Note :-All areas are in Hectares(ha.)
Sno.State NameProposal No.RO/Ministry File NumberProposal NameCategoryUser Agency NameArea (ha.)Proposal StatusImportant DatesAllocation of Fresh forest land (Form-A) Part-IView Report (Part-II to Part-V and Stage-I Clearances)Stage-II Approval on
1 Orissa FP/OR/Others/14546/2015 5-ORC322/2017-BHU Infrastructure Project for Kurmitar & Rantha ML Others ODISHA MINING CORPORATION LTD 11.912 APPROVED
Proposal received(at Nodal Officer)electronically on : 31 Oct 2015
Stage-I Approval on : 29 Nov 2018
Compliance Report Submitted by User Agency on : 19 May 2020
29 May 2020
2 Orissa FP/OR/MIN/28732/2017 8-28/2019-FC Banspani Iron Ore Mines Mining ODISHA MINING CORPORATION LTD 183.218 APPROVED
Proposal received(at Nodal Officer)electronically on : 31 Aug 2017
Stage-I Approval on : 04 Nov 2020
Compliance Report Submitted by User Agency on : 01 Oct 2021
16 Dec 2021
3 Orissa FP/OR/TRANS/40463/2019 5-ORB403/2019-BHU “Diversion of 400KV D/C Talcher – Meramundli Transmission Line” of PGCIL at Village Kamalang in Dhenkanal district, Odisha. Transmission Line POWERGRID KANHIA 0.378 APPROVED
Proposal received(at Nodal Officer)electronically on : 30 May 2019
Stage-I Approval on : 16 Jan 2020
Compliance Report Submitted by User Agency on : 22 Jan 2021
09 Feb 2021
4 Orissa FP/OR/TRANS/39618/2019 5-ORC426/2020-BHU For construction of a 132 KV 2 phase Transmission line from exiting 220/132/33 KV Grid sub-station at Therubali to proposed 132/25 KV switch yard of RTSS Bhalumaska of Odisha Power Transmission Corpor Transmission Line ODISHA POWER TRANSMISSION CORPORATION LIMITED 14.661 IN-PRINCIPLE
Proposal received(at Nodal Officer)electronically on : 30 Mar 2019
Stage-I Approval on : 10 Sep 2020
Compliance Report Submitted by User Agency on : 24 Aug 2022
5 Orissa FP/OR/MIN/35045/2018 8-135/2003-FC vol.I DIVERSION OF UNBROKEN 59.606 HA FOREST LAND (57.515 HA FOR MINING & ANCILLARY ACTIVITIES INCLUDING 1.417 HA OF FOREST LAND DIVERTED EARLIER FOR SAFETY ZONE ALONG PART SURRENDER AREA + 2.091 HA FOR SAFETY ZONE ALONG M.L BOUNDARY) IN RESPECT OF SANINDPUR IRON & BAUXITE MINES OF M/S. RUNGTA SONS (P) LIMITED. Mining RUNGTA SONS PRIVATE LIMITED 59.606 APPROVED
Proposal received(at Nodal Officer)electronically on : 30 Jul 2018
Stage-I Approval on : 13 Jan 2020
Compliance Report Submitted by User Agency on : 07 Oct 2020
26 Nov 2020
6 Orissa FP/OR/TRANS/17794/2016 5-ORC306/2017-BHU 400 KV D/C tarnsmission line from LILO point to PGCIL Sundargarh Pooling Station by M/s Vedanta Ltd. Transmission Line VEDANTA LIMITED 6 APPROVED
Proposal received(at Nodal Officer)electronically on : 30 Jan 2016
Stage-I Approval on : 28 Feb 2017
Compliance Report Submitted by User Agency on : 03 Aug 2022
11 Aug 2022
7 Orissa FP/OR/IND/36705/2018 5-ORC400/2019-BHU Iron Ore Grinding, De-Sliming (Beneficiation) Plant & Slurry Pumping Station and Water Intake System of M/s JSW Utkal Steel Ltd., Barbil Tahasil, Keonjhar District Industry JSW UTKAL STEEL LIMITED 22.671 IN-PRINCIPLE
Proposal received(at Nodal Officer)electronically on : 29 Oct 2018
Stage-I Approval on : 23 Dec 2019
Compliance Report Submitted by User Agency on : 22 Mar 2022
