Sno. | State Name | Proposal No. | RO/Ministry File Number | Proposal Name | Category | User Agency Name | Area (ha.) | Proposal Status | Important Dates | Allocation of Fresh forest land (Form-A) Part-I | View Report (Part-II to Part-V and Stage-I Clearances) | Stage-II Approval on |
1
|
Gujarat
|
FP/GJ/Others/25303/2017
|
6-GJB021/2018-BHO
|
Proposal for laying OFC for Reliance Jio Infocomm Limited 4G Gir West Distriect
|
Others
|
RELIANCE JIO INFOCOMM LTD
|
1.6143
|
Pending With-SG for verifying Compliance of Conditions
|
Proposal received(at Nodal Officer)electronically on
|
:
|
25 Mar 2017
|
Stage-I Approval on
|
:
|
25 May 2018
|
Compliance Report Submitted by User Agency on
|
:
|
27 Sep 2023
|
|
|
|
|
2
|
Gujarat
|
FP/GJ/Others/33231/2018
|
6-GJB08/2019-BHO
|
Proposal for grant of permission for laying of 300 mm Ø DI RAW Water Supply Pipeline from Intake Well at Variav to Adani Wilmar Limited at Sunvali in Dist. Surat
|
Others
|
ADANI WILMAR LIMITED
|
0.8357
|
Pending With-SG for verifying Compliance of Conditions
|
Proposal received(at Nodal Officer)electronically on
|
:
|
20 Apr 2018
|
Stage-I Approval on
|
:
|
24 May 2019
|
Compliance Report Submitted by User Agency on
|
:
|
16 Jul 2019
|
|
|
|
|
3
|
Gujarat
|
FP/GJ/Others/32241/2018
|
FCA-1018/5-42/18/SF-163/F
|
To connect various domestic, commercial and industrial customers in surrounding areas of Palanpur city in Palanpur & Vadgam Taluka in Banaskantha District of Banaskantha GA.
|
Others
|
IRM ENERGY PRIVATE LIMITED
|
0.2409
|
Pending With-SG for verifying Compliance of Conditions
|
Proposal received(at Nodal Officer)electronically on
|
:
|
24 Feb 2018
|
Stage-I Approval on
|
:
|
26 Jun 2019
|
Compliance Report Submitted by User Agency on
|
:
|
23 Jan 2025
|
|
|
|
|
4
|
Gujarat
|
FP/GJ/ROAD/25121/2017
|
FCA-1019/7-05/19/SF-100/F
|
Proposal for diversion of 0.6750 ha. Reserved forest land for the project of Widening and Strengthening Construction of Kubada-Shivad Road (Village Road) K.M. 0/00 to 3/500 (Working Section 1/000 to 1/900) Village : Kubda Dist. Amreli in Gujarat State.
|
Road
|
R N B PANCHAYAT DIVISION AMRELI
|
0.675
|
Pending With-SG for verifying Compliance of Conditions
|
Proposal received(at Nodal Officer)electronically on
|
:
|
22 Mar 2017
|
Stage-I Approval on
|
:
|
07 Sep 2019
|
Compliance Report Submitted by User Agency on
|
:
|
26 Sep 2024
|
|
|
|
|
5
|
Gujarat
|
FP/GJ/Others/35053/2018
|
6-GJB043/2019-BHO
|
Proposal for laying OFC for Reliance Jio Infocomm Limited 4G Banaskantha District
|
Others
|
RELIANCE JIO INFOCOMM LTD
|
0.25
|
Pending With-SG for verifying Compliance of Conditions
|
Proposal received(at Nodal Officer)electronically on
|
:
|
30 Jul 2018
|
Stage-I Approval on
|
:
|
06 Dec 2019
|
Compliance Report Submitted by User Agency on
|
:
|
10 Aug 2022
|
|
|
|
|
6
|
Gujarat
|
FP/GJ/Others/42615/2019
|
6-GJB020/2020-BHO
|
Laying of underground power cable for electrification of ropeway project on girnar hill
|
Others
|
PGVCL JUNAGADH
|
2
|
Pending With-SG for verifying Compliance of Conditions
|
Proposal received(at Nodal Officer)electronically on
|
:
|
04 Nov 2019
|
Stage-I Approval on
|
:
|
30 Jun 2020
|
Compliance Report Submitted by User Agency on
|
:
|
05 Aug 2023
|
|
|
|
|
7
|
Gujarat
|
FP/GJ/OFC/48577/2020
|
6-GJB031/2021-BHO
|
Proposal for Diversion of 1.9 ha. Reserved forest land (ESZ) for the grant permission for laying GFGNL Optical Fiber Cable line along the Shoolpaneshwar sanctuary area in Ta. Dediyapada and Nandod, Dist. Narmada
|
Optical Fibre Cable
|
GFGNL
|
1.9
|
Pending With-SG for verifying Compliance of Conditions
|
Proposal received(at Nodal Officer)electronically on
|
:
|
12 Aug 2020
|
Stage-I Approval on
|
:
|
22 Apr 2021
|
Compliance Report Submitted by User Agency on
|
:
|
19 Jun 2024
|
|
|
|
|
8
|
Gujarat
|
FP/GJ/TRANS/146196/2021
|
FCA-1021/3-30/21/SF-246/F
|
66KV S/C (3+1) 630Sq.mm, underground cable from 220KV Otha Sub-station to 66KV Mahuva (Neswad) Sub-station.
