List of Proposals submitted Online by User Agencies (Proposals received on or after 15th July 2014)
Help
Using this report, you can view details of proposals (Received on or after 15th July 2014) . Click on Proposal no to view detail of FORM-A part I. Click on   to print
 
Proposal Year : Region :
State : Category :
Circle : Division :
Status of the Proposal : Whether EC required(Yes/No)? :
Enter value for Search :
Note :-All areas are in Hectares(ha.)
Sno.State NameProposal No.RO/Ministry File NumberProposal NameCategoryUser Agency NameArea (ha.)Proposal StatusProposal initially received at RO/HO(Date)Proposal Pending Since(Date)View Report on Allocation of Fresh forest land (Form-A) Part-IView Report (Part-II to Part-V and Stage-I Clearances) View TimeLine DetailsOther Related DocumentsWhether EC required (if so, status)?
1 Himachal Pradesh FP/HP/TRANS/37139/2018 FC/HPC/04/72/2022 Construction of 66/22KV,2x10MVA sub station HATKOTI along with 66KV single circuit line on D/C towers from Hatkoti to Samoli Transmission Line HPSEBL 5.7027 IN-PRINCIPLE
04-Jul-2022
09-Sep-2022



No
2 Himachal Pradesh FP/HP/ROAD/36919/2018 FC/HPC/06/69/2021 Diversion of Forest Land for Construction of Dumti - Nithal Thalch Road from 0.00 km to 8.24 km by CPWD under Kinnaur District of Himachal Pradesh Road ITBP 14.442 IN-PRINCIPLE
04-Dec-2021
18-Aug-2022



No
3 Himachal Pradesh FP/HP/RAIL/146861/2021 FC/HPC/07/14/2022 BHANUPALI-BILASPUR-BERI NEW RAIL LINE, PHASE-IV, FROM KM. 52.015 TO KM. 62.900 Railway RAIL VIKAS NIGAM LIMITED CHANDIGARH 12.04 IN-PRINCIPLE
09-Mar-2022
06-Aug-2022



No
4 Himachal Pradesh FP/HP/ROAD/36921/2018 FC/HPC/06/04/2022 Diversion of Forest Land for Construction of Namgia Dogri - Lukma I Road from 0.00 km to 31.43 km by CPWD under Kinnaur District of Himachal Pradesh Road ITBP 85.3903 IN-PRINCIPLE
07-Jan-2022
10-Jun-2022



No
5 Himachal Pradesh FP/HP/MIN/30477/2017 8C/HP/05/27/2021/FC sand,stone and bajri mining project by sh Tepender Singh Saini Mining MINING PROJECT BY SH TEPENDER SINGH SAINI 6.2255 Pending at ROHQ
06-Mar-2021
03-Jun-2022
Yes


Proposal Status: EC application yet to be submitted
6 Himachal Pradesh FP/HP/Others/42429/2019 8B/HP/09/28/2020/FC Construction of Judicial Court Complex in Mandi (H.P.) Others HIGH COURT OF HP 9.6 IN-PRINCIPLE
04-Mar-2020
13-Apr-2022
Yes


Proposal Status: EC application yet to be submitted
7 Himachal Pradesh FP/HP/ROAD/42899/2019 FC/HPC/06/30/2021 C/O shamshar to Panai km 0/0 to 9/390 Road HIMACHAL PRADESH PUBLIC WORK DEPARTMENT 5.31 IN-PRINCIPLE
24-Sep-2021
21-Jan-2022



No
8 Himachal Pradesh FP/HP/ROAD/41501/2019 8B/HP/06/76/2021 C/o Channi Bridge Elaka Mata to Jalsu Jot M/able Road K.M. 0/0 to 17/0 Road EXECUTIVE ENGINEER HPPWD BHARMOUR DIVISION 9.3355 IN-PRINCIPLE
18-Jun-2021
23-Dec-2021



No
9 Himachal Pradesh FP/HP/HYD/52179/2020 8B/HP/01/45/2021 HAIL HEP Hydel HPSEB 9.3408 IN-PRINCIPLE
22-Apr-2021
09-Dec-2021



