Ministry of Environment,Forest and Climate Change
Government of India
Uttarakhand
State Forest Department
List of Proposals accorded Stage-II Clearance (Proposals received on or after 15th July 2014)
Help
Using this report, you can view details of proposals (Received on or after 15th July 2014) .Click on   to print
 
Proposal Year :
Region : State :
Category : Status of the Proposal :
Enter value for Search :
Note :-All areas are in Hectares(ha.)
Sno.State NameProposal No.RO/Ministry File NumberProposal NameCategoryUser Agency NameArea (ha.)Proposal StatusImportant DatesAllocation of Fresh forest land (Form-A) Part-IView Report (Part-II to Part-V and Stage-I Clearances)Stage-II Approval on
1 Uttarakhand FP/UK/ROAD/11345/2015 8B/UCP/06/275/2015/FC This road is starts from Km 5 of Ratangarh-Bhandaga-Kuniyali of PMGSY and connect Village Rahadr, Bhadanga, Kuniyali etc in 5.15 Km total area for dirversion is 2.3975 Ha Road PUBLIC WORK DEPARTMENT 2.3975 IN-PRINCIPLE
Proposal received(at Nodal Officer)electronically on : 31 Mar 2015
Stage-I Approval on : 21 Feb 2018
Compliance Report Submitted by User Agency on : 05 Sep 2019
2 Uttarakhand FP/UK/ROAD/9801/2015 8B/UCP/06/17/2015/FC This road is started from Km 26 of Nagrasu-Dhanpur-Dandakhal Motor and end point of Jasoli Kanda Motor road and connect village Bhunka total area for dirversion is 2.7825 Road PUBLIC WORK DEPARTMENT 2.7825 IN-PRINCIPLE
Proposal received(at Nodal Officer)electronically on : 31 Jan 2015
Stage-I Approval on : 21 Jul 2017
Compliance Report Submitted by User Agency on : 09 May 2019
3 Uttarakhand FP/UK/ROAD/8985/2014 8B/UCP/06/12/2015 Construction of Didihat(Devichona) to Jamtari M/R (Length- 10.525 Km.). Road PUBLIC WORK DEPARTMENT 8.1123 IN-PRINCIPLE
Proposal received(at Nodal Officer)electronically on : 31 Dec 2014
Stage-I Approval on : 31 Mar 2016
Compliance Report Submitted by User Agency on : 27 Dec 2018
4 Uttarakhand FP/UK/ROAD/8961/2014 8B/UCP/06/122/2015/FC Forest Land Transfer for Padair Gaon to Pairi Motor Road under PMGSY serving padairgaon, boora, ala, jokhana, geri, sik, pairi with a total population of 2723. Road PMGSY 10.71 IN-PRINCIPLE
Proposal received(at Nodal Officer)electronically on : 31 Dec 2014
Stage-I Approval on : 27 Aug 2018
Compliance Report Submitted by User Agency on : 07 May 2019
5 Uttarakhand FP/UK/ROAD/7789/2014 8B/UCP/06/31/2015 Length-8.050KM Road PUBLIC WORK DEPARTMENT 6.79 IN-PRINCIPLE
Proposal received(at Nodal Officer)electronically on : 31 Dec 2014
Stage-I Approval on : 23 Mar 2016
Compliance Report Submitted by User Agency on : 14 May 2019
6 Uttarakhand FP/UK/ROAD/16302/2015 8B/UCP/06/256/2016/FC This Road will connect the remote village Nivattar having a population of 120 which will provide convenience and connectivity to villagers with tehsil and block headquarter. Road EECDPWDUKM 0.755 IN-PRINCIPLE
Proposal received(at Nodal Officer)electronically on : 30 Oct 2015
Stage-I Approval on : 16 Oct 2017
Compliance Report Submitted by User Agency on : 17 Jun 2019
