PART-II
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal : JH-022/2018
1. Location of the project/Scheme : Jharkhand
 (i) State / Union Territory : Jharkhand  (ii) District : Deoghar  (iii) Forest Division : Deoghar  (iv) Area of forest land proposed for diversion (in ha.) : 19.46863  (v)

Category of the Proposal: Transmission Line
2. Legal status of forest land proposed for diversion
S. No. DivisionForest Land(ha.)Legal Status
1Deoghar8.96559Protected Forest
2Deoghar10.50304jungle-jhari land
Total 19.46863
Division 1. : Deoghar
3. District wise area to be diverted in the division
S. No. DistrictArea(ha.)
1Deoghar19.46863
Total19.46863
4. Details of Vegetation available in the forest land proposed for diversion
 (i) Density of vegetation
S. No. Area(in ha.)Density Eco-Class
119.468630.4Eco 3
Total. 19.46863


(ii) Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No. Scientific Name Local Name (0-30)cm. (31-60)cm. (61-90)cm. (91-120)cm. (121-150)cm. (>150)cm.
1Butea MonospermaPalash0675017160
2Mangifera IndicaMango021250
3Shorea RobustaSaal002100
4Azadirachta IndicaNeem054100
5Terminalia CatappaGamhar040000
6Albezzia LabbeckSirish0133000
7Dalburgia SisooShisam01512000
8Syzigium CuminiJamun087230
9OthersBamboo1100000
10OthersPalm0007240
11Madhuka IndicaMahua0015150
12Artocarpus HeterophyllusJackfruit011000
Total 11 11581 3563 0
Sub Total (No of Trees.) 305


5. Working plan prescription for the forest land proposed for diversion : NIL
6. Brief note on vulnerability of the forest area to erosion : The Proposed area is prone to erosion.
7. Approximate distance of the proposed site for diversion from boundary of forest(in km.) : 0
8. Significance of the forest land proposed for diversion from wildlife point of view
 (i). Details of wildlife present in and around the forest land proposed for diversion : 1. Macaca fascicularis 2. Erethizon dorsaum 3. Susu scrofa 4. Naza naza 5. Python molurus 6.Felis chaus 7. Lepus areticus 8. Funambulus palmarum 9. Acridotheres tristis 10. Crocuta crocuta
 (ii). Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. : No
 (iii). Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ): No
 (iv). Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion : No
 (v). Whether any rare/endangered/unique species of flora and fauna found in the area : No
9. Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
 (i). Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area : No
10. Comment as to the reasonability of the extent of the forest land proposed for diversion
 (i). Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project : Yes
11. Details of violation(s), if any ,committed
 (i). Whether any work in violation of the Act or guidelines issued under the Act has been carried out : Yes
  (a)Details of violation(s): All the transmission towers have already been laid
   (b) Period of Work done(year) : 1
   (c) Area of forest land involved in violation (in ha.) : 19.46863
S. No. Name of person responsible for violation Designation & Address of person responsible for violationAction taken against the person responsible for violation
1Sri Sanjeev Kumar BurnwalElectrical superintending Engineer Transmission circle DeogharThe violation has been reported to the Conservator of forest territorial circle Deoghar and District level Three Member Committee
12. Whether work in violation is still in progres(Yes/No) : No
13. Details of compensatory afforestation scheme
Patch wise details for Degraded Area (To be earmarked by DFO)
(i). Total Financial Outlay for C.A(lacs): 6658331
Patch Wise Details
S.no Patch No.Area(ha.)Name of PF/RFRangeCompartment NoUploaded KML file of patch
1138.94Bishanpur urf BabudihDeoghar Territorial599, 607    View file
(ii). Copy of CA scheme details: (iii). Scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station: (iv). Copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A.:
 (V). Copy of NOC from Competent Authority :

Additional information Details
S. No. DocumentsRemarks
1 CA land mouza map
2 CA land details
3 Tree Enumeration List
4 Details of flora and fauna
5 FRA from DC Deoghar

14. District Profile
S.no District NameGeographical area of the district (in ha.)Forest area of the district (in ha.)Total forest area diverted since 1980 (in ha.)No. of Approved CasesForest Land including penal C.A. (in ha.)Progress of compensatory afforestation as on(date)A) Forest land (in ha.)B) Non-forest land (in ha.)
1Deoghar24285923906841.84111240.51401/10/2018978.32307.728
15. Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division NameCircleSite inspected ByWhether site inspectedNo. of times site visited Site inspection reportDate of visit
DeogharDeogharDFOYesOne29/09/2018
 DeogharCFNoNo Data
 Nodal OfficerNoNo Data
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16. Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
DivisionCircleRecommendation ByRecommendationReasonLetter Whether CF agreed
DeogharDeogharDFO RecommendedJharkhand is having acute shortage of electricity production. Hence this proposal may be accepted in the vide interest of this power deficient State.
DeogharCF Recommended As per the Site inspection report and recommendation of DFO, Deoghar, there is gross violation of Forest Conservation Act, 1980 by the User Agency. The User Agency has erected all Transmission Towers and Connected with wire conductors covering total area of 19.46864 ha. which is the proposed area. Divisionl Forest Officer has been directed to take necessary action against the User Agency as well as the delinquent staff. There is no any option left before me to agree with the recommendation of D.F.O. and to accept the proposal and recommend it because the work has already been executed by the User Agency. In the background of facts and circumstances mention in the above, In the interest of Jharkhand State, this proposal is recommended for its Forest Clearance with strict provisions of Penal CA & Penal NPV or any other provisions/conditions as the Government may deem fit. Yes
Nodal Officer RecommendedRecommended
Specific recommendation of the State Government(Part V)
17. Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
StateRecommendation ByRecommendationRecommendation DateRemarksSigning AuthorityNotificationRecommendation Letter
JharkhandState SecretaryRecommended14/03/2019 State Govt. OfficerNo Data
17. Stage-I Clearance Report
Regional OfficeRecommendation ByMoEF File No.Date of Stage-I ClearanceClearance Letter
RanchiRegional OfficeFP/JH/TRANS/30079/201703/05/2019
18. Payment made by User Agency
Proposal No.Application No.Total Amount (Rs.)Recieved Amount (Rs.)Transaction DateTransaction IDBank NameMode of PaymentDemmand Generated By User AgencyDemmand Verified By Nodal OfficerUploaded Demand Letter
FP/JH/TRANS/30079/2017TRANS30079201703621,784,560.0021,784,560.0019/06/2019SBINR52019061900025770Corporation BankNEFT/RTGS (Challan)16/06/201918/06/2019
FP/JH/TRANS/30079/2017TRANS30079201788227,275,001.0027,275,001.0002/07/2019SBINR52019070200059938Corporation BankNEFT/RTGS (Challan)29/06/201901/07/2019
19. Uploaded Status of Land to be transferred to Forest Department under FCA (Mutation Details) : No
20. Mutation Details Verified By Nodal Officer
Proposal No.Verified DateMutation LetterRemarks
FP/JH/TRANS/30079/201709 Jul 2019No DataVerified
21. Compliance Details Submitted by User Agency
Proposal No.Compliance Details submitted on(Date)Uploaded Letter
FP/JH/TRANS/30079/201709 Jul 2019
22. Compliance Details Verified by Nodal Officer
Proposal No.RemarksVerified DateUploaded Letter
FP/JH/TRANS/30079/2017Stage I compliance22 Nov 2022
23. Stage-II Clearance Details
Proposal No.Date of Stage-II ClearanceProposal StatusClearance Letter
FP/JH/TRANS/30079/201707 Feb 2023APPROVED