Sno. | State Name | Proposal No. | RO/Ministry File Number | Proposal Name | Category | User Agency Name | Area (ha.) | Proposal Status | Important Dates | Allocation of Fresh forest land (Form-A) Part-I | View Report (Part-II to Part-V and Stage-I Clearances) | Stage-II Approval on |
1
|
Assam
|
FP/AS/Pipeline/48074/2020
|
F.No.3- AS B 07 6 /2021-GHy
|
Laying of Proposed 18" Ø (Carbon steel) Natural Gas Pipeline along with OFC Conduit From Guwahati to Panisagar.
|
Pipeline
|
INDRADHANUSH GAS GRID LIMITED
|
4.7289
|
IN-PRINCIPLE
|
Proposal received(at Nodal Officer)electronically on
|
:
|
30 Jul 2020
|
Stage-I Approval on
|
:
|
09 Mar 2022
|
Compliance Report Submitted by User Agency on
|
:
|
22 Aug 2022
|
|
|
|
|
2
|
Assam
|
FP/AS/TRANS/119559/2021
|
3-AS-C-096/2022/GHY
|
Diversion of Forest Land for 11 nos. of Tower Location (123 to 136A) against “Diversion work of 132KV S/C Haflong-Jiribam transmission line of POWERGRID in the section between tower location no. 104 to location no. 164 for facilitating the construction of NH-54 (E) under Borail Wildlife Sanctuary under Cachar Dist. of Assam State
|
Transmission Line
|
POWERGRID CORPORATION OF INDIA LIMITED
|
9.23
|
IN-PRINCIPLE
|
Proposal received(at Nodal Officer)electronically on
|
:
|
15 Jan 2021
|
Stage-I Approval on
|
:
|
09 Feb 2023
|
Compliance Report Submitted by User Agency on
|
:
|
11 Apr 2023
|
|
|
|
|
3
|
Assam
|
FP/AS/ROAD/44439/2020
|
3-AS-C-100/2022/GHY
|
Up gradation of Bilasipura-Chapar-Tulungia-Jogighopa-Gendera-Paikan-Dudhnoi-Guwahati Road (Length 225.000 km) for Goalpara district, in the State of Assam
|
Road
|
NHIDCL BO TEZPUR
|
27.054
|
IN-PRINCIPLE
|
Proposal received(at Nodal Officer)electronically on
|
:
|
06 Feb 2020
|
Stage-I Approval on
|
:
|
16 Dec 2022
|
Compliance Report Submitted by User Agency on
|
:
|
08 Aug 2024
|
|
|
|
|
4
|
Assam
|
FP/AS/MIN/32798/2018
|
3-AS-B-138/2022/GHY
|
Proposed Development Drilling Wells and Testing of Hydrocarbons in Dipling Block-AA/ONDSF/DIPLING/2016 in Sivasagar (Charaideo) and Dibrugarh District,Assam
|
Mining
|
RAMAYANA ISPAT PVT LTD
|
3.06
|
IN-PRINCIPLE
|
Proposal received(at Nodal Officer)electronically on
|
:
|
04 Apr 2018
|
Stage-I Approval on
|
:
|
11 Apr 2023
|
Compliance Report Submitted by User Agency on
|
:
|
10 Feb 2025
|
|
|
|
|