7 Uttarakhand FP/UK/ROAD/13621/2015 8B/UCP/06/148/2016/FC c/o Adichaura to Sinni M/Road Under PMGSY (13.00 km) Forest Land 20.70 hct. the Prominent point of target habitation Namik sach as Primary School, Primary Health Center, Maternity and Child Welfare centers and Post Office will be connected by this road. Road PMGSY 10.35 IN-PRINCIPLE
Proposal received(at Nodal Officer)electronically on : 30 Jun 2015
Stage-I Approval on : 26 Sep 2017
Compliance Report Submitted by User Agency on : 07 May 2019
8 Uttarakhand FP/UK/ROAD/9770/2015 8B/UCP/06/23/2016/FC in this road there are three village connected by the road village karti,jali and ghansali at persent all three villags are not connected with the road. Due to the not connectivity of road villagers are migrate. in this villages no any other option of communication. if that road will be sancation th Road PWD LANSDOWNE 1.53 IN-PRINCIPLE
Proposal received(at Nodal Officer)electronically on : 30 Jan 2015
Stage-I Approval on : 26 Sep 2017
Compliance Report Submitted by User Agency on : 28 Aug 2019
9 Uttarakhand FP/UK/ROAD/7395/2014 1(30)/2015 Length-11KM Road PUBLIC WORK DEPARTMENT 4.935 IN-PRINCIPLE
Proposal received(at Nodal Officer)electronically on : 29 Sep 2014
Stage-I Approval on : 20 Mar 2015
Compliance Report Submitted by User Agency on : 28 Dec 2018
10 Uttarakhand FP/UK/ROAD/11370/2015 8b/UCP/09/178/2015 New construction of Road for connected Kothoyu & kwaralli villages. Road PMGSY 5.31 IN-PRINCIPLE
Proposal received(at Nodal Officer)electronically on : 29 Mar 2015
Stage-I Approval on : 15 Apr 2016
Compliance Report Submitted by User Agency on : 28 Sep 2018
11 Uttarakhand FP/UK/ROAD/18704/2016 8B/UCP/06/210/2016/FC This road connects Upla Basti Gyansu to Gyansu Sald motor road and Dharasu Gangotri National Highway no. 108, which gives direct connectivity to villagers. The road is being demanded by villagers for many years. This road will lead to economical and social development villagers. Road EXECUTIVE ENGINEER PD PWD UTTARKASHI 0.576 IN-PRINCIPLE
Proposal received(at Nodal Officer)electronically on : 28 Mar 2016
Stage-I Approval on : 08 Feb 2018
Compliance Report Submitted by User Agency on : 24 Apr 2019
12 Uttarakhand FP/UK/ROAD/10568/2015 8B/UCP/06/90/2015-FC construction of road Road PUBLIC WORK DEPARTMENT 1.925 IN-PRINCIPLE
Proposal received(at Nodal Officer)electronically on : 28 Feb 2015
Stage-I Approval on : 12 Oct 2015
Compliance Report Submitted by User Agency on : 17 Jan 2018
13 Uttarakhand FP/UK/ROAD/10549/2015 8B/UCP/06/181/2016/FC For Construction of above Motor Road 0.916 Ha. Civil Land is Required. After Construction of this Motor Road Villagers of Lwani & Besara Village. Road PUBLIC WORK DEPARTMENT 0.916 IN-PRINCIPLE
Proposal received(at Nodal Officer)electronically on : 28 Feb 2015
Stage-I Approval on : 03 Nov 2017
Compliance Report Submitted by User Agency on : 21 May 2019
14 Uttarakhand FP/UK/Others/31012/2017 8B/UCP/09/70/2018/FC The District Head quarter Gopaeshwar have approx Thirty thousand population.and there is no sewage treatment for that at three places the sewage treatment plant will be establish. These sewage plant there are require 0.290 Hect forest land Others CONSTRUCTION & MAINTENANCE UNIT (GANGA) 0.29 IN-PRINCIPLE
Proposal received(at Nodal Officer)electronically on : 28 Dec 2017
