Ministry of Environment,Forest and Climate Change
Government of India
Rajasthan
State Forest Department
List of Proposals accorded Stage-II Clearance (Proposals received on or after 15th July 2014)
Help
Using this report, you can view details of proposals (Received on or after 15th July 2014) .Click on   to print
 
Proposal Year :
Region : State :
Category : Status of the Proposal :
Enter value for Search :
Note :-All areas are in Hectares(ha.)
Sno.State NameProposal No.RO/Ministry File NumberProposal NameCategoryUser Agency NameArea (ha.)Proposal StatusImportant DatesAllocation of Fresh forest land (Form-A) Part-IView Report (Part-II to Part-V and Stage-I Clearances)Stage-II Approval on
1 Rajasthan FP/RJ/ROAD/7757/2014 1(52)Forest/2015 Approch road Barodiya to Jatamari Road EXECUTIVE ENGINEER 0.994 IN-PRINCIPLE
Proposal received(at Nodal Officer)electronically on : 29 Oct 2014
Stage-I Approval on : 18 Mar 2015
Compliance Report Submitted by User Agency on : 04 Aug 2022
2 Rajasthan FP/RJ/ROAD/7759/2014 1(46)forest/2015 A/R to Nayagoav Bhanpura Road EXECUTIVE ENGINEER 0.2 IN-PRINCIPLE
Proposal received(at Nodal Officer)electronically on : 29 Oct 2014
Stage-I Approval on : 03 Mar 2015
Compliance Report Submitted by User Agency on : 04 Aug 2022
3 Rajasthan FP/RJ/ROAD/44021/2020 8B/Raj/12/31/2021/FC Widening of Kishangarh Toll Plaza between km 360+000 to Km 362+000 on (LHS) on Jaipur – Kishangarh Section of NH - 8 in the State of Rajasthan. Road National Highways Authority of India 1.751 IN-PRINCIPLE
Proposal received(at Nodal Officer)electronically on : 24 Jan 2020
Stage-I Approval on : 10 Jan 2022
Compliance Report Submitted by User Agency on : 27 Sep 2022
4 Rajasthan FP/RJ/ROAD/41639/2019 1(7)forest/2021 Rectification of Black Spot ID No. RJ-032/Jalore ; reg. Construction of 6 lane VUP with service road at km 268.620 of NH-15 (Jaisalmer - Barmer-Sanchore Section) in the state of Rajasthan Road PUBLIC WORKS DEPARTMENT NH DIVISION BARMER 0.99 IN-PRINCIPLE
Proposal received(at Nodal Officer)electronically on : 24 Aug 2019
Stage-I Approval on : 23 Feb 2021
Compliance Report Submitted by User Agency on : 22 Oct 2021
5 Rajasthan FP/RJ/TRANS/45503/2020 8B/Raj/04/39/2020 Construction of 400 kV D/C Khetri-Sikar Transmission Line under Transmission System Associated with LTA Applications for Rajasthan Solar Energy Zone, Part –C Total Line Length: 78.168Kms. Transmission Line POWERGRID KHETRI TRANSMISSION SYSTEM LIMITED 1.3706 IN-PRINCIPLE
Proposal received(at Nodal Officer)electronically on : 22 May 2020
Stage-I Approval on : 05 Jan 2021
Compliance Report Submitted by User Agency on : 22 Nov 2021
6 Rajasthan FP/RJ/OFC/44570/2020 8B/Raj014/2022-JPR BHARATNET PROJECT of Govt of India to connect Gram Panchayats Maharajpur, Nimbhera, daulatpura and Rahir on highspeed Broadband under Digital India Flagship program. There are two routes. ROUTE-1 Kms 0 to 40.459 KMs and ROUTE 2 Kms 0 to 11.340 KMs. Total Forest land 30.527 Kms and Non forest land KMs 21.272. Optical Fibre Cable BHARAT SANCHAR NIGAM LIMITED RAJASTHAN 1.3737 IN-PRINCIPLE
Proposal received(at Nodal Officer)electronically on : 22 Feb 2020
Stage-I Approval on : 04 Apr 2022
Compliance Report Submitted by User Agency on : 23 Sep 2022
7 Rajasthan FP/RJ/TRANS/45462/2020 8B/Raj/04/40/2020 Construction of 765 kV D/C Khetri-Jhatikra Transmission Line under Transmission System Associated with LTA Applications for Rajasthan Solar Energy Zone, Part –C Line Length - 28.513Kms in Rajasthan. Transmission Line POWERGRID KHETRI TRANSMISSION SYSTEM LIMITED 2.2401 IN-PRINCIPLE
Proposal received(at Nodal Officer)electronically on : 20 May 2020
Stage-I Approval on : 05 Jan 2021