8 Orissa FP/OR/MIN/18729/2016 8-116/2002-FC Vol-I Mahagiri Mines (Chromite) of M/s. IMFA Ltd Mining Indian Metals & Ferro Alloys Ltd 7.397 APPROVED
Proposal received(at Nodal Officer)electronically on : 29 Mar 2016
Stage-I Approval on : 20 Oct 2016
Compliance Report Submitted by User Agency on : 26 Sep 2017
30 Oct 2018
9 Orissa FP/OR/MIN/18726/2016 8-16/2016-FC Sukinda Mines (Chromite) of M/S. IMFA Ltd Mining Indian Metals & Ferro Alloys Ltd 115.05 APPROVED
Proposal received(at Nodal Officer)electronically on : 29 Mar 2016
Stage-I Approval on : 20 Oct 2016
Compliance Report Submitted by User Agency on : 10 Nov 2017
22 Jun 2018
10 Orissa FP/OR/ROAD/35474/2018 5-ORB389/2019-BHU Proposed approach road from NH 520 to Kamanda Steel Plan of Rungta Mines Ltd. Road MS RUNGTA MINES LIMITED 0.28 APPROVED
Proposal received(at Nodal Officer)electronically on : 29 Aug 2018
Stage-I Approval on : 30 Jul 2019
Compliance Report Submitted by User Agency on : 20 Mar 2020
23 Mar 2020
11 Orissa FP/OR/MIN/32796/2018 8-25/2021-FC SIARMAL OCP OF MAHANADI COALFIELDS LIMITED Mining SIARMAL OCP MAHANADI COALFIELDS LIMITED 349.709 Pending at Nodal Officer after receiving Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 28 Mar 2018
Stage-I Approval on : 21 Apr 2022
Compliance Report Submitted by User Agency on : 05 Aug 2022
12 Orissa FP/OR/HYD/39171/2019 5-ORB436/2020-BHU Upper Indravati Pump Storage Hydro Project Hydel ODISHA HYDRO POWER CORPORATION LIMITED 0.99 APPROVED
Proposal received(at Nodal Officer)electronically on : 28 Feb 2019
Stage-I Approval on : 21 Dec 2020
Compliance Report Submitted by User Agency on : 08 Nov 2021
29 Dec 2021
13 Orissa FP/OR/MIN/30980/2017 8-01/2020-FC Naini Open Cast Project (Coal), (Rated Capcity 10 MTPA, Singareni Collieries Company Ltd., Angul, Dist- Odisha) Mining SCCL NAINI 783.275 Pending at HO for Stage-II
Proposal received(at Nodal Officer)electronically on : 28 Dec 2017
Stage-I Approval on : 28 Jul 2021
Compliance Report Submitted by User Agency on : 21 Sep 2022
14 Orissa FP/OR/MIN/8707/2014 8-46/2018-FC Khandbandh Iron Ore Mines Mining ODISHA MINING CORPORATION LTD 345.189 APPROVED
Proposal received(at Nodal Officer)electronically on : 27 Jan 2017
Stage-I Approval on : 31 Jan 2019
Compliance Report Submitted by User Agency on : 03 Sep 2021
16 Dec 2021
15 Orissa FP/OR/TRANS/30962/2017 5-ORC418/2020-BHU 132 KV Transmission Line from 132/33 KV to Kamanda Steel Plant at- Village Kamanda, Sundargarh to grid Barbil Keonjhar. Transmission Line RUNGTA MINES LTD 35.507 APPROVED
Proposal received(at Nodal Officer)electronically on : 27 Dec 2017
Stage-I Approval on : 25 Jun 2020
Compliance Report Submitted by User Agency on : 19 Feb 2021
31 Mar 2021
16 Orissa FP/OR/Pipeline/45293/2020 5-ORB457/2021-BHU Execution of 02 Nos. of Individual Rural Piped Water Supply Projects pertaining to Jharsuguda district including five years of Pipeline RURAL WATER SUPPLY & SANITATION KEONJHAR 4.046 IN-PRINCIPLE
Proposal received(at Nodal Officer)electronically on : 26 Apr 2020
Stage-I Approval on : 06 Apr 2021
Compliance Report Submitted by User Agency on : 18 Jun 2022