Stage-I Approval on : 14 Nov 2018
Compliance Report Submitted by User Agency on : 08 Mar 2019
15 Uttarakhand FP/UK/ROAD/7374/2014 1(57)/15 Construction of Sumeti To Bhaitari M/R, Length-7.00km Road PUBLIC WORK DEPARTMENT 3.809 IN-PRINCIPLE
Proposal received(at Nodal Officer)electronically on : 27 Sep 2014
Stage-I Approval on : 30 Mar 2015
Compliance Report Submitted by User Agency on : 28 Dec 2018
16 Uttarakhand FP/UK/ROAD/8938/2014 1(163)/2014 This road will provide connectivity to the villagers of remote areas. The people of the area will able to sell their agricultural product to main market and will be benefited in education, hospital facility. Road PUBLIC WORK DEPARTMENT 2.7825 IN-PRINCIPLE
Proposal received(at Nodal Officer)electronically on : 27 Dec 2014
Stage-I Approval on : 14 Jun 2016
Compliance Report Submitted by User Agency on : 15 Nov 2018
17 Uttarakhand FP/UK/TRANS/35101/2018 8B/UCP/04/07/2019/FC Construction of LILO of 132kV Chilla-Najibabad line at 132kV Substation, Padartha, Patanjali, Haridwar is necessary for strengthening of electricity supply system in Padartha & nearby Villages under Jwalapur Tehsil Block Bahadrabad. After energisation of this line & substation quality of electricit Transmission Line POWER TRANSMISSION CORPORATION OF UTTARAKHAND LIMITED 8.2377 IN-PRINCIPLE
Proposal received(at Nodal Officer)electronically on : 27 Aug 2018
Stage-I Approval on : 09 Aug 2019
Compliance Report Submitted by User Agency on : 21 Sep 2019
18 Uttarakhand FP/UK/ROAD/22594/2016 8B/UCP/06/108/2018/FC This road will provide connectivity to the village of bijori bhonti remote areas. The people of the area will able to sell their agricultural product to main market and will be benefited in education,hospital facility.etc Road PUBLIC WORK DEPARTMENT 2.758 IN-PRINCIPLE
Proposal received(at Nodal Officer)electronically on : 26 Nov 2016
Stage-I Approval on : 28 Dec 2018
Compliance Report Submitted by User Agency on : 18 Jun 2019
19 Uttarakhand FP/UK/ROAD/11303/2015 8B/UCP/06/111/2017/FC This object proposed for connect to gair gaon for road facilities and provide to conectivity of main market & stae higway. Road PMGSYID PUROLA 4.165 IN-PRINCIPLE
Proposal received(at Nodal Officer)electronically on : 26 Mar 2015
Stage-I Approval on : 25 Sep 2018
Compliance Report Submitted by User Agency on : 07 Sep 2019
20 Uttarakhand FP/UK/ROAD/10497/2015 8B/UCP/06/190/2015/FC The length of the road is 2 Km and it starts from Paiyatall goes to near Dhanoli village Road PUBLIC WORK DEPARTMENT 1.4 IN-PRINCIPLE
Proposal received(at Nodal Officer)electronically on : 26 Feb 2015
Stage-I Approval on : 05 Oct 2017
Compliance Report Submitted by User Agency on : 09 Sep 2019
21 Uttarakhand FP/UK/ROAD/8880/2014 1(94)/15 Chinyalisaur to Kot-Bagi motor Road from Km. 7.00 to Km. 10.00 till kot village this road provide the connectivity of road to 338 population of kot villagers Road PMGSY ID UTTARKASHI 0.262 IN-PRINCIPLE
Proposal received(at Nodal Officer)electronically on : 26 Dec 2014
Stage-I Approval on : 17 Apr 2015
Compliance Report Submitted by User Agency on : 02 Jul 2019
