Using this report, you can view details of proposals (Received on or after 15th July 2014) .Click on   to print
 
Proposal Year :
Region : State :
Category : Status of the Proposal :
Enter value for Search :
Note :-All areas are in Hectares(ha.)
Sno.State NameProposal No.RO/Ministry File NumberProposal NameCategoryUser Agency NameArea (ha.)Proposal StatusImportant DatesAllocation of Fresh forest land (Form-A) Part-IView Report (Part-II to Part-V and Stage-I Clearances)Stage-II Approval on
1 Andhra Pradesh FP/AP/TRANS/22375/2016 GO.Rt.No.87, Dt:17.04.2017 Proposal for Erection of 33kv Transmission line from wind farm common point VCB yard at pattanagaram to 132/33kv substation of AP Transco grid at Banaganapaali, Kurnool District, A P. Transmission Line APSPDCL DHONE 0.85 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 18 Nov 2016
Stage-I Approval on : 17 Apr 2017
Compliance Report Submitted by User Agency on : 28 Jun 2017
2 Bihar FP/BR/Others/25228/2017 FP/BR/Others/25228/2017 Diversion of 0.00375 ha of forest land for construction of approach road for opening retail outlet of HPCL on Lalganj Road (SH-74) in Vaishali district of Bihar. Others SATRUDHAN KUMAR 0.00375 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 24 Mar 2017
Stage-I Approval on : 01 Jun 2017
Compliance Report Submitted by User Agency on : 14 Sep 2017
3 Bihar FP/BR/Others/20581/2016 FP/BR/Others/20581/2016 The road side land 0.0416 ha required only for the proposal to use as a approach road so that the vehicle can reach to retail outlet will supply petrol/Diesel to local people. Farmer for vehicle, pump sets. etc. Others RABINDRA KUMAR SHAHI 0.0416 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 21 Jul 2016
Stage-I Approval on : 25 Aug 2017
Compliance Report Submitted by User Agency on : 13 Sep 2017
4 Bihar FP/BR/Others/23520/2017 FP/BR/Others/23520/2017 The applicant on the Khaira-Sattarghat Road, Dist.-Saran. The road side land 0.0239 ha required only for the proposal to use as a approach road so that the vehicle can reach to retail outlet will supply petrol/Diesel to local people. Farmer for vehicle, pump sets. etc. Others BABITA DEVI 0.0239 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 09 Jan 2017
Stage-I Approval on : 29 Aug 2017
Compliance Report Submitted by User Agency on : 14 Sep 2017
5 Haryana FP/HR/Others/10771/2015 4981 NOC FOR ESTABLISHMENT OF NEW RETAIL OUTLET (KSK) OF INDIAN OIL CORPORATION LTD. ON MURABA NO. 105, KILA NO. 18 ON DABWALI-CHOUTALA ROAD(MDR-105), VILLAGE-ABUB SEHAR,TEHSIL-DABWALI,DISTT-SIRSA. Others INDIAN OIL CORPORATION LTD 0.0115 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 09 Mar 2015
Stage-I Approval on : 18 Sep 2015
Compliance Report Submitted by User Agency on : 23 Oct 2015
6 Haryana FP/HR/Others/13376/2015 5108 NOC for diversion of forest land of 0.0069 hectare area for our Retail Outlet at Bharog to Dahri Road, Village Bharog, Distt. Ambala (Haryana) Others IOCL PANIPAT DIVISIONAL OFFICE 0.0069 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 22 Jun 2015
Stage-I Approval on : 19 Nov 2015
Compliance Report Submitted by User Agency on : 23 Feb 2016
7 Haryana FP/HR/Others/14155/2015 5146 NOC for diversion of forest land of 0.0112 hectare area for our Retail Outlet between KM 2-8, on SH-7, near KM stone no. 6, Karnal – Ladwa Road, at Village Darar, District Karnal (Haryana) Others IOCL PANIPAT DIVISIONAL OFFICE 0.0112 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 25 Jul 2015
Stage-I Approval on : 08 Jan 2016
Compliance Report Submitted by User Agency on : 14 Jan 2016
8 Haryana FP/HR/ROAD/16294/2015 5203 Diversion of forest land for widening of NH-1 from 162 to 163 & KM 181 to 182 in Kurukshetra district as part of Six Laning NH-1. Road National Highways Authority of India 0.319 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 18 Nov 2015
Stage-I Approval on : 11 Feb 2016
Compliance Report Submitted by User Agency on : 29 Apr 2016
9 Haryana FP/HR/Others/10892/2015 5211 Diversion of 0.0129 ha of forest land for Retail Outlet at village- Behal, Khewat No.264/251, Khatoni No 666 Khasra no. 49//2O (10-10), 49//21 (5-12) on Bhiwani Road, SH12 Tehsil - Loharu District Bhiwani Haryana (Haryana). Others BHARAT PETROLEUM CORPORATION LIMITED 0.0129 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 13 Mar 2015
Stage-I Approval on : 29 Feb 2016
Compliance Report Submitted by User Agency on : 28 Mar 2016
10 Haryana FP/HR/Others/13906/2015 5119 NOC for diversion of forest land of 0.0191 hectare area for our Retail Outlet on Shehjadpur to old Saharanpur road, Village Bhogpur, Distt. Yamunanagar (Haryana) Others IOCL PANIPAT DIVISIONAL OFFICE 0.0191 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 14 Jul 2015
Stage-I Approval on : 14 Mar 2016
Compliance Report Submitted by User Agency on : 21 Mar 2016
11 Haryana FP/HR/Others/16315/2015 5240 DIVERSION OF FOREST LAND FOR ACCESS TO THE PROPOSED PETROL PUMP OF BHARAT PETROLEUM CORPORATION LTD. MDR 118 KM STONE 20.515 ON PUNDRI RAJOUND ROAD VILLAGE PAI DISTT KAITHAL (HARYANA)BEARING KHASRA NO 134//5/1. Others BHARAT PETROLEUM CORPORATION LIMITED 0.0159 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 31 Oct 2015
Stage-I Approval on : 22 Mar 2016
Compliance Report Submitted by User Agency on : 04 Apr 2016
12 Rajasthan FP/RJ/Others/11491/2015 8B/RAJ/09/42/2015 Construction of Diversion channel of Forest Nallah is an important and integral part of Baran city flood protection scheme. This diversion channel will divert the excess flood discharge from forest nallah to nalka nallah. Thus minimizing effect of floods in Baran city. Others WATER RESOURCE DIVISION IST BARAN 0.4273 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 09 Apr 2015
Stage-