Compliance Report Submitted by User Agency on : 22 Nov 2021
8 Rajasthan FP/RJ/ROAD/7595/2014 1(51)Forest/2015 NH-12 to Rojya Road EXECUTIVE ENGINEER 0.95 IN-PRINCIPLE
Proposal received(at Nodal Officer)electronically on : 16 Oct 2014
Stage-I Approval on : 18 Mar 2015
Compliance Report Submitted by User Agency on : 04 Aug 2022
9 Rajasthan FP/RJ/ROAD/38150/2019 1(30)forest/2020 Construction of Approach road jhalra patan railway station Road PUBLIC WORKS DEPARTMENT JHALAWAR 0.9 IN-PRINCIPLE
Proposal received(at Nodal Officer)electronically on : 16 Jan 2019
Stage-I Approval on : 04 Oct 2021
Compliance Report Submitted by User Agency on : 15 Feb 2022
10 Rajasthan FP/RJ/ROAD/35959/2018 1(2)forest/2021 “Construction of CC.Road from Triveni road to Brahmani Mata Temple ” Road PUBLIC WORK DEPARTMENT 0.5004 IN-PRINCIPLE
Proposal received(at Nodal Officer)electronically on : 15 Sep 2018
Stage-I Approval on : 27 Jan 2021
Compliance Report Submitted by User Agency on : 15 Jul 2022
11 Rajasthan FP/RJ/ROAD/33605/2018 F.1(62)Forest/2018 Construction of Missing link road between Boraj to Existing Chamunda Road Road PUBLIC WORKS DEPARTMENT 0.592 IN-PRINCIPLE
Proposal received(at Nodal Officer)electronically on : 14 May 2018
Stage-I Approval on : 05 Oct 2018
Compliance Report Submitted by User Agency on : 02 Aug 2022
12 Rajasthan FP/RJ/TRANS/145974/2021 8B/RAJ026/2022-JPR Construction of 220 kV Transmission Line Transmission Line SBE Renewables Ten Private Limited 0.175 IN-PRINCIPLE
Proposal received(at Nodal Officer)electronically on : 13 Aug 2021
Stage-I Approval on : 06 Jun 2022
Compliance Report Submitted by User Agency on : 03 Aug 2022
13 Rajasthan FP/RJ/TRANS/146976/2021 1(15)forest/2022 “Construction for LILO of 132kV S/C Beawar-Jethana line at Peeplaj , District -Ajmer (Rajasthan)” Transmission Line RVPNL AJMER 0.0918 IN-PRINCIPLE
Proposal received(at Nodal Officer)electronically on : 09 Sep 2021
Stage-I Approval on : 22 Feb 2022
Compliance Report Submitted by User Agency on : 17 Aug 2022
14 Rajasthan FP/RJ/ROAD/6954/2014 8B/RJ/06/04/2015/FC Road Work from Jalwara to Kishanpura Road PUBLIC WORKS DEPARTMENT 2.96 IN-PRINCIPLE
Proposal received(at Nodal Officer)electronically on : 08 Sep 2014
Stage-I Approval on : 23 Aug 2016
Compliance Report Submitted by User Agency on : 05 Jul 2022
15 Rajasthan FP/RJ/ROAD/6994/2014 8B/RAJ/06/6/2015 Road from Khandela to Halawani Road PUBLIC WORKS DEPARTMENT 2.05 IN-PRINCIPLE
Proposal received(at Nodal Officer)electronically on : 08 Sep 2014
Stage-I Approval on : 04 Aug 2016
Compliance Report Submitted by User Agency on : 05 Jul 2022
16 Rajasthan FP/RJ/ROAD/7000/2014 8B/RJ/06/19/2015 Road from Gordhanpura to Kali mati Road PUBLIC WORKS DEPARTMENT 2.98 IN-PRINCIPLE
Proposal received(at Nodal Officer)electronically on : 08 Sep 2014
Stage-I Approval on : 04 Aug 2016
Compliance Report Submitted by User Agency on : 05 Jul 2022
17 Rajasthan FP/RJ/ROAD/42305/2019 8B/Raj/06/7/2021/FC Diversion of 0.980 Ha forest Land for Development and Maintenance of Siwana-Samdari- Balesr Section of SH-66 Road ADD CHIEF ENGINEER PPP PWD JAIPUR RAJ 0.98 IN-PRINCIPLE
Proposal received(at Nodal Officer)electronically on : 02 Oct 2019
Stage-I Approval on : 21 Feb 2022
Compliance Report Submitted by User Agency on : 26 Jul 2022
18 Rajasthan FP/RJ/ROAD/43002/2019 1(107) Van/2020 Rehabilitation of jhalrapatan ,Gindor,Railway station Jhikriya, Kishanpura Durgpura Gagron (MDR-227) Road PUBLIC WORKS DEPARTMENT JHALAWAR 0.999 IN-PRINCIPLE
Proposal received(at Nodal Officer)electronically on : 02 Dec 2019
Stage-I Approval on : 22 Oct 2020
Compliance Report Submitted by User Agency on : 02 Aug 2022
Please wait ...