22 Uttarakhand FP/UK/ROAD/28731/2017 1(26)/2018 the road connects villages like Jineth, Panoth, Painther etc.the road is required by villagers and demanded from several years. Road EXECUTIVE ENGINEER PD PWD UTTARKASHI 0.874 IN-PRINCIPLE
Proposal received(at Nodal Officer)electronically on : 26 Aug 2017
Stage-I Approval on : 23 Feb 2018
Compliance Report Submitted by User Agency on : 20 Nov 2018
23 Uttarakhand FP/UK/ROAD/7355/2014 1(41)/2015 Bungachina to Kusail Motor Road under PMGSY Road PUBLIC WORK DEPARTMENT 4.984 IN-PRINCIPLE
Proposal received(at Nodal Officer)electronically on : 25 Sep 2014
Stage-I Approval on : 24 Mar 2015
Compliance Report Submitted by User Agency on : 28 Dec 2018
24 Uttarakhand FP/UK/ROAD/9620/2015 1(229)/2015 Construction of Hudoli to Bingadera Malla Motor Road under CM Ghosna No. 237/2013 Road PWD 1.03401 In-Principle
Proposal received(at Nodal Officer)electronically on : 25 Jan 2015
Stage-I Approval on : 01 Jul 2015
Compliance Report Submitted by User Agency on : 27 Nov 2018
25 Uttarakhand FP/UK/ROAD/7706/2014 1(140)/15 This Road will connect Bairat Beran to Baungad habitation which starts from Bairat and it ends at Baungad.The length of road is 4.040 Km,and passes through civil soyam forest and nap land in which 1.440 hectares of Civil soyam land is required. Road Vinod Kumar 1.44 IN-PRINCIPLE
Proposal received(at Nodal Officer)electronically on : 25 Dec 2014
Stage-I Approval on : 12 May 2015
Compliance Report Submitted by User Agency on : 03 May 2019
26 Uttarakhand FP/UK/ROAD/26717/2017 01(145)/2018 The proposed road for connectivity of Unconnected village Patakhal, Hadim, Gwana which total population 199 and road length is 3.600 km. Road PWD 0.7875 IN-PRINCIPLE
Proposal received(at Nodal Officer)electronically on : 24 Jun 2017
Stage-I Approval on : 09 Jan 2018
Compliance Report Submitted by User Agency on : 31 Jul 2019
27 Uttarakhand FP/UK/ROAD/26710/2017 1(132)/2017 The proposed road for connectivity of Unconnected village Padiyar gaon, Badon, Musan gaon and Jhirkoti which total population 72 and road length is 2.00 km. Road PWD 0.805 IN-PRINCIPLE
Proposal received(at Nodal Officer)electronically on : 24 Jun 2017
Stage-I Approval on : 25 Jan 2018
Compliance Report Submitted by User Agency on : 08 Jul 2019
28 Uttarakhand FP/UK/Others/27134/2017 8B/UCP/09/148/2018/FC Under Mussoorie sewerage scheme one no. of STP for Arcadia zone cap. 0.70 MLD has been proposed. Others UTTARAKHAND PAYJAL SANSADHAN VIKAS AVAM NIRMAN NIGAM 0.02 IN-PRINCIPLE
Proposal received(at Nodal Officer)electronically on : 24 Jul 2017
Stage-I Approval on : 30 Apr 2019
Compliance Report Submitted by User Agency on : 30 Jul 2019
29 Uttarakhand FP/UK/ROAD/13811/2015 8B/UCP/06/29/2016/FC For Construction of Kodwa Bend Devsthali Motor Road Total Area of Forest Land proposed for diversion is 0.649 Ha & Non Forest land is 0.066 Ha. Road PUBLIC WORK DEPARTMENT 0.649 IN-PRINCIPLE
Proposal received(at Nodal Officer)electronically on : 24 Jul 2015
Stage-I Approval on : 26 Oct 2017
Compliance Report Submitted by User Agency on : 21 May 2019
