Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (WLM Tirupati)
|
EDS
|
User Agency (eegnssrgt2017@gmail.com)
|
23/01/2018
|
Omissions & Commissions
|
|
2
|
User Agency (eegnssrgt2017@gmail.com)
|
REPLY
|
DFO (WLM Tirupati)
|
05/06/2018
|
The correction have been made as per the instruction received
|
|
3
|
DFO (WL Chittoor East)
|
EDS
|
User Agency (eegnssrgt2017@gmail.com)
|
05/06/2018
|
Short comings noticed in the proposals in respect of area proposed for diversion in the jurisdiction of Chittoor East WL Division
|
|
4
|
User Agency (eegnssrgt2017@gmail.com)
|
REPLY
|
DFO (WL Chittoor East)
|
06/06/2018
|
The correction have been made as per the instruction received
|
|
5
|
DFO (WL Chittoor East)
|
EDS
|
User Agency (eegnssrgt2017@gmail.com)
|
06/06/2018
|
The authentication map of proposed diversion area as well as CA area are not yet received from the UA
|
|
6
|
User Agency (eegnssrgt2017@gmail.com)
|
REPLY
|
DFO (WL Chittoor East)
|
09/08/2018
|
The correction have been made as per the instruction received
|
|
7
|
CF (WLM - Tirupathi)
|
EDS
|
DFO (WLM Tirupati)
|
04/09/2018
|
Eco-Sensitive Zone extent not reported in the proposals
|
|
8
|
DFO (WLM Tirupati)
|
REPLY
|
CF (WLM - Tirupathi)
|
04/09/2018
|
Reply
|
|
9
|
CF (WLM - Tirupathi)
|
EDS
|
DFO (WLM Tirupati)
|
06/09/2018
|
The total area 594.75 H falls in ESZ. As per the guidelines, the proposals to submit in wildlife formats.
|
|
10
|
DFO (WLM Tirupati)
|
REPLY
|
CF (WLM - Tirupathi)
|
08/09/2018
|
Reply
|
|
11
|
Nodal Officer
|
EDS
|
CF (WLM - Tirupathi)
|
10/09/2018
|
please upload the site inspection report by the CF
|
|
12
|
CF (WLM - Tirupathi)
|
REPLY
|
Nodal Officer
|
10/09/2018
|
Reply
|
|