PART-II
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal :
PB-0251/2021
1.
Location of the project/Scheme :
Punjab
(i)
State / Union Territory :
Punjab
(ii)
District :
Patiala
(iii)
Forest Division :
Patiala
 (iv)
Area of forest land proposed for diversion (in ha.) :
0.456
 (v)
Category of the Proposal:
Pipeline
2.
Legal status of forest land proposed for diversion
S. No.
Division
Forest Land(ha.)
Legal Status
1
Patiala
0.456
Protected Forest
Total
0.456
Division 1. : Patiala
3.
District wise area to be diverted in the division
S. No.
District
Area(ha.)
1
Patiala
0.456
Total
0.456
4.
Details of Vegetation available in the forest land proposed for diversion
(i)
Density of vegetation
S. No.
Area(in ha.)
Density
Eco-Class
1
0.456
0
Eco 3
Total.
0.456
(ii)
Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No.
Scientific Name
Local Name
(0-30)cm.
(31-60)cm.
(61-90)cm.
(91-120)cm.
(121-150)cm.
(>150)cm.
NIL
5.
Working plan prescription for the forest land proposed for diversion :
Diversion of 0.456 Ha. of Forest Land {(0.2250 Ha. at Narwana Branch Canal RD 78 – 81 RHS WTP Site Pabra), (0.0945 HA at Bahadurghar to Ghanaur Road from Shekhu pura to Siyalu RHS, Mandauli Cluster), (0.1365 HA at Banur Canal RD Nanhera to Bhuri Majra (RHS)} for the laying of drinking water Pipe line Various Strips in Rajpura Range, Tehsil Rajpura,Distt.Patiala under Forest Division, Patiala,Punjab.
6.
Brief note on vulnerability of the forest area to erosion :
72 Plants and 12 U/g Pole are affected
7.
Approximate distance of the proposed site for diversion from boundary of forest(in km.) :
0
8.
Significance of the forest land proposed for diversion from wildlife point of view
(i).
Details of wildlife present in and around the forest land proposed for diversion :
NA
(ii).
Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. :
No
(iii).
Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ):
No
(iv).
Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion :
No
(v).
Whether any rare/endangered/unique species of flora and fauna found in the area :
No
9.
Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
(i).
Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area :
No
10.
Comment as to the reasonability of the extent of the forest land proposed for diversion
(i).
Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project :
Yes
11.
Details of violation(s), if any ,committed
(i).
Whether any work in violation of the Act or guidelines issued under the Act has been carried out :
No
12.
Whether work in violation is still in progres(Yes/No) :
NIL
13.
Details of compensatory afforestation scheme
Patch wise details for Degraded Area (To be earmarked by DFO)
(i).
Total Financial Outlay for C.A(lacs):
660606
Patch Wise Details
S.no
Patch No.
Area(ha.)
Name of PF/RF
Range
Compartment No
Uploaded KML file of patch
1
1
1.476
PF
Samana
Badshapur Minor RD 0 to Tail Both side
View file
(ii).
Copy of CA scheme details:
(iii).
Scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station:
(iv).
Copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A.:
(V).
Copy of NOC from Competent Authority :
Additional information Details
S. No.
Documents
Remarks
1
DEPT APPROVAL LETTER
2
PHOTO
3
PWD NOC
4
LETTER WITH TABLE
5
APPROVED LAYOUT PLAN
6
DETAIL OF FOREST AREA
7
DETAIL OF NON FOREST AREA
8
DGPS MAP
9
GPM FEE
10
LAND SUITABILITY CERTIFICATE
11
LOCATION MAP OF CA SITE
12
PART II
13
UT CA NPV ACA ANPV
14
UT FRA
15
ACA SCHEME
16
UT PVT GOVT PREMISES
17
CA SCHEME
18
DETAILED NOTE ON THE PROJECT
19
OTHER DOCUMENTS
20
PART I
21
PROCESSING FEE CHALLAN
22
SITE INSPECTION REPORT
23
UT COST OF TREES
24
UT NON FOREST LAND
25
ANNEXURE A
26
PROJECT APPROVAL
14.
District Profile
S.no
District Name
Geographical area of the district (in ha.)
Forest area of the district (in ha.)
Total forest area diverted since 1980 (in ha.)
No. of Approved Cases
Forest Land including penal C.A. (in ha.)
Progress of compensatory afforestation as on(date)
A) Forest land (in ha.)
B) Non-forest land (in ha.)
1
Patiala
369947
11316.97
1069.543
709
2120.857
13/08/2021
1934.3327
69.5871
15.
Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division Name
Circle
Site inspected By
Whether site inspected
No. of times site visited
Site inspection report
Date of visit
Patiala
South Circle
DFO
Yes
One
18/10/2021
South Circle
CF
No
No Data
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16.
Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
Division
Circle
Recommendation By
Recommendation
Reason
Letter
Whether CF agreed
Patiala
South Circle
DFO
Recommended
Recommended for approval
South Circle
CF
Recommended
Recommended
Yes
Nodal Officer
Recommended
Public Utility Project
Specific recommendation of the State Government(Part V)
17.
Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
State
Recommendation By
Recommendation
Recommendation Date
Remarks
Signing Authority
Notification
Recommendation Letter
Punjab
State Secretary
Recommended
17/03/2022
Public Utility Project
State Govt. Officer
No Data
17.
Stage-I Clearance Report
Regional Office
Recommendation By
MoEF File No.
Date of Stage-I Clearance
Clearance Letter
Chandigarh
State Government
FOREST-FCA0FC2P/145/2021-FCA
16/03/2022
18.
Payment made by User Agency
Proposal No.
Application No.
Total Amount (Rs.)
Recieved Amount (Rs.)
Transaction Date
Transaction ID
Bank Name
Mode of Payment
Demmand Generated By User Agency
Demmand Verified By Nodal Officer
Uploaded Demand Letter
FP/PB/Pipeline/146466/2021
PIPELINE1464662021965
1,473,021.00
1,473,021.00
25/04/2022
CNRB411481346838
Union Bank Of India
NEFT/RTGS (Challan)
30/03/2022
30/03/2022
19.
Uploaded Status of Land to be transferred to Forest Department under FCA (Mutation Details) :
No
20.
Mutation Details Verified By Nodal Officer
Proposal No.
Verified Date
Mutation Letter
Remarks
FP/PB/Pipeline/146466/2021
20 Sep 2022
No Data
CA Land not required.
21.
Compliance Details Submitted by User Agency
Proposal No.
Compliance Details submitted on(Date)
Uploaded Letter
FP/PB/Pipeline/146466/2021
21 Sep 2022
22.
Compliance Details Verified by Nodal Officer
Proposal No.
Remarks
Verified Date
Uploaded Letter
FP/PB/Pipeline/146466/2021
Compliance Report
17 Oct 2022
23.
Stage-II Clearance Details
Proposal No.
Date of Stage-II Clearance
Proposal Status
Clearance Letter
FP/PB/Pipeline/146466/2021
16 Oct 2022
APPROVED
Print
Checklist for State Nodal Officer
×