Ministry of Environment,Forest and Climate Change
Government of India
Orissa
State Forest Department
List of Proposals accorded Stage-I Clearance (Proposals received on or after 15th July 2014)
Help
Using this report, you can view details of proposals (Received on or after 15th July 2014) . Click on Proposal no to view detail of FORM-A part I. Click on   to print
 
Proposal Year : Region :
State : Category :
Circle : Division :
Status of the Proposal : Whether EC required(Yes/No)? : Decided at level :
Enter value for Search :
Note :-All areas are in Hectares(ha.)
Sno.State NameProposal No.RO/Ministry File NumberProposal NameCategoryUser Agency NameArea (ha.)Proposal StatusDate of Stage-IView Report on Allocation of Fresh forest land (Form-A) Part-IView Report (Part-II to Part-V and Stage-I Clearances) View TimeLine DetailsSite Inspection ReportOther Related DocumentsWhether EC required (if so, status)?
1 Orissa FP/OR/TRANS/8680/2014 5-ORC312/2017-BHU 220 Kv Line Diversion from Loc-59 to 75 Transmission Line OPTCL 7.102 IN-PRINCIPLE
29-May-2017



No
2 Orissa FP/OR/ROAD/9123/2015 5-ORA293/2016-BHU Cuttack-Angul Section of NH 42(New 55) Road NATIONAL HIGHWAYS AUTHORITY OF INDIA PIU SAMBALPUR 66.783 IN-PRINCIPLE
23-Feb-2017
Yes

EC File No.: F.No.10-76/2011-IA-III
Proposal Status: EC Granted
3 Orissa FP/OR/TRANS/40463/2019 5-ORB403/2019-BHU “Diversion of 400KV D/C Talcher – Meramundli Transmission Line” of PGCIL at Village Kamalang in Dhenkanal district, Odisha. Transmission Line POWERGRID KANHIA 0.378 IN-PRINCIPLE
16-Jan-2020



No
4 Orissa FP/OR/ROAD/17550/2016 5-ORA313/2017-BHU REHABILITATION AND UPGRADATION OF NH-6 PACKAGE-1 BAHARGORA TO SINGARA (KM 199.200 TO KM 310.806) SECTION OF NH-6 IN THE STATE OF ORISSA Road NATIONAL HIGHWAY AUTHORITY OF INDIA PIU BALASORE 85.104 IN-PRINCIPLE
12-Sep-2017



No
5 Orissa FP/OR/TRANS/25459/2017 5-ORC391/2019-BHU 132/33 KV LILO Transmission Line by OPTCL Transmission Line ODISHA POWER TRANSMISSION CORPORATION LIMITED 14.019 IN-PRINCIPLE
11-Dec-2019



No
6 Orissa FP/OR/ROAD/17857/2016 5-ORA310/2017-BHU 4-laning of Teleibani Sambalpur Section of NH-6 (Km.493.300 to Km.518.800 and Km.545.176 to Km.567.400) Road NATIONAL HIGHWAYS AUTHORITY OF INDIA PIU SAMBALPUR 54.214 IN-PRINCIPLE
24-May-2017



No
7 Orissa FP/OR/ROAD/17857/2016 5-ORA310/2017-BHU 4-laning of Teleibani Sambalpur Section of NH-6 (Km.493.300 to Km.518.800 and Km.545.176 to Km.567.400) Road NATIONAL HIGHWAYS AUTHORITY OF INDIA PIU SAMBALPUR 54.214 IN-PRINCIPLE
24-May-2017



No
8 Orissa FP/OR/Others/12382/2015 5-ORB351/2018-BHU Forest Diversion Proposal for Conveyor Corridor from Khondbond Iron Ore Mine to Railway Siding of Joda East Iron Ore Mine by M/s Tata Steel Ltd. Others TATA STEEL LIMITED KHONDBOND IRON AND MN MINES 4.68 IN-PRINCIPLE
17-Sep-2018



EC File NA
9 Orissa FP/OR/Others/32590/2018 5-ORB399/2019-BHU Installation of pipeline over a length 4.748 km for drawal of water from river Mahanadi to Boudh Distillery in Odisha Others BOUDH DISTILLERY PVT LTD 0.966 IN-PRINCIPLE
04-Dec-2019



No
10 Orissa FP/OR/IND/12823/2015 5-ORB228/2015-BHU Surendra Mining Industries (P) Ltd, Barhamusa. Industry SURENDRA MINING INDUSTRIES PRIVATE LIMITED 0.797 IN-PRINCIPLE
08-Jul-2015
Yes

EC File No.: J-11011/728/2008-IA.II(I)
Proposal Status: EC Granted
11 Orissa FP/OR/IRRIG/13439/2015 5-ORC304 Jeera Irrigation Project Irrigation PADAMPUR INVESTIGATION DIVISION,PADAMPUR 5.391 IN-PRINCIPLE
04-Aug-2017
Yes


