proposal is pending at Nodal Officer due to EDS raised by Regional Office .