No
10 Himachal Pradesh FP/HP/HYD/23837/2017 8B/HP/01/129/2019/FC SAI KOTHI-II HYDEL ELECTRIC PROJECT Hydel HPSEB 11.9813 IN-PRINCIPLE
19-Sep-2019
09-Dec-2021



No
11 Himachal Pradesh FP/HP/HYD/32280/2018 8B/HP/01/116/2019/FC Devi Kothi Hydel Electric Project hpsebl Tissa Hydel HPSEB 9.739 IN-PRINCIPLE
06-Sep-2019
08-Dec-2021



No
12 Himachal Pradesh FP/HP/ROAD/8164/2014 8B/HP/06/56/2017/FC C/O road From Dummi to Kharechi 0/00 to 10/165 Road HIMACHAL PRADESH PUBLIC WORK DEPARTMENT 5.6581 IN-PRINCIPLE
18-May-2017
12-Apr-2021



No
13 Himachal Pradesh FP/HP/ROAD/45519/2020 8B/HP/06/96/2020/FC C/o Kiani Bagori Shakti Dehra Tikri Hamal Side 0/00 to 10/500 Road HPPWD 5.48 IN-PRINCIPLE
30-Oct-2020
08-Apr-2021



No
14 Himachal Pradesh FP/HP/ROAD/18277/2016 8B/HP/06/146/2019/FC C/O Bagsiad,Rahidhar,Kathyali,Dharwar,Dhanshal road Road PUBLIC WORK DEPARTMENT 5.5363 IN-PRINCIPLE
25-Nov-2019
04-Feb-2021



No
15 Himachal Pradesh FP/HP/ROAD/36476/2018 8B/HP/06/54/2020/FC CONSTRUCTION OF MUD ROAD (Attargoo Sangam Mudh Bhawa road) Road HIMACHAL PRADESH PUBLIC WORK DEPARTMENT 15.94 IN-PRINCIPLE
23-Jun-2020
19-Oct-2020



No
16 Himachal Pradesh FP/HP/ROAD/28594/2017 8B/HP/06/106/2019/FC C/o Shanad Shrikot Raod Road HIMACHAL PRADESH PUBLIC WORK DEPARTMENT 5.18 IN-PRINCIPLE
25-Jul-2019
24-Feb-2020



No
17 Himachal Pradesh FP/HP/Others/31571/2018 8B/HP/09/60/2018/FC Himani Chamunda Passenger Ropeway Project. Others DEPARTMENT OF TOURISM & CIVIL AVIATION, HIMACHAL PRADESH 8.0598 IN-PRINCIPLE
23-Aug-2018
04-May-2019
Yes


Proposal Status: EC application yet to be submitted
18 Himachal Pradesh FP/HP/HYD/13963/2015 8B/HP/01/39/2017/FC 14 MW UHL S.H.E.P. Hydel PURI OIL MILLS LIMITED 12.4332 IN-PRINCIPLE
30-Mar-2017
16-Oct-2018



No
19 Himachal Pradesh FP/HP/ROAD/17709/2016 8B/HP/06/59/2017/FC C/O link road from Daand to Bhasua Road HIMACHAL PRADESH PUBLIC WORK DEPARTMENT 5.96 IN-PRINCIPLE
18-May-2017
16-Dec-2017



No
20 Himachal Pradesh FP/HP/ROAD/11163/2015 8B/HPB/06/63/2016 C/o Bag - Kayalu Road Road HIMACHAL PRADESH PUBLIC WORK DEPARTMENT 6.6997 IN-PRINCIPLE
27-Sep-2016
30-Nov-2016



No
21 Himachal Pradesh FP/HP/TRANS/8960/2014 8B/HPB/04/60/2015 132KV D/C Transmission Line from Tangnu-Romai HEP to 66/132/220KV P.S. Sunda(Chirgaon) Transmission Line HIMACHAL PRADESH POWER TRANSMISSION CORPORATION LIMITED 14.551 IN-PRINCIPLE
21-Aug-2015
16-Jun-2016



No
22 Himachal Pradesh FP/HP/TRANS/9312/2015 8B/HPB/02/39/2015 Tangnu Romai-II HEP (6MW) Transmission Line TANGNU ROMAI POWER GENERATION PRIVATE LIMITED 22.6664 IN-PRINCIPLE
30-May-2015
30-Jul-2015



No