Proposal Status: EC under process
12 Orissa FP/OR/ROAD/20160/2016 5-ORC358/2018-BHU Widening & strengthening to NH-220 from km 35/700 to 71/120 km (Rairangpur - Jashipur section Road EXECUTIVE ENGINEER NHDIVISION BARIPADA 7.8199 IN-PRINCIPLE
18-Jul-2018



No
13 Orissa FP/OR/TRANS/15421/2015 5-ORB368/2018-BHU Proposal for diversion of 3.665 Ha. forests lands under Keonjhar forest division for non-forest purpose for construction of 33 kV DC Transmission line from MRSS, Joda to Khondbond Transmission Line TATA STEEL LIMITED KHONDBOND IRON AND MN MINES 3.665 IN-PRINCIPLE
28-Jan-2019



No
14 Orissa FP/OR/ROAD/15279/2015 5-ORA340/2018-BHU Rehabilitation and Upgrading of the Existing Road to 2/4- lane with paved shoulders configuration from Birmitrapur to Barkote Section of NH-23 (Ch 211.200 to Ch.337.197 Road NATIONAL HIGHWAYS AUTHORITY OF INDIA PIU SAMBALPUR 135.216 IN-PRINCIPLE
04-May-2018



EC File NA
15 Orissa FP/OR/TRANS/20956/2016 5-ORC314/2017-BHU 400kV D/C OPGC-Jharsuguda(Sundargarh) Transmission Line Transmission Line ODISHA GENERATION PHASE II TRANSMISSION LIMITED 30.134 IN-PRINCIPLE
24-May-2017



No
16 Orissa FP/OR/TRANS/20956/2016 5-ORC314/2017-BHU 400kV D/C OPGC-Jharsuguda(Sundargarh) Transmission Line Transmission Line ODISHA GENERATION PHASE II TRANSMISSION LIMITED 30.134 IN-PRINCIPLE
24-May-2017



No
17 Orissa FP/OR/ROAD/17128/2015 5-ORB317/2017-BHU Rehabilitation & Upgradation of NH-149 from Pallahara to Pitri Section (Pallahara Bypass road) Road NH DIVISION PALLAHARA 4.546 IN-PRINCIPLE
13-Mar-2018



No
18 Orissa FP/OR/RAIL/29907/2017 5-ORA374/2019-BHU Khurda Road Bolangir New B.G. Raillink Project Phase-II i.e. from 238-289 Railway EAST COAST RAILWAY 69.77 IN-PRINCIPLE
22-Feb-2019



No
19 Orissa FP/OR/IND/36821/2018 5-ORC32/2019-BHU IDCO has allotted 279 Acres of land to M/s Shyam Metalics & Energy Ltd. for establishment of Industry in the village-Pandloi and Nishanbhnaga of Rengali-Tahsil ,District-Sambalpur for establishment o Industry IDCO 8.361 IN-PRINCIPLE
23-Dec-2019



No
20 Orissa FP/OR/THE/29588/2017 5-ORC383/2019-BHU 3x800 MW Super Critical Thermal Power Plant at Kamakhyanagar Tahasil in Dhenkanal District Thermal ODISHA THERMAL POWER CORPORATION LTD (OTPCL) 38.098 IN-PRINCIPLE
07-Jun-2019
Yes


Proposal Status: EC application yet to be submitted
21 Orissa FP/OR/Pipeline/36091/2018 5-ORB387/2019-BHU Joda to Paradeep Iron Ore Slurry Pipelines System [Alignment under Non-RoW]of M/s JSW Utkal Steel Ltd. Pipeline JSW UTKAL STEEL LIMITED 0.654 IN-PRINCIPLE
12-Jul-2019



No
22 Orissa FP/OR/Pipeline/36091/2018 5-ORB387/2019-BHU Joda to Paradeep Iron Ore Slurry Pipelines System [Alignment under Non-RoW]of M/s JSW Utkal Steel Ltd. Pipeline JSW UTKAL STEEL LIMITED 0.654 IN-PRINCIPLE
12-Jul-2019



No
23 Orissa FP/OR/Others/32129/2018 5-ORB397/2019-BHU Setting up a new Oil Depot of BPCL Others BHARAT PETROLEUM CORP LTD SADASHIBPUR 2.091 IN-PRINCIPLE
25-Nov-2019
Yes


