| Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
|
1
|
CF (Kurnool)
|
EDS
|
DFO (Kurnool)
|
30/01/2021
|
Certain shortcomings required and further information called for Regarding
|
|
|
2
|
DFO (Kurnool)
|
REPLY
|
CF (Kurnool)
|
08/03/2021
|
Certain shortcomings and further information is submitted herewith.
|
|
|
3
|
CF (Kurnool)
|
EDS
|
DFO (Kurnool)
|
17/03/2021
|
further information called for
|
|
|
4
|
DFO (Kurnool)
|
REPLY
|
CF (Kurnool)
|
06/04/2021
|
Further information submitted
|
|
|
5
|
Nodal Officer
|
EDS
|
CF (Kurnool)
|
11/06/2021
|
Shortcomings Noticed
|
|
|
6
|
CF (Kurnool)
|
EDS
|
DFO (Kurnool)
|
18/06/2021
|
Shortcomings noticed
|
|
|
7
|
DFO (Kurnool)
|
REPLY
|
CF (Kurnool)
|
08/07/2021
|
Reply submitted
|
|
|
8
|
CF (Kurnool)
|
REPLY
|
Nodal Officer
|
14/07/2021
|
Additional Information submission off Reg
|
|
|
9
|
Nodal Officer
|
EDS
|
CF (Kurnool)
|
10/08/2021
|
Additional information requested.
|
|
|
10
|
CF (Kurnool)
|
EDS
|
DFO (Kurnool)
|
31/08/2021
|
Additional information requested
|
|
|
11
|
DFO (Kurnool)
|
EDS
|
User Agency (gmreddy9009@gmail.com)
|
03/11/2021
|
Submit the Approved Mining Plan - Reg
|
|
|
12
|
User Agency (gmreddy9009@gmail.com)
|
REPLY
|
DFO (Kurnool)
|
08/11/2021
|
The correction have been made as per the instruction received
|
|
|
13
|
DFO (Kurnool)
|
REPLY
|
CF (Kurnool)
|
18/11/2021
|
Approved Mining Plan submission off -Reg
|
|
|
14
|
CF (Kurnool)
|
EDS
|
DFO (Kurnool)
|
30/11/2021
|
Additional information called for
|
|
|
15
|
DFO (Kurnool)
|
REPLY
|
CF (Kurnool)
|
22/12/2021
|
Additional information submission off-Reg
|
|
|
16
|
CF (Kurnool)
|
EDS
|
DFO (Kurnool)
|
03/01/2022
|
Additional information as called for
|
|
|
17
|
DFO (Kurnool)
|
REPLY
|
CF (Kurnool)
|
07/01/2022
|
Additional information
|
|
|
18
|
CF (Kurnool)
|
REPLY
|
Nodal Officer
|
14/01/2022
|
Additional information submission off - Reg
|
|
|
19
|
Nodal Officer
|
EDS
|
CF (Kurnool)
|
09/02/2022
|
Additional Information requested
|
|
|
20
|
CF (Kurnool)
|
EDS
|
DFO (Kurnool)
|
23/02/2022
|
Additional information called for
|
|
|
21
|
DFO (Kurnool)
|
EDS
|
User Agency (gmreddy9009@gmail.com)
|
16/03/2022
|
Additional information called for -Re
|
|
|
22
|
User Agency (gmreddy9009@gmail.com)
|
REPLY
|
DFO (Kurnool)
|
04/04/2022
|
The correction have been made as per the instruction received
|
|
|
23
|
DFO (Kurnool)
|
REPLY
|
CF (Kurnool)
|
17/06/2022
|
Additional information submission off -Reg
|
|
|
24
|
CF (Kurnool)
|
EDS
|
DFO (Kurnool)
|
28/06/2022
|
Additional information called for
|
|
|
25
|
DFO (Kurnool)
|
EDS
|
User Agency (gmreddy9009@gmail.com)
|
09/07/2022
|
additional information called for
|
|
|
26
|
User Agency (gmreddy9009@gmail.com)
|
REPLY
|
DFO (Kurnool)
|
13/08/2022
|
The correction have been made as per the instruction received
|
|
|
27
|
DFO (Kurnool)
|
REPLY
|
CF (Kurnool)
|
13/08/2022
|
additional information submission
|
|
|
28
|
CF (Kurnool)
|
REPLY
|
Nodal Officer
|
16/08/2022
|
Additional information submission off
|
|
|
29
|
Regional Office
|
EDS
|
State secretary
|
30/03/2023
|
As per the attached EDS
|
|
|
30
|
State secretary
|
EDS
|
Nodal Officer
|
19/04/2023
|
Additional Information Called for.