30 Uttarakhand FP/UK/ROAD/17679/2016 8B/UCP/06/176/2016/FC This Motor Road will connect two villages Barmwadi and Temariya having a total population of 512 which are not connected to any Road link till now. This Road Will also serve as a bypass between NH 107 (Rudraprayag-Gaurikund) and SH 37 (Mayali-Guptkashi)which will be an alternate route to travelers i Road EECDPWDUKM 1.451 IN-PRINCIPLE
Proposal received(at Nodal Officer)electronically on : 24 Jan 2016
Stage-I Approval on : 13 Feb 2018
Compliance Report Submitted by User Agency on : 08 Oct 2018
31 Uttarakhand FP/UK/ROAD/7245/2014 8B/UCP/06/26/2015-FC This Road will connect Brambachkuri habitation which starts from Chaubati and it ends at Barambachkuri.The length of road is 9.070 Km,and passes through civil soyam forest and nap land in which 5.409 hectares of Civil soyam land is required in this project. Road Vinod Kumar 5.409 IN-PRINCIPLE
Proposal received(at Nodal Officer)electronically on : 24 Dec 2014
Stage-I Approval on : 08 Mar 2016
Compliance Report Submitted by User Agency on : 03 May 2019
32 Uttarakhand FP/UK/ROAD/25766/2017 849/x-4-18(141)/2018 With the construction of this motor road, tourism and travel will be facilitated and employment opportunities for the youth will also be available. The development plans of the government also operate smoothly. this road construction connectivity by public facility school, Hospital & Mandi Dehradun Road PUBLIC WORKS DEPARTMENT 0.42 IN-PRINCIPLE
Proposal received(at Nodal Officer)electronically on : 24 Apr 2017
Stage-I Approval on : 28 Aug 2018
Compliance Report Submitted by User Agency on : 29 Jun 2019
33 Uttarakhand FP/UK/ROAD/30395/2017 01(60)/2018 Road is proposed from Km. 2 of Matiyali to Prachin Mandir Kalirow in 4.00 km length Gram Lweshal (Tok-ghatgad) will be directly benefited by motor road and Education, as well as Medicalfacilitywillbe enhance. Road EE CD NAINITAL 0.1125 IN-PRINCIPLE
Proposal received(at Nodal Officer)electronically on : 23 Nov 2017
Stage-I Approval on : 16 Mar 2018
Compliance Report Submitted by User Agency on : 07 May 2019
34 Uttarakhand FP/UK/ROAD/13453/2015 1(485)/2015 Construction of Nyay Pancayat Mukhyalya Ustoli Motor Road in District Chamoli. (Length 10.00 Km) Road PUBLIC WORKS DEPARTMENT 4.564 IN-PRINCIPLE
Proposal received(at Nodal Officer)electronically on : 23 Jun 2015
Stage-I Approval on : 30 Oct 2015
Compliance Report Submitted by User Agency on : 01 Jun 2019
35 Uttarakhand FP/UK/ROAD/9574/2015 1(114)/15 To provide the Road facility of village Paab of 408 population Road PMGSY ID UTTARKASHI 1.092 IN-PRINCIPLE
Proposal received(at Nodal Officer)electronically on : 23 Jan 2015
Stage-I Approval on : 02 May 2015
Compliance Report Submitted by User Agency on : 01 Jun 2019
36 Uttarakhand FP/UK/ROAD/9556/2015 8B/UCP/06/194/2015/FC Takh khandak to Balatadi motor road under PMGSY Lohaghat in District Champawat The road construction will be beneficial for habitation of Tak balwari, Sakdena & Balatari villages 791 peoples and villeges conected by district headquater, tehshil, Block headquater Pati Road PMGSY LOHAGHAT 4.97 IN-PRINCIPLE
Proposal received(at Nodal Officer)electronically on : 23 Jan 2015
Stage-I Approval on : 22 Feb 2018