Proposal Status: EC application yet to be submitted
24 Orissa FP/OR/IRRIG/12731/2015 5-ORC307/2017-BHU Sono Barrage Project Irrigation MAYURBHANJ INVESTIGATION DIVISION DEPARTMENT OF WATER RESOURCES ODISHA 14.928 IN-PRINCIPLE
04-Aug-2017
Yes
Proposal No.:
EC File No.:
Proposal Status: No Proposal no.
25 Orissa FP/OR/TRANS/21714/2016 5-ORA334/2018-BHU 765 KV D/C JHARSUGUDA (SUNDARGARH) – RAIPUR POOL TRANSMISSION LINE Transmission Line ODISHA GENERATION PHASE II TRANSMISSION LIMITED 94.656 IN-PRINCIPLE
06-Mar-2018



No
26 Orissa FP/OR/RAIL/26003/2017 5-ORB396/2019-BHU ESTABLISHMENT OF RAILWAY SIDING IN VILLAGE JALPAPOSHI , NAYAGARH KEONJHAR BY BHUSHAN STEEL LIMITED Railway BHUSHAN STEEL LIMITED 3.869 IN-PRINCIPLE
27-Nov-2019
Yes


Proposal Status: EC application yet to be submitted
27 Orissa FP/OR/IRRIG/15278/2015 5-ORC308/2017-BHU Ranjore Irrigation Project Irrigation PADAMPUR INVESTIGATION DIVISION,PADAMPUR 7.054 IN-PRINCIPLE
01-Dec-2017
Yes
Proposal No.:
EC File No.:
Proposal Status: No Proposal no.
28 Orissa FP/OR/THE/13286/2015 5-ORC278/2016-BHU ORISSA INTEGRATED POWER LIMITED Thermal ORISSA INTEGRATED POWER LIMITED 17.02 IN-PRINCIPLE
27-Jun-2016
Yes


Proposal Status: EC under process
29 Orissa FP/OR/ROAD/25629/2017 5-ORC344/2018-BHU Balasore-Baripada-Jharpokharia Section of NH-5 Road NATIONAL HIGHWAY AUTHORITY OF INDIA PIU BALASORE 13.856 IN-PRINCIPLE
27-Apr-2018



No
30 Orissa FP/OR/ROAD/7575/2014 5-ORC259/2015-BHU Bankibahal to kanika Railway siding Road Road EXECUTIVE ENGINEER 39.98 IN-PRINCIPLE
14-Oct-2015



No
31 Orissa FP/OR/IRRIG/13364/2015 5-ORC303/2017-BHU Aherajore Irrigation Project Irrigation EXECUTIVE ENGINEER, IB INVESTIGATION DIVISION 14.53 IN-PRINCIPLE
04-Aug-2017
Yes


Proposal Status: EC application yet to be submitted
32 Orissa FP/OR/ROAD/35088/2018 5-ORC373/2019-BHU Construction of 200 Feet (60 Mts) Master plan road from Rail Vihar- Hatiasuni- Ekamrakanan Park over a stretch of 1.790 Km by Executive Engineer (R&B) Division (No-III), Bhubaneswar and under Tahsil : Bhubaneswar of Khordha District. Odisha Road EXECUTIVE ENGINEER, BBSR (R&B) DIVISION NO.III. BHUBANESWAR 10.183 IN-PRINCIPLE
29-Mar-2019



No
33 Orissa FP/OR/IRRIG/12758/2015 5-ORC292/2016-BHU SANDUL IRRIGATION PROJECT Irrigation KALAHANDI INVESTIGATION DIVISION 7.535 IN-PRINCIPLE
18-Nov-2016
Yes

EC File No.: 2007
Proposal Status: EC Granted
34 Orissa FP/OR/THE/12401/2015 5-ORB327/2017-BHU Proposal for diversion of 2.337 acre of forest land for construction of intake water pump house at Samal, Talcher, Odisha for the proposed expansion of Talcher Thermal Power Station (2X660MW). Thermal CHITTARANJAN BARIK 0.95 IN-PRINCIPLE
12-Jun-2018



No
35 Orissa FP/OR/Others/14546/2015 5-ORC322/2017-BHU Infrastructure Project for Kurmitar & Rantha ML Others ODISHA MINING CORPORATION LTD 11.912 IN-PRINCIPLE
29-Nov-2018



EC File NA
36 Orissa FP/OR/RAIL/33802/2018 5-ORB408/2020-BHU Propasal for diversion of 4.232ha of forest land for construction of Nirgundi- Bhadrak 3rd line Railway Project, Phase-I(0-14km) Railway EAST COAST RAILWAY JJKR 4.232 IN-PRINCIPLE
20-Feb-2020



No
37 Orissa FP/OR/RAIL/23845/2017 5-ORA386/2019-BHU Proposal for diversion of 244.623 ha of forest land for Talcher-Bimlagarh New B.G. Rail link Project, Phase-II(Chainage 25.00km to 153.90km) Railway EAST COAST RAILWAY 244.623 IN-PRINCIPLE
01-Jul-2019