|
|
|
31
|
Nodal Officer
|
REPLY
|
State secretary
|
16/06/2023
|
Modified Approved Mining Plan furnished by the User Agency is submitted
|
|
|
32
|
State secretary
|
REPLY
|
Regional Office
|
21/07/2023
|
Modified mining plan.
|
|
|
33
|
RO/HQ
|
EDS
|
( ROVIJA )
|
09/08/2024
|
Original e-file was already returned to Sub Office Vijayawada
|
|
|
34
|
Regional Office
|
EDS
|
State secretary
|
19/08/2024
|
As per attached EDS
|
|
|
35
|
State secretary
|
EDS
|
Nodal Officer
|
30/01/2025
|
CA area
|
|
|
36
|
Nodal Officer
|
EDS
|
CF (Kurnool)
|
12/02/2025
|
Requested to submit the reply to the EDS raised by the State Govt.,
|
|
|
37
|
CF (Kurnool)
|
EDS
|
DFO (Kurnool)
|
27/02/2025
|
Requested to submit the reply to the EDS raised by the State Govt. and Prl.CCF, AP, Mangalgiri
|
|
|
38
|
DFO (Kurnool)
|
EDS
|
User Agency (gmreddy9009@gmail.com)
|
21/03/2025
|
Requested to submit the reply to the EDS raised by the State Govt. and Prl.CCF, AP, Mangalgiri
|
|
|
39
|
User Agency (gmreddy9009@gmail.com)
|
REPLY
|
DFO (Kurnool)
|
21/03/2025
|
The correction have been made as per the instruction received
|
|
|
40
|
DFO (Kurnool)
|
REPLY
|
CF (Kurnool)
|
21/03/2025
|
EDS information submitted
|
|
|
41
|
CF (Kurnool)
|
REPLY
|
Nodal Officer
|
02/04/2025
|
EDS information submitted
|
|
|
42
|
Nodal Officer
|
EDS
|
CF (Kurnool)
|
12/09/2025
|
uploaded
|
|
|
43
|
CF (Kurnool)
|
REPLY
|
Nodal Officer
|
13/01/2026
|
The additional information called vide reference Rc.No.EFS02-15029/11/2018-FCA-1 dt 04.02.2025.
|
|
|
44
|
Nodal Officer
|
EDS
|
CF (Kurnool)
|
29/01/2026
|
The proposal was inadvertently forwarded to the Nodal Officer instead of the Divisional Forest Officer.
Accordingly, the proposal may be returned to the Conservator of Forests, Kurnool, with instructions to exercise due care while forwarding proposals in future.
|
|
|
45
|
CF (Kurnool)
|
EDS
|
DFO (Kurnool)
|
30/01/2026
|
EDS replies submitted by DFO nandyla
|
|
|
46
|
DFO (Kurnool)
|
REPLY
|
CF (Kurnool)
|
31/01/2026
|
EDS information submitted
|
|
|
47
|
CF (Kurnool)
|
REPLY
|
Nodal Officer
|
31/01/2026
|
addl information furnished by DFO nandyal and same submitted for necessaryaction
|
|
|
48
|
Nodal Officer
|
REPLY
|
State secretary
|
16/02/2026
|
The Government is requested to consider the EDS reply submitted by the CF, Kurnool and forward the same to the MoEF&CC, GoI, RO, Chennai for taking further
action
|
|
|
49
|
State secretary
|
REPLY
|
Regional Office
|
20/02/2026
|
Reply to EDS raised by MoEF&CC is submitted
|
|