Compliance Report Submitted by User Agency on : 25 May 2019
37 Uttarakhand FP/UK/ROAD/9581/2015 8B/UCP/06/250/2015 Conversion and Damrikaran of Banjbagar Telan LVR to Motor Road in Km 9 and Construction of Motor Road from Km 10 to 12 in District Chamoli. (Length 4.00) The proposed road is for providing connectivity to village Syari, Bangali with a population of 1101 numbers. The road is located in Block-Ghat of Road PUBLIC WORKS DEPARTMENT 2.012 IN-PRINCIPLE
Proposal received(at Nodal Officer)electronically on : 23 Jan 2015
Stage-I Approval on : 04 Aug 2016
Compliance Report Submitted by User Agency on : 21 Aug 2019
38 Uttarakhand FP/UK/ROAD/10294/2015 1(490)/2015 Making Motor Road. Road PUBLIC WORKS DEPARTMENT 2.7 IN-PRINCIPLE
Proposal received(at Nodal Officer)electronically on : 23 Feb 2015
Stage-I Approval on : 03 Nov 2015
Compliance Report Submitted by User Agency on : 25 May 2019
39 Uttarakhand FP/UK/ROAD/34294/2018 8B/UCP/06/157/2018/FC The proposed road is for providing the connectivity to the village Majyari, NailGenwali,Mald, Jakh, Chaura and Mahar with a population of 2418.The total length of the road is 16.775 km and approval of the road has been granted by Government of India under PMGSY project. Road PMGSY 3.6085 IN-PRINCIPLE
Proposal received(at Nodal Officer)electronically on : 22 Jun 2018
Stage-I Approval on : 21 Jan 2019
Compliance Report Submitted by User Agency on : 02 Sep 2019
40 Uttarakhand FP/UK/ROAD/9499/2015 1(423)/2015 Kathpuriyachina-Raikholi to Siya Motor Road is being sanctioned under PMGSY. The project length is 6.5 km which required 4.968 ha of forest land transfer. 2 Nos of villages Siya (381), Ariyagaad (163) will be benefited with this project. Road EXICUTIVE ENGINEER 4.968 IN-PRINCIPLE
Proposal received(at Nodal Officer)electronically on : 22 Jan 2015
Stage-I Approval on : 19 Aug 2015
Compliance Report Submitted by User Agency on : 27 May 2019
41 Uttarakhand FP/UK/ROAD/9526/2015 8B/UCP/06/255/2016/FC The proposal has been made for construction of Munch to Dubarjainal Motor Road under PMGSY which shall provide connectivity to villages Dubarjainal with a population of 311. Thus total population being served with this road. Road PMGSY 0.84 IN-PRINCIPLE
Proposal received(at Nodal Officer)electronically on : 22 Jan 2015
Stage-I Approval on : 31 Jul 2018
Compliance Report Submitted by User Agency on : 21 May 2019
42 Uttarakhand FP/UK/WATER/31878/2018 02(20)/2018 Villagers of the scheme is facing lots of problem as they have to fetch the drinking water from the distance sources. so there for forestland is required for drinking water supply scheme. Drinking Water CONSTRUCTION DIVISION UTTARAKHAND PAYJAL NIGAM 0.192 IN-PRINCIPLE
Proposal received(at Nodal Officer)electronically on : 22 Feb 2018
Stage-I Approval on : 09 Jul 2018
Compliance Report Submitted by User Agency on : 05 Feb 2019
43 Uttarakhand FP/UK/ROAD/14877/2015 8B/UCP/06./98/2018/FC Construction of Kotha bend to Panjiya Motor Road Under PMGSY scheme of Length-15.600 km. It will be served Population of (kakari-290, Kanbuwa-419, Sakani-313, Alasi-277 and Panjiya-484) total 1783 Conected. Road EXECUTIVE ENGINEER 9.093 IN-PRINCIPLE