17 Orissa FP/OR/TRANS/139357/2021 5-ORB478/2021-BHU Modification of 132 KV Budhipadar - Jorabaga line. Transmission Line OPTCL. 0.827 IN-PRINCIPLE
Proposal received(at Nodal Officer)electronically on : 25 Mar 2021
Stage-I Approval on : 30 Dec 2021
Compliance Report Submitted by User Agency on : 28 Sep 2022
18 Orissa FP/OR/MIN/10335/2015 8-27/2017-FC Daitari Conveyor Corridor (2.5 MTPA) Mining ODISHA MINING CORPORATION LTD 106.016 APPROVED
Proposal received(at Nodal Officer)electronically on : 25 Jul 2016
Stage-I Approval on : 27 Sep 2017
Compliance Report Submitted by User Agency on : 02 Dec 2019
22 Mar 2021
19 Orissa FP/OR/RAIL/39739/2019 5-ORC423/2020-BHU Proposal for diversion of 18.131ha of forest land for construction of 3rd & 4th Railway line from Jarapada-Budhapank Railway DEPUTY CHIEF ENGINEER CON-1 18.131 APPROVED
Proposal received(at Nodal Officer)electronically on : 25 Apr 2019
Stage-I Approval on : 31 Jul 2020
Compliance Report Submitted by User Agency on : 10 Aug 2021
02 Sep 2021
20 Orissa FP/OR/Pipeline/36091/2018 5-ORB387/2019-BHU Joda to Paradeep Iron Ore Slurry Pipelines System [Alignment under Non-RoW]of M/s JSW Utkal Steel Ltd. Pipeline JSW UTKAL STEEL LIMITED 0.654 APPROVED
Proposal received(at Nodal Officer)electronically on : 24 Sep 2018
Stage-I Approval on : 12 Jul 2019
Compliance Report Submitted by User Agency on : 09 Jul 2020
27 Jul 2020
21 Orissa FP/OR/ROAD/24576/2017 5-ORA357/2018-BHU Rehabilitation and upgradation to two/four laning of Talchar-Dubari-Chandikhole section of NH-200 in Odisha Road National Highways Authority of India 176.231 APPROVED
Proposal received(at Nodal Officer)electronically on : 24 Feb 2017
Stage-I Approval on : 05 Dec 2018
Compliance Report Submitted by User Agency on : 10 Nov 2020
03 Dec 2020
22 Orissa FP/OR/RAIL/35352/2018 5-ORC471/2021-BHU Construction of 3rd Railway line between Vizianagaram to Titlagarh under East Coast Railway by Rail Vikas Nigam Limited. Railway CHIEF PROJECT MANGERRAIL VIKAS NIGAM LIMITED 5.858 APPROVED
Proposal received(at Nodal Officer)electronically on : 24 Aug 2018
Stage-I Approval on : 07 Sep 2021
Compliance Report Submitted by User Agency on : 03 Aug 2022
10 Aug 2022
23 Orissa FP/OR/IND/10338/2015 5-ORB295/2016-BHU Tata Steel Special Economic Zone at Gopalpur in Ganjam District, Odisha. Industry Tata Steel Limited, Jamshedpur 3.792 APPROVED
Proposal received(at Nodal Officer)electronically on : 24 Aug 2015
Stage-I Approval on : 19 Dec 2016
Compliance Report Submitted by User Agency on : 26 Oct 2018
24 Oct 2018
24 Orissa FP/OR/TRANS/38533/2019 5-ORC416/2020-BHU Construction of 220 KV Lilo Transmission line from LOC No. 331 of Existing 220 KV Rengali Tarkera Line to proposed 220/ 33 KV Grid Sub-station at Deogarh. Transmission Line OPTCL 21.159 IN-PRINCIPLE
Proposal received(at Nodal Officer)electronically on : 23 Jan 2019
Stage-I Approval on : 25 Jun 2020
Compliance Report Submitted by User Agency on : 08 Jun 2021
25 Orissa FP/OR/DISP/43480/2019 5-ORC439/2020-BHU Centers of Excellence ,AIIMS Bhubaneswar Dispensary/Hospital DIRECTOR AIIMS BHUBANESWAR 10.58 APPROVED
Proposal received(at Nodal Officer)electronically on : 23 Dec 2019
Stage-I Approval on : 07 Jan 2021
Compliance Report Submitted by User Agency on : 21 Dec 2021
