Ministry of Environment,Forest and Climate Change
Government of India
Orissa
State Forest Department
List of Proposals accorded Stage-II Clearance (Proposals received on or after 15th July 2014)
Help
Using this report, you can view details of proposals (Received on or after 15th July 2014) .Click on   to print
 
Proposal Year :
Region : State :
Category : Status of the Proposal :
Enter value for Search :
Note :-All areas are in Hectares(ha.)
Sno.State NameProposal No.RO/Ministry File NumberProposal NameCategoryUser Agency NameArea (ha.)Proposal StatusImportant DatesAllocation of Fresh forest land (Form-A) Part-IView Report (Part-II to Part-V and Stage-I Clearances)Stage-II Approval on
1 Orissa FP/OR/TRANS/39618/2019 5-ORC426/2020-BHU For construction of a 132 KV 2 phase Transmission line from exiting 220/132/33 KV Grid sub-station at Therubali to proposed 132/25 KV switch yard of RTSS Bhalumaska of Odisha Power Transmission Corpor Transmission Line ODISHA POWER TRANSMISSION CORPORATION LIMITED 14.661 IN-PRINCIPLE
Proposal received(at Nodal Officer)electronically on : 30 Mar 2019
Stage-I Approval on : 10 Sep 2020
Compliance Report Submitted by User Agency on : 24 Aug 2022
2 Orissa FP/OR/IND/36705/2018 5-ORC400/2019-BHU Iron Ore Grinding, De-Sliming (Beneficiation) Plant & Slurry Pumping Station and Water Intake System of M/s JSW Utkal Steel Ltd., Barbil Tahasil, Keonjhar District Industry JSW UTKAL STEEL LIMITED 22.671 IN-PRINCIPLE
Proposal received(at Nodal Officer)electronically on : 29 Oct 2018
Stage-I Approval on : 23 Dec 2019
Compliance Report Submitted by User Agency on : 22 Mar 2022
3 Orissa FP/OR/Pipeline/45293/2020 5-ORB457/2021-BHU Execution of 02 Nos. of Individual Rural Piped Water Supply Projects pertaining to Jharsuguda district including five years of Pipeline RURAL WATER SUPPLY & SANITATION KEONJHAR 4.046 IN-PRINCIPLE
Proposal received(at Nodal Officer)electronically on : 26 Apr 2020
Stage-I Approval on : 06 Apr 2021
Compliance Report Submitted by User Agency on : 18 Jun 2022
4 Orissa FP/OR/TRANS/139357/2021 5-ORB478/2021-BHU Modification of 132 KV Budhipadar - Jorabaga line. Transmission Line OPTCL. 0.827 IN-PRINCIPLE
Proposal received(at Nodal Officer)electronically on : 25 Mar 2021
Stage-I Approval on : 30 Dec 2021
Compliance Report Submitted by User Agency on : 28 Sep 2022
5 Orissa FP/OR/TRANS/38533/2019 5-ORC416/2020-BHU Construction of 220 KV Lilo Transmission line from LOC No. 331 of Existing 220 KV Rengali Tarkera Line to proposed 220/ 33 KV Grid Sub-station at Deogarh. Transmission Line OPTCL 21.159 IN-PRINCIPLE
Proposal received(at Nodal Officer)electronically on : 23 Jan 2019
Stage-I Approval on : 25 Jun 2020
Compliance Report Submitted by User Agency on : 08 Jun 2021
Please wait ...