Proposal received(at Nodal Officer)electronically on : 21 May 2018
Stage-I Approval on : 20 Jun 2019
Compliance Report Submitted by User Agency on : 29 Aug 2019
44 Uttarakhand FP/UK/ROAD/32113/2018 1(138)/2018 Construction of this road brings multiple socio-economic benefits to the rural areas and results in forming a strong backbone for the agro-based economy. It will serve better connectivity in nearby villages. Road EECDPWDUKM 0.833 IN-PRINCIPLE
Proposal received(at Nodal Officer)electronically on : 20 Feb 2018
Stage-I Approval on : 10 Sep 2018
Compliance Report Submitted by User Agency on : 07 Sep 2019
45 Uttarakhand FP/UK/ROAD/14803/2015 1(499)/2015 Road Road PUBLIC WORK DEPARTMENT 4.769 IN-PRINCIPLE
Proposal received(at Nodal Officer)electronically on : 20 Aug 2015
Stage-I Approval on : 07 Nov 2015
Compliance Report Submitted by User Agency on : 14 May 2019
46 Uttarakhand FP/UK/ROAD/18961/2016 8B/UCP/06/137/2016/FC Madkot to Tomik Motor Road Under PMGSY. length 27.500 km. Block- Munsyari Vidhansabha Chetra - Munsyari The Prominent point of target habitation tomik sach as Primary School, Primary Health Center, Maternity and Child Welfare centers and Post Office will be connected by this road. Tota Road PMGSY 9.53 IN-PRINCIPLE
Proposal received(at Nodal Officer)electronically on : 20 Apr 2016
Stage-I Approval on : 15 Jan 2018
Compliance Report Submitted by User Agency on : 07 May 2019
47 Uttarakhand FP/UK/ROAD/11836/2015 8B/UCP/06/123/2016/FC village Amola (205) Talai(217) Pangadu(210) population will beneficial from this project. For the Development all above villages it is compulsorily they are connected with Motor Road. Road PMGSY 8.541 IN-PRINCIPLE
Proposal received(at Nodal Officer)electronically on : 20 Apr 2015
Stage-I Approval on : 21 Jan 2019
Compliance Report Submitted by User Agency on : 03 Sep 2019
48 Uttarakhand FP/UK/ROAD/11082/2015 8B/UCP/06/129/2015/FC This is a road project of length 4.50 Km. joining the village Simaldhar in Almora Distt Uttarkahnd Road PUBLIC WORK DEPARTMENT 1.935 IN-PRINCIPLE
Proposal received(at Nodal Officer)electronically on : 19 Mar 2015
Stage-I Approval on : 13 Nov 2015
Compliance Report Submitted by User Agency on : 25 Jun 2019
49 Uttarakhand FP/UK/ROAD/10272/2015 8B/UCP/06/171/2015/FC Under the PMGSY I.D. Bageshwar Block Garur the road "Binkholi to Kothon Motor Road" it proposed to be of length 2.60km having 2.34 ha of total land area in which the civil soyam land is 0.54 ha. This project is going to connect the villages named Binkholi & Kothon and giving connectivity to a total Road EXICUTIVE ENGINEER 0.54 IN-PRINCIPLE
Proposal received(at Nodal Officer)electronically on : 19 Feb 2015
Stage-I Approval on : 24 Jan 2018
Compliance Report Submitted by User Agency on : 27 May 2019
50 Uttarakhand FP/UK/ROAD/10226/2015 8B/UCP/06/126/2015/FC This road will provide connectivity to palla,jakhola,kimana,Uchhaugwad,kalgoth village of Joshimath Block. Road PMGSY DIVISION PWD POKHARI 8.64 IN-PRINCIPLE
Proposal received(at Nodal Officer)electronically on : 18 Feb 2015
Stage-I Approval on : 10 Jul 2018
Compliance Report Submitted by User Agency on : 18 Mar 2019
12
Please wait ...