30 Dec 2021
26 Orissa FP/OR/TRANS/22467/2016 5-ORC320/2017-BHU LILO of Both Circuits of Rourkela-Raigarh 400KV D/C transmission line (2nd line) at Jharsuguda (Sundargarh) Sub-Station Transmission Line POWER GRID CORPORATION OF INDIA LTD 24.424 APPROVED
Proposal received(at Nodal Officer)electronically on : 22 Nov 2016
Stage-I Approval on : 04 Aug 2017
Compliance Report Submitted by User Agency on : 20 Jul 2019
26 Jul 2019
27 Orissa FP/OR/MIN/18611/2016 8-55/2018-FC Ghoraburhani Sagasahi Iron Ore Block of Essar Steel India Limited Mining ArcelorMittal Nippon Steel India Limited 126.401 APPROVED
Proposal received(at Nodal Officer)electronically on : 22 Mar 2016
Stage-I Approval on : 06 Mar 2019
Compliance Report Submitted by User Agency on : 19 Oct 2020
15 Dec 2020
28 Orissa FP/OR/ROAD/46616/2020 5-ORB433/2020-BHU Construction of link road on forest land for Page Industry Ltd. to provide connectivity to the project area. Road IDCO 0.307 APPROVED
Proposal received(at Nodal Officer)electronically on : 22 Jun 2020
Stage-I Approval on : 21 Oct 2020
Compliance Report Submitted by User Agency on : 23 Dec 2020
22 Jan 2021
29 Orissa FP/OR/QRY/32655/2018 5-ORB369/2018-BHU Khindo Stone Quarry Quarrying TAHSILDAR KANIHA 1.214 APPROVED
Proposal received(at Nodal Officer)electronically on : 21 Mar 2018
Stage-I Approval on : 29 May 2020
Compliance Report Submitted by User Agency on : 03 May 2021
08 Jun 2021
30 Orissa FP/OR/TRANS/10367/2015 5-ORC274/2016-BHU Proposal for diversion of 11.377 ha of forest land in Reserve Forest,Jungle Block & Patra Jungle for 220 KV S/C Transmission Line on D/C Tower from existing 220/33 K/V Sub-Station at Laxmipur to premises of Nalco at Damanjodi in Koraput District of Odisha Transmission Line NATIONAL ALUMINIUM COMPANY 11.377 APPROVED
Proposal received(at Nodal Officer)electronically on : 21 Mar 2015
Stage-I Approval on : 05 Aug 2016
Compliance Report Submitted by User Agency on : 26 Sep 2017
04 Aug 2017
31 Orissa FP/OR/MIN/20126/2016 8-87/1996-FC Vol. Bolani Ores Mines (6.90 sq.mile ML) of SAIL, Dist: Keonjhar Odisha Mining Rourkela Steel Plant, Steel Authority of India Limited (SAIL) 238.093 APPROVED
Proposal received(at Nodal Officer)electronically on : 21 Jun 2016
Stage-I Approval on : 12 Sep 2017
Compliance Report Submitted by User Agency on : 24 Jan 2019
29 Apr 2019
32 Orissa FP/OR/Others/32590/2018 5-ORB399/2019-BHU Installation of pipeline over a length 4.748 km for drawal of water from river Mahanadi to Boudh Distillery in Odisha Others BOUDH DISTILLERY PVT LTD 0.966 Pending at Nodal Officer after receiving Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 20 Mar 2018
Stage-I Approval on : 04 Dec 2019
Compliance Report Submitted by User Agency on : 07 Sep 2022
33 Orissa FP/OR/TRANS/34271/2018 5-ORC415/2020-BHU Construction of Proposed 132 KV Transmission line from 132/133 KvV Grid Sub-Station at Dabugaon to 220/132/33 KV Grid Sub-Stationat Jaypatna Transmission Line ODISHA POWER TRANSMISSION CORPORATION LIMITED 22.253 Pending at DFO for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 20 Jun 2018
Stage-I Approval on : 03 Jun 2020
Compliance Report Submitted by User Agency on : 08 Oct 2021
