Sno.State NameProposal No.RO/Ministry File NumberProposal NameCategoryUser Agency NameArea (ha.)Proposal StatusImportant DatesAllocation of Fresh forest land (Form-A) Part-IView Report (Part-II to Part-V and Stage-I Clearances)Stage-II Approval on
1 Maharashtra FP/MH/ROAD/13978/2015 FC-II/MH-73/2017-NGP Rehabilitation and upgradation of existing Buttibori-Wardha section of NH-361, km28.800-km80.000 to 4 lane configuration, in the state of Maharastra Road National Highways Authority of India 19.532 Pending at RO for Stage-II
Proposal received(at Nodal Officer)electronically on : 17 Jul 2015
Stage-I Approval on : 06 Nov 2017
Compliance Report Submitted by User Agency on : 22 Apr 2022
2 Maharashtra FP/MH/RAIL/6560/2014 FC-II/MH-72/2017-NGP Wardha-Nanded New Railway Line Railway Dy Chief Engineer (Construction) Wardha 19.06 Pending at RO for Stage-II
Proposal received(at Nodal Officer)electronically on : 20 Aug 2014
Stage-I Approval on : 24 May 2018
Compliance Report Submitted by User Agency on : 10 Aug 2022
3 Maharashtra FP/MH/ROAD/16793/2015 FC-II-MH-97-2018-NGP Four Laning of Aurangabad- Karodi Section of NH-211 designed with partial Green filed alignment as bypass to Aurangabad city in Aurangabad District Road National Highways Authority of India 11.78 Pending at RO for Stage-II
Proposal received(at Nodal Officer)electronically on : 06 Aug 2018
Stage-I Approval on : 25 Jan 2019
Compliance Report Submitted by User Agency on : 17 Mar 2022
4 Maharashtra FP/MH/WATER/39483/2019 FC-I/MH-173/2020-NGP Re-diversion on Forest land from NHAI to CIDCO of Survey No. 22pt and 15 pt Village Shitole Pen Dist Raigad Drinking Water CIDCO 0.079 Pending at RO for Stage-II
Proposal received(at Nodal Officer)electronically on : 19 Mar 2019
Stage-I Approval on : 07 Jan 2021
Compliance Report Submitted by User Agency on : 24 Jun 2022
5 Maharashtra FP/MH/ROAD/36105/2018 FC-I/MH-167/2019-NGP Improvements and Construction of Ahmednagar bypass of NH-222 from Km 0+000 to 40+150 In Maharashtra State Road NATIONAL HIGHWAYS AUTHORITY OF INDIA PIU AHMEDNAGAR 4.98 Pending at RO for Stage-II
Proposal received(at Nodal Officer)electronically on : 23 Sep 2018
Stage-I Approval on : 31 Mar 2021
Compliance Report Submitted by User Agency on : 12 Sep 2022
6 Maharashtra FP/MH/TRANS/43219/2019 FC-I/MH-222/2021-NGP 220 KV DC Vishwind Bhenda Transmission line Transmission Line MAHATRANSCO NASHIK 1.68 Pending at RO for Stage-II
Proposal received(at Nodal Officer)electronically on : 05 Dec 2019
Stage-I Approval on : 19 Apr 2021
Compliance Report Submitted by User Agency on : 04 Jul 2022
7 Maharashtra FP/MH/RAIL/25112/2017 FC-I/MH-102/2018-NGP Diversion of 4.0673Ha forest land for the Nerul Uran Rail Corridor-Phase-II ( Chainage 8000 to 11000 Mtr)Project Railway CITY AND INDUSTRIAL DEVELOPEMENT CORPORATION OF MAHARASHTRA LIMITED 4.0673 Pending at RO for Stage-II
Proposal received(at Nodal Officer)electronically on : 23 Mar 2017
Stage-I Approval on : 22 Apr 2021
Compliance Report Submitted by User Agency on : 26 Aug 2022
8 Maharashtra FP/MH/Others/43917/2020 FC-I/MH-241/2021-NGP CONSTRUCTION OF RESTAURANT, RESIDEDANCES ROAD ETC. Others SHRI. TUSHAR CHINTAMANI MENGALE 0.6804 Pending at RO for Stage-II
Proposal received(at Nodal Officer)electronically on : 16 Jan 2020
Stage-I Approval on : 30 Sep 2021
Compliance Report Submitted by User Agency on : 14 Sep 2022
9 Maharashtra FP/MH/ROAD/40239/2019 FC-II/MH-152/2021-NGP “Rehabilitation and Up-gradation of Patgaon to Khopoli Section I design Ch (km 43.783 to km 69.508) part of NH-3 Shahpur - Murbad – Mhasa – Karjat - Khopoli-NH4 section of newly declared NH-548 A in t Road MSRDC BANDRA MUMBAI 12.8957 Pending at RO for Stage-II
Proposal received(at Nodal Officer)electronically on : 14 May 2019
Stage-I Approval on : 26 Aug 2021
Compliance Report Submitted by User Agency on : 03 Aug 2022
10 Maharashtra FP/MH/WATER/21099/2016 FC-I/MH-147/2019-NGP GSR PROJECT AT GOKHALE NAGAR Drinking Water ESTATE AND MANAGEMENT DEPT PMC 0.432 Pending at RO for Stage-II
Proposal received(at Nodal Officer)electronically on : 23 Aug 2016
Stage-I Approval on : 30 Nov 2021
Compliance Report Submitted by User Agency on : 02 Sep 2022
11 Maharashtra FP/MH/Others/120374/2021 FC-I/MH-238/2021-NGP Diversion of 0.9950 Ha. Reserved Forest Land for Upgradation and proposed development of Nature trail at Gavlidev precinct for Navi Mumbai Municipal Corporation, Navi Mumbai, At Village Ghansoli Others NAVI MUMBAI MUNICIPAL CORPORATION 0.995 Pending at RO for Stage-II
Proposal received(at Nodal Officer)electronically on : 22 Jan 2021
Stage-I Approval on : 31 Dec 2021
Compliance Report Submitted by User Agency on : 11 Aug 2022
12 Maharashtra FP/MH/Others/35309/2018 FC-I/MH-227/2021-NGP Construction of Rope Suspension Bridge (Skywalk) connecting Hurricane Point and Goreghat Point at Chikhaldara Hill Station : Diversion of 0.872 HA Forest Land in Municipal Council Chikhaldara, District Amravati, Maharashtra Others CIDCO 0.9286 Pending at RO for Stage-II
Proposal received(at Nodal Officer)electronically on : 13 Aug 2018
Stage-I Approval on : 19 Jan 2022
Compliance Report Submitted by User Agency on : 13 Sep 2022
13 Maharashtra FP/MH/Others/148428/2021 FC-I/MH-271/2022-NGP Diversion of Forest Land 1.2 Ha to Non Forest Purposes I.E. Construction of Residencial Houses, Roads,Garden, Electric Line, etc. in Survey No120/1 of the Village Kune (Nama) Tal- Maval, Dist-Pune Others AJINKYA SHINDE 1.2 Pending at RO for Stage-II
Proposal received(at Nodal Officer)electronically on : 17 Oct 2021
Stage-I Approval on : 31 May 2022
Compliance Report Submitted by User Agency on : 14 Sep 2022