PART-II
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal : MN-02/2016
1. Location of the project/Scheme : Manipur
 (i) State / Union Territory : Manipur  (ii) District : Chandel  (iii) Forest Division : Tengnoupal Forest Division, Chandel  (iv) Area of forest land proposed for diversion (in ha.) : 111.05  (v)

Category of the Proposal: Transmission Line
2. Legal status of forest land proposed for diversion
S. No. DivisionForest Land(ha.)Legal Status
1Tengnoupal Forest Division, Chandel24.329Wildlife Sanctuary
2Tengnoupal Forest Division, Chandel86.721Unclassed Forests
Total 111.05
Division 1. : Tengnoupal Forest Division, Chandel
3. District wise area to be diverted in the division
S. No. DistrictArea(ha.)
1Chandel111.05
Total111.05
4. Details of Vegetation available in the forest land proposed for diversion
 (i) Density of vegetation
S. No. Area(in ha.)Density Eco-Class
186.72160Eco 1
224.32965Eco 1
Total. 111.05


(ii) Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No. Scientific Name Local Name (0-30)cm. (31-60)cm. (61-90)cm. (91-120)cm. (121-150)cm. (>150)cm.
1Alnus Nepalensispareng0780000
2Albzzia Spp.albzzia0690000
3OthersThanji010914000
4Othersquercus024826000
5OthersHeikreng (Celtis australis011819000
6Cinnamomum ZeylanicumUsingsa060000
7Emblica OfficianalisHeikru0120000
8Misc. Speciesuningthou manbi0365000
9Othersusoi015812000
10Syzigium CuminiSileima0303000
11OthersTairen (Toona ciliata)001000
12OthersLinpop0240000
13OthersPheija (Wendlandra glabra)0480000
14Misc. SpeciesUthangjing0193000
15Misc. SpeciesWangthinam07310000
16Misc. SpeciesLarong0840000
17Misc. SpeciesThanji (Castanopsis)*0440000
18Misc. SpeciesKheu (Melanorhoea usitata)*040000
19Misc. SpeciesMeijigri (Xylia dolabriformis)*000000
20Bauhinia ParvifloraChingthrao*000000
21Misc. SpeciesKhangra (Dipterocarpus turbiculatus)*0880000
22Othersothers*0340000
Total 0 128293 00 0
Sub Total (No of Trees.) 1375


5. Working plan prescription for the forest land proposed for diversion : The forest land proposed for diversion falls within the Plantation, Protection and fuel/fodder working circles. Besides, the forest area of Wildlife sanctuary proposed to be diverted is managed separately.
6. Brief note on vulnerability of the forest area to erosion : The project site is linear in nature with narrow width as such erosion might be considerably low or negligible.
7. Approximate distance of the proposed site for diversion from boundary of forest(in km.) : 0
8. Significance of the forest land proposed for diversion from wildlife point of view
 (i). Details of wildlife present in and around the forest land proposed for diversion : the area is rich in wildlife as some portion of the site also forms a part of Wildlife sanctuary. Some of the important animals present include slow Loris, Leopard cat, clouded leopard, python and Mr.
 (ii). Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. : Yes
  Details and comments on the impact of Project on such areas : The electric transmission line of the project will pass through the Yangnoupokpi Lokchao Wildlife Sanctuary. The impact of the project on the sanctuary might not be that high as only a linear strip of 3m width would be cleared on the ground. This shall also be planted with dwarf species.
 (iii). Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ): Yes
  Details of Protected Area and comments on the impact of Project on the ESZ : the name of the protected area is the Yangnoupokpi Lokchao Wildlife Sanctuary and the impact is same as mentioned above
 (iv). Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion : Yes
  Details and comments on the impact of Project on such areas : Passes through the Yangnoupokpi Lokchao Wildlife Sanctuary and impact would be same as mentioned above
 (v). Whether any rare/endangered/unique species of flora and fauna found in the area : Yes
9. Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
 (i). Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area : No
10. Comment as to the reasonability of the extent of the forest land proposed for diversion
 (i). Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project : Yes
11. Details of violation(s), if any ,committed
 (i). Whether any work in violation of the Act or guidelines issued under the Act has been carried out : No
12. Whether work in violation is still in progres(Yes/No) : NIL
13. Details of compensatory afforestation scheme
Patch wise details for Degraded Area (To be earmarked by DFO)
(i). Total Financial Outlay for C.A(lacs): 395
Patch Wise Details
S.no Patch No.Area(ha.)Name of PF/RFRangeCompartment NoUploaded KML file of patch
1144Kangbung RFChakpikarong Range12    View file
2344Gamphajol BlockMorch Range1    View file
3443Charangching blockChandel Range34    View file
4243Tonglang BlockTengnoupal Raitge2    View file
5549Yangoupokpi SanctuaryMorch RangeNear the River    View file
(ii). Copy of CA scheme details: (iii). Scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station: (iv). Copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A.:
 (V). Copy of NOC from Competent Authority :

Additional information Details
S. No. DocumentsRemarks
1 site inspection report of the Deputy Conservator of Forests

14. District Profile
S.no District NameGeographical area of the district (in ha.)Forest area of the district (in ha.)Total forest area diverted since 1980 (in ha.)No. of Approved CasesForest Land including penal C.A. (in ha.)Progress of compensatory afforestation as on(date)A) Forest land (in ha.)B) Non-forest land (in ha.)
1Chandel33130028070034.5427019/01/2016700
15. Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division NameCircleSite inspected ByWhether site inspectedNo. of times site visited Site inspection reportDate of visit
Tengnoupal Forest Division, ChandelEastern Forest CircleDFOYesOne15/01/2016
 Eastern Forest CircleCFYesOne19/01/2016
 Nodal OfficerNoNo Data
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16. Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
DivisionCircleRecommendation ByRecommendationReasonLetter Whether CF agreed
Tengnoupal Forest Division, ChandelEastern Forest CircleDFO RecommendedThe diversion being linear in nature, might not impact significantly in the ecology of the forests. On the other hand, the project will provide basic electricity needs to the people of Moreh township.
Eastern Forest CircleCF Recommendedas the project is for improvement of basic amenities of the people-power supply, it is Recommended.Yes
Nodal Officer RecommendedThe project proposal being a public utility project causing less disturbance to Forest & Environment is recommended.
quetiapin ritalin quetiapin und valdoxan quetiapin wirkstoff
Specific recommendation of the State Government(Part V)
17. Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
StateRecommendation ByRecommendationRecommendation DateRemarksSigning AuthorityNotificationRecommendation Letter
ManipurState SecretaryRecommended10/02/2016 State Govt. OfficerNo Data
17. Stage-I Clearance Report
Regional OfficeRecommendation ByMoEF File No.Date of Stage-I ClearanceClearance Letter
ShillongRegional Office3.MN C 007/2016-SHI30/09/2016
23. Stage-II Clearance Details
Proposal No.Date of Stage-II ClearanceProposal StatusClearance Letter
FP/MN/TRANS/17453/2016Approved In-PrincipleNo Data