List of Proposals accorded Stage-II Clearance (Proposals received on or after 15th July 2014)
Help
Using this report, you can view details of proposals (Received on or after 15th July 2014) .Click on   to print
 
Proposal Year :
Region : State :
Category : Status of the Proposal :
Enter value for Search :
Note :-All areas are in Hectares(ha.)
Sno.State NameProposal No.RO/Ministry File NumberProposal NameCategoryUser Agency NameArea (ha.)Proposal StatusImportant DatesAllocation of Fresh forest land (Form-A) Part-IView Report (Part-II to Part-V and Stage-I Clearances)Stage-II Approval on
1 Meghalaya FP/ML/MIN/8842/2014 3-MG B 027/2018-SHI Madan Pyrda Chiehruphi Block - 1 Mining GREEN VALLIEY INDUTRIES LIMITED 6.55 APPROVED
Proposal received(at Nodal Officer)electronically on : 29 Jul 2015
Stage-I Approval on : 14 Oct 2019
Compliance Report Submitted by User Agency on : 03 Dec 2020
30 Mar 2021
2 Meghalaya FP/ML/ROAD/10974/2015 3-MG C 042/2016-SHI Diversion of 14.138 hectares of deemed private forest land for Approch Road to Cement Plant and Residential Colony Development at Umsoo Mootang Thangskai Village, East Jaintia Hills District Road Adhunik Cement Ltd. 14.138 Pending at DFO for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 28 Oct 2015
Stage-I Approval on : 25 Apr 2019
Compliance Report Submitted by User Agency on : 06 Oct 2020
3 Meghalaya FP/ML/ROAD/40846/2019 3-MG B 113/2019-SHI Diversion of 16.107 Ha of Forest Land (15.296 Ha Protected Forest and 0.811 Ha Deemed Forest) at Upper Shillong Protected Forestbetween km 1+390 (2 1/2 Mile Upper Shillong) to km 8+980 (Pomlum PHC, Baniun) in the state of Meghalaya for improvement/ widening to 2-lane with paved shoulders/ 4 laning of stretch Shillong-Dawki road (km 0+000 to 71+520 Road NHIDCL 16.107 APPROVED
Proposal received(at Nodal Officer)electronically on : 26 Jun 2019
Stage-I Approval on : 06 Mar 2020
Compliance Report Submitted by User Agency on : 19 Mar 2021
18 Apr 2022
4 Meghalaya FP/ML/TRANS/38514/2019 3-MG B 042/2020-SHI CONSTRUCTION OF LOOP-IN SECTION OF 132 KV MLHEP-KHLERIHAT LINE AT MYNKRE Transmission Line MEGHALAYA POWER TRANSMISSION CORPORATION LIMITED 4.85 Pending at DFO for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 22 Jan 2019
Stage-I Approval on : 31 Mar 2022
Compliance Report Submitted by User Agency on : 19 Jul 2022
5 Meghalaya FP/ML/TRANS/39803/2019 3-MG B 111/2019-SHI 132KV AGIA-CHIBINANG-HATSINGIMARI TRANSMISSION LINE Transmission Line ASSAM ELECTRICITY GRID CORPORATION LIMITED(AEGCL) 4.563 APPROVED
Proposal received(at Nodal Officer)electronically on : 11 Apr 2019
Stage-I Approval on : 29 Jan 2021
Compliance Report Submitted by User Agency on : 22 Jan 2022
28 Jun 2022
6 Meghalaya FP/ML/ROAD/44918/2020 3-MG C 026/2021-SHI Diversion of 27.606 Ha of Baghmara Reserve Forest Land for up-gradation to 2-lane of State Highway (SH-04) stretch from Panda to Baghmara (from Existing km 119.800 to 139.00) (Design Length = 17.085 k Road NHIDCL 27.606 IN-PRINCIPLE
Proposal received(at Nodal Officer)electronically on : 05 Mar 2020
Stage-I Approval on : 03 Sep 2021
Compliance Report Submitted by User Agency on : 03 Mar 2022