Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Kullu)
|
EDS
|
User Agency (manaliropeways20@gmail.com)
|
18/05/2018
|
Please send the hard copy of the proposal folder to this office.
|
|
2
|
User Agency (manaliropeways20@gmail.com)
|
REPLY
|
DFO (Kullu)
|
25/08/2018
|
The correction have been made as per the instruction received
|
|
3
|
Nodal Officer
|
EDS
|
CF (Kullu)
|
01/09/2018
|
EDS
|
|
4
|
CF (Kullu)
|
EDS
|
DFO (Kullu)
|
01/09/2018
|
Please attend the observation as instructed by Nodal Officer
|
|
5
|
DFO (Kullu)
|
EDS
|
User Agency (manaliropeways20@gmail.com)
|
01/09/2018
|
Please attend the observation as raised by Nodal Officer vide EDS dated 01/09/2018
|
|
6
|
User Agency (manaliropeways20@gmail.com)
|
REPLY
|
DFO (Kullu)
|
03/09/2018
|
The correction have been made as per the instruction received
|
|
7
|
DFO (Kullu)
|
EDS
|
User Agency (manaliropeways20@gmail.com)
|
04/09/2018
|
The correction have been made as per the instruction received
|
|
8
|
User Agency (manaliropeways20@gmail.com)
|
REPLY
|
DFO (Kullu)
|
04/09/2018
|
The correction have been made as per the instruction received
|
|
9
|
DFO (Kullu)
|
REPLY
|
CF (Kullu)
|
04/09/2018
|
The EDS raised by the Nodal officer on dated 01/09/2018 have been attended and same uploaded in MOEF web portal
|
|
10
|
CF (Kullu)
|
REPLY
|
Nodal Officer
|
04/09/2018
|
The EDS raised on dated 01/09/2018 have been attended by DFO ,Kullu and same have been uploaded in MoEF portal please
|
|
11
|
Regional Office
|
EDS
|
State secretary
|
27/09/2018
|
The State Govt. may attend the shortcomings as per attachment here.
|
|
12
|
State secretary
|
EDS
|
Nodal Officer
|
28/09/2018
|
EDS
|
|
13
|
Nodal Officer
|
EDS
|
CF (Kullu)
|
28/09/2018
|
EDS
|
|
14
|
CF (Kullu)
|
EDS
|
DFO (Kullu)
|
29/09/2018
|
Please attend the observations raised by GoI as per the attached pdf. and submit the compliance report at the earliest.
|
|
15
|
DFO (Kullu)
|
EDS
|
User Agency (manaliropeways20@gmail.com)
|
01/10/2018
|
Please attend the observations raised by GoI as per the attached pdf. and submit the compliance report at the earliest.
|
|
16
|
User Agency (manaliropeways20@gmail.com)
|
REPLY
|
DFO (Kullu)
|
21/12/2018
|
The correction have been made as per the instruction received
|
|
17
|
DFO (Kullu)
|
REPLY
|
CF (Kullu)
|
22/12/2018
|
The observation has been attended as per instruction received.
|
|
18
|
CF (Kullu)
|
REPLY
|
Nodal Officer
|
24/12/2018
|
The EDS raised by GoI on dated 27/09/2018 have been attended by DFO ,Kullu and User agency and same have been uploaded in MoEF portal please
|
|
19
|
Nodal Officer
|
EDS
|
CF (Kullu)
|
01/01/2019
|
Please upload the FRA certificate against column No. K i.
|
|
20
|
CF (Kullu)
|
EDS
|
DFO (Kullu)
|
02/01/2019
|
Please upload the FRA certificate against column No. K i
|
|
21
|
DFO (Kullu)
|
EDS
|
User Agency (manaliropeways20@gmail.com)
|
03/01/2019
|
Please upload the FRA certificate against column No. K i
|
|
22
|
User Agency (manaliropeways20@gmail.com)
|
REPLY
|
DFO (Kullu)
|
03/01/2019
|
The correction have been made as per the instruction received
|
|
23
|
DFO (Kullu)
|
REPLY
|
CF (Kullu)
|
03/01/2019
|
The needful has been done as per instruction received.
|
|
24
|
CF (Kullu)
|
REPLY
|
Nodal Officer
|
03/01/2019
|
The FRA certificate against column No. K i has been uploaded.
|
|
25
|
Nodal Officer
|
REPLY
|
State secretary
|
07/01/2019
|
Complete reply is submitted.
|
|
26
|
State secretary
|
REPLY
|
Regional Office
|
07/01/2019
|
Complete reply is submitted.
|
|
27
|
Regional Office
|
EDS
|
State secretary
|
15/02/2019
|
State Govt. may attend the following shortcomings as per the attachment here
|
|
28
|
State secretary
|
EDS
|
Nodal Officer
|
15/02/2019
|
EDS
|
|
29
|
Nodal Officer
|
EDS
|
CF (Kullu)
|
15/02/2019
|
EDS
|
|
30
|
CF (Kullu)
|
EDS
|
DFO (Kullu)
|
18/02/2019
|
Please attend the observations raised by GoI as per the attached pdf.
|
|
31
|
DFO (Kullu)
|
EDS
|
User Agency (manaliropeways20@gmail.com)
|
22/02/2019
|
Please to through the observations as per the attached pdf and do the needful.
|
|
32
|
User Agency (manaliropeways20@gmail.com)
|
REPLY
|
DFO (Kullu)
|
11/03/2019
|
The correction have been made as per the instruction received
|
|
33
|
DFO (Kullu)
|
REPLY
|
CF (Kullu)
|
11/03/2019
|
The correction have been made as per the instruction received
|
|
34
|
CF (Kullu)
|
REPLY
|
Nodal Officer
|
11/03/2019
|
The EDS raised has been attended by the DFO Kullu as per the attached pdf.
|
|
35
|
Nodal Officer
|
REPLY
|
State secretary
|
11/03/2019
|
Complete reply is submitted.
|
|
36
|
State secretary
|
REPLY
|
Regional Office
|
11/03/2019
|
Complete reply is submitted.
|
|