34 Orissa FP/OR/MIN/14006/2015 8-18/2016-FC Baphlimali Bauxite Mining Project of M/s Utkal Alumina International Limited ( UAIL) Mining M/S HINDALCO INDUSTRIES LTD. 233.34 APPROVED
Proposal received(at Nodal Officer)electronically on : 20 Jul 2015
Stage-I Approval on : 29 Jun 2017
Compliance Report Submitted by User Agency on : 04 Dec 2017
02 Feb 2018
35 Orissa FP/OR/RAIL/34204/2018 5-ORC411/2020-BHU Propasal for diversion of 24.188ha of forest land for construction of Budhapank-Salegaon 3rd & 4th Railway line Project, (0-85km) Railway DCE CON I EAST COAST RAILWAY 24.188 APPROVED
Proposal received(at Nodal Officer)electronically on : 19 Jun 2018
Stage-I Approval on : 08 Oct 2020
Compliance Report Submitted by User Agency on : 30 Aug 2022
09 Sep 2022
36 Orissa FP/OR/Others/32129/2018 5-ORB397/2019-BHU Setting up a new Oil Depot of BPCL Others BHARAT PETROLEUM CORP LTD SADASHIBPUR 2.091 APPROVED
Proposal received(at Nodal Officer)electronically on : 19 Feb 2018
Stage-I Approval on : 25 Nov 2019
Compliance Report Submitted by User Agency on : 20 Oct 2020
12 Nov 2020
37 Orissa FP/OR/TRANS/21714/2016 5-ORA334/2018-BHU 765 KV D/C JHARSUGUDA (SUNDARGARH) – RAIPUR POOL TRANSMISSION LINE Transmission Line ODISHA GENERATION PHASE II TRANSMISSION LIMITED 94.656 APPROVED
Proposal received(at Nodal Officer)electronically on : 18 Oct 2016
Stage-I Approval on : 06 Mar 2018
Compliance Report Submitted by User Agency on : 06 Jun 2022
22 Jun 2022
38 Orissa FP/OR/MIN/20081/2016 8-01/2018-FC Katamati Iron Mine Mining TATA STEEL LIMITED KHONDBOND IRON AND MN MINES 160.838 APPROVED
Proposal received(at Nodal Officer)electronically on : 18 Jun 2016
Stage-I Approval on : 20 Aug 2018
Compliance Report Submitted by User Agency on : 03 Dec 2020
09 Jun 2021
39 Orissa FP/OR/MIN/17936/2016 8-17/2016-FC 5.10 Sq. Miles ML of Bolani Ores Mines Mining Rourkela Steel Plant, Steel Authority of India Limited (SAIL) 87.09 APPROVED
Proposal received(at Nodal Officer)electronically on : 17 Feb 2016
Stage-I Approval on : 12 Sep 2017
Compliance Report Submitted by User Agency on : 24 Jan 2019
06 Nov 2019
40 Orissa FP/OR/Others/37517/2018 5-ORC395/2019-BHU Jagdishpur-Haldia-Bokaro-Dhamra Pipeline (JHBDPL), Odisha Project of GAIL Permanent land acquisition Others GAIL INDIA LIMITED 0.9712 APPROVED
Proposal received(at Nodal Officer)electronically on : 17 Dec 2018
Stage-I Approval on : 04 Oct 2019
Compliance Report Submitted by User Agency on : 25 Jun 2020
08 Dec 2020
41 Orissa FP/OR/THE/29588/2017 5-ORC383/2019-BHU 3x800 MW Super Critical Thermal Power Plant at Kamakhyanagar Tahasil in Dhenkanal District Thermal ODISHA THERMAL POWER CORPORATION LTD (OTPCL) 38.098 APPROVED
Proposal received(at Nodal Officer)electronically on : 16 Oct 2017
Stage-I Approval on : 07 Jun 2019
Compliance Report Submitted by User Agency on : 11 Nov 2020
04 Jan 2021
42 Orissa FP/OR/TRANS/45428/2020 5-ORC450/2021-BHU 33 kv power transmission line from Jaroli sub station to PMPL Plant site at Basantapur Transmission Line ESSEL MINING & INDUSTRIES LIMITED 22.368 APPROVED
Proposal received(at Nodal Officer)electronically on : 16 May 2020
Stage-I Approval on : 08 Jun 2021