No
38 Orissa FP/OR/RAIL/23845/2017 5-ORA386/2019-BHU Proposal for diversion of 244.623 ha of forest land for Talcher-Bimlagarh New B.G. Rail link Project, Phase-II(Chainage 25.00km to 153.90km) Railway EAST COAST RAILWAY 244.623 IN-PRINCIPLE
01-Jul-2019



No
39 Orissa FP/OR/ROAD/14688/2015 5-ORB273/2016-BHU Widening and strengthening of existing SL/IL to double lane Lane with paved shoulder from 140/900 to 162/01 km of NH-57 in Boudh District. Road NH DIVISION SAMBALPUR 3.544 IN-PRINCIPLE
26-Feb-2016



No
40 Orissa FP/OR/IND/36705/2018 5-ORC400/2019-BHU Iron Ore Grinding, De-Sliming (Beneficiation) Plant & Slurry Pumping Station and Water Intake System of M/s JSW Utkal Steel Ltd., Barbil Tahasil, Keonjhar District Industry JSW UTKAL STEEL LIMITED 22.671 IN-PRINCIPLE
23-Dec-2019
Yes
Proposal No.: IA/OR/IND/74415/2018
EC File No.: IA-J-11011/271/2018-IA-II(I)
Proposal Status: TOR GRANTED
41 Orissa FP/OR/ROAD/31840/2018 5-ORC350/2018-BHU Construction of 200 feet master plan road from Rail Vihar to Ekamrakanan over a stretch of 1.930 KM under Executive Engineer (R&B) Division (No-III), bhubaneswar and under Tahasil: Bhubaneswar of Khurdha District. Road EXECUTIVE ENGINEER, BBSR (R&B) DIVISION NO.III. BHUBANESWAR 10.501 IN-PRINCIPLE
18-Jul-2018



No
42 Orissa FP/OR/IRRIG/22787/2016 5-ORC345/2018-BHU For Construction of Additional Spillway of Hirakud Dam Project, Burla Irrigation EXECUTIVE ENGGINEER MAIN DAM DIVISION BURLA 9.441 IN-PRINCIPLE
01-May-2018



No
43 Orissa FP/OR/RAIL/30199/2017 5-ORC348/2018-BHU Establishment of Industries i.e.Establishment of Railway line & Siding under Danagadi Tahasil in Jajpur District of M/s Emami Cement Ltd. Railway IDCO 8.114 IN-PRINCIPLE
18-Jun-2018



No
44 Orissa FP/OR/ROAD/23286/2016 5-ORC332/2017-BHU Widening to two lane carriage way from 327/700 to 413/700km of NH-326 (erstwhile form 16/0 to 102/000 of SH-25) under Vijayawada – Ranchi corridor with state Koraput & Malkangiri district in the state of Odisha Road EXECUTIVE ENGINEER, NH DIVISION, JEYPORE 10.635 IN-PRINCIPLE
05-Mar-2018



No
45 Orissa FP/OR/ROAD/24576/2017 5-ORA357/2018-BHU Rehabilitation and upgradation to two/four laning of Talchar-Dubari-Chandikhole section of NH-200 in Odisha Road National Highways Authority of India 176.231 IN-PRINCIPLE
05-Dec-2018



EC File NA
46 Orissa FP/OR/Others/37517/2018 5-ORC395/2019-BHU Jagdishpur-Haldia-Bokaro-Dhamra Pipeline (JHBDPL), Odisha Project of GAIL Permanent land acquisition Others GAIL INDIA LIMITED 0.9712 IN-PRINCIPLE
04-Oct-2019



No
47 Orissa FP/OR/TRANS/26634/2017 5-ORB353/2018-BHU Odisha Power Transmission Corporation Ltd Transmission Line E.H.T. (C) DIVISION OPTCL ANUGUL 3.94 IN-PRINCIPLE
18-Jul-2018



No
48 Orissa FP/OR/ROAD/18943/2016 5-ORA346/2018-BHU 4- laning of Singara - Brinjabahal Section of NH-6 (Km. 310.806 to km 414.982) Road National Highways Authority of India 111.407 IN-PRINCIPLE
12-Jul-2018



No
49 Orissa FP/OR/ROAD/18943/2016 5-ORA346/2018-BHU 4- laning of Singara - Brinjabahal Section of NH-6 (Km. 310.806 to km 414.982) Road National Highways Authority of India 111.407 IN-PRINCIPLE
12-Jul-2018



No
50 Orissa FP/OR/TRANS/17794/2016 5-ORC306/2017-BHU 400 KV D/C tarnsmission line from LILO point to PGCIL Sundargarh Pooling Station by M/s Vedanta Ltd. Transmission Line VEDANTA LIMITED 6 IN-PRINCIPLE
28-Feb-2017



No
12
Please wait ...