|
Transmission Line
|
GUJARAT ENERGY TRANSMISSION CORP LTD
|
0.43252
|
Pending With-SG for verifying Compliance of Conditions
|
Proposal received(at Nodal Officer)electronically on
|
:
|
19 Aug 2021
|
Stage-I Approval on
|
:
|
06 Jan 2022
|
Compliance Report Submitted by User Agency on
|
:
|
26 Sep 2024
|
|
|
|
|
9
|
Gujarat
|
FP/GJ/TRANS/145120/2021
|
FCA-1021/3-20/21/SF-188/F
|
66KV S/C (3+1) 630 Sq. mm, UG Cable from 66KV Ghanghali – 3 S/S (GETCO S/S) to M/s.Prabodh steel Pvt. Ltd. village-Ghanghali,Ta. Sihor,Dist.Bhavnagar.
|
Transmission Line
|
GUJARAT ENERGY TRANSMISSION CORP LTD
|
0.15
|
Pending With-SG for verifying Compliance of Conditions
|
Proposal received(at Nodal Officer)electronically on
|
:
|
22 Jul 2021
|
Stage-I Approval on
|
:
|
06 Jan 2022
|
Compliance Report Submitted by User Agency on
|
:
|
26 Sep 2024
|
|
|
|
|
10
|
Gujarat
|
FP/GJ/TRANS/37923/2018
|
6-GJC042/2021-BHO
|
Erection of 66kV Tower line for 66kV Kalibel substation LILO from exist 66kV Waghai-Ahwa line
|
Transmission Line
|
GUJARAT ENERGY TRANSMISSION CORP LTD
|
6.642
|
Pending With-SG for verifying Compliance of Conditions
|
Proposal received(at Nodal Officer)electronically on
|
:
|
28 Dec 2018
|
Stage-I Approval on
|
:
|
25 Jan 2022
|
Compliance Report Submitted by User Agency on
|
:
|
26 Sep 2024
|
|
|
|
|
11
|
Gujarat
|
FP/GJ/ROAD/152422/2022
|
FC-6/GJC-39/2022-GNR
|
Widening & Strengthening of Talala to Ankolvadi road SH-98 between km. 69/000 to 53/000
|
Road
|
EXECUTIVE ENGINEER ROAD AND BUILDING DIVISION GIRSOMNATH
|
8.4
|
Pending With-SG for verifying Compliance of Conditions
|
Proposal received(at Nodal Officer)electronically on
|
:
|
15 Feb 2022
|
Stage-I Approval on
|
:
|
04 Jul 2022
|
Compliance Report Submitted by User Agency on
|
:
|
02 Jul 2024
|
|
|
|
|
12
|
Gujarat
|
FP/GJ/ROAD/43099/2019
|
FC-6/GJC-17/2022-GNR
|
Widening & Strengthening of existing B.T. Surface and reconstruction of cross drainage structure of Deshalpar Mandvi Naliya Narayansarovar road. (NH – 8A-Ext) Section : KM 226/200 to 242/500
|
Road
|
NATIONAL HIGHWAY DIVISION GANDHIDHAM
|
6.52
|
Pending With-SG for verifying Compliance of Conditions
|
Proposal received(at Nodal Officer)electronically on
|
:
|
01 Dec 2019
|
Stage-I Approval on
|
:
|
21 Jul 2022
|
Compliance Report Submitted by User Agency on
|
:
|
12 Feb 2025
|
|
|
|
|
13
|
Gujarat
|
FP/GJ/Pipeline/154945/2022
|
FCA-1022/5-17/22/SF-133/F
|
125 mm Dia MDPE Gas Pipeline Connectivity For Scoda Tubes ltd. Kadi Dist:Mehsana
|
Pipeline
|
SABARMATI GAS LIMITED
|
0.068
|
Pending With-SG for verifying Compliance of Conditions
|
Proposal received(at Nodal Officer)electronically on
|
:
|
27 Apr 2022
|
Stage-I Approval on
|
:
|
27 Jul 2022
|
Compliance Report Submitted by User Agency on
|
:
|
24 Sep 2024
|
|
|
|
|
14
|
Gujarat
|
FP/GJ/Others/50281/2020
|
FC-6/GJB-40/2022-GNR
|
Proposal for laying OFC for Jio Digital Fibre Pvt. Ltd. Patan District
|
Others
|
JIO DIGITAL FIBER PRIVATE LIMITED
|
0.2934
|
Pending With-SG for verifying Compliance of Conditions
|
Proposal received(at Nodal Officer)electronically on
|
:
|
30 Sep 2020
|
Stage-I Approval on
|
:
|
05 Sep 2022
|
Compliance Report Submitted by User Agency on
|
:
|
26 Apr 2024
|
|
|
|
|
15
|
Gujarat
|
FP/GJ/ROAD/148923/2021
|
FC-6/GJC-58/2022-GNR
|
Widening & Strengthening of Junagadh-Bhesan-Parab Vavdi Road
|
Road
|
DEPUTY EXECUTIVE ENGINEER-R&B CITY SUB DIVISION-JUNAGADH
|
17.24625
|
Pending With-SG for verifying Compliance of Conditions
|
Proposal received(at Nodal Officer)electronically on
|
:
|
30 Oct 2021
|
Stage-I Approval on
|
:
|
30 Oct 2022
|
Compliance Report Submitted by User Agency on
|
:
|
04 Jul 2024
|
|
|
|
|
16
|
Gujarat
|
FP/GJ/IND/29375/2017
|
FC-6/GJC-72/2023-GNR
|
Hazira Capacity Expansion Project (HCEP)
|
Industry
|
Shell Energy India Private Limited
|
12
|
Pending With-SG for verifying Compliance of Conditions
|
Proposal received(at Nodal Officer)electronically on
|
:
|
18 Sep 2019
|
Stage-I Approval on
|
:
|
05 Nov 2024
|
Compliance Report Submitted by User Agency on
|
:
|
07 May 2025
|
|
|
|
|