Compliance Report Submitted by User Agency on : 23 Dec 2021
08 Mar 2022
43 Orissa FP/OR/HYD/9265/2015 5-ORB409/2020-BHU 25 MW SHAHEED LAKHAN NAYAK SHEP Hydel MEENAKSHI ODISHA POWER PRIVATE LIMITED 4.902 APPROVED
Proposal received(at Nodal Officer)electronically on : 16 Jun 2016
Stage-I Approval on : 06 Jul 2020
Compliance Report Submitted by User Agency on : 18 Dec 2020
16 Feb 2021
44 Orissa FP/OR/ROAD/25629/2017 5-ORC344/2018-BHU Balasore-Baripada-Jharpokharia Section of NH-5 Road NATIONAL HIGHWAY AUTHORITY OF INDIA PIU BALASORE 13.856 APPROVED
Proposal received(at Nodal Officer)electronically on : 15 Jul 2017
Stage-I Approval on : 27 Apr 2018
Compliance Report Submitted by User Agency on : 12 Jan 2021
16 Feb 2021
45 Orissa FP/OR/ROAD/31840/2018 5-ORC350/2018-BHU Construction of 200 feet master plan road from Rail Vihar to Ekamrakanan over a stretch of 1.930 KM under Executive Engineer (R&B) Division (No-III), bhubaneswar and under Tahasil: Bhubaneswar of Khurdha District. Road EXECUTIVE ENGINEER, BBSR (R&B) DIVISION NO.III. BHUBANESWAR 10.501 APPROVED
Proposal received(at Nodal Officer)electronically on : 15 Feb 2018
Stage-I Approval on : 18 Jul 2018
Compliance Report Submitted by User Agency on : 02 Mar 2020
15 Sep 2020
46 Orissa FP/OR/Others/17057/2015 5-ORB315/2017-BHU Establishment of Lighthouse as advised by Central Advisory Committee for Lighthouses (CACL) Others DIRECTORATE OF LIGHT HOUSES AND LIGHTSHIPS KOLKATA 0.332 APPROVED
Proposal received(at Nodal Officer)electronically on : 15 Dec 2015
Stage-I Approval on : 12 Oct 2017
Compliance Report Submitted by User Agency on : 12 Jun 2019
24 Jul 2019
47 Orissa FP/OR/ROAD/17550/2016 5-ORA313/2017-BHU REHABILITATION AND UPGRADATION OF NH-6 PACKAGE-1 BAHARGORA TO SINGARA (KM 199.200 TO KM 310.806) SECTION OF NH-6 IN THE STATE OF ORISSA Road NATIONAL HIGHWAY AUTHORITY OF INDIA PIU BALASORE 85.104 APPROVED
Proposal received(at Nodal Officer)electronically on : 14 Jan 2016
Stage-I Approval on : 12 Sep 2017
Compliance Report Submitted by User Agency on : 06 Nov 2020
08 Dec 2020
48 Orissa FP/OR/TRANS/38942/2019 5-ORB402/2019-BHU CONSTRUCTION OF DIVERSION PORTION OF HVDC EARTH ELECTRODE TRANSMISSION LINE Transmission Line POWERGRID KANHIA 0.943 APPROVED
Proposal received(at Nodal Officer)electronically on : 14 Feb 2019
Stage-I Approval on : 16 Jan 2020
Compliance Report Submitted by User Agency on : 16 Mar 2021
17 May 2021
49 Orissa FP/OR/TRANS/38936/2019 5-ORB432/2020-BHU CONSTRUCTION OF DIVERSION PORTION OF 400 KV DOUBLE CIRCUIT TALCHER-MERAMUNDALI TRANSMISSION LINE. Transmission Line POWERGRID KANHIA 1.3841 APPROVED
Proposal received(at Nodal Officer)electronically on : 14 Feb 2019
Stage-I Approval on : 05 Nov 2020
Compliance Report Submitted by User Agency on : 03 May 2021
02 Jul 2021
50 Orissa FP/OR/RAIL/30199/2017 5-ORC348/2018-BHU Establishment of Industries i.e.Establishment of Railway line & Siding under Danagadi Tahasil in Jajpur District of M/s Emami Cement Ltd. Railway IDCO 8.114 APPROVED
Proposal received(at Nodal Officer)electronically on : 13 Nov 2017
Stage-I Approval on : 18 Jun 2018
Compliance Report Submitted by User Agency on : 18 Dec 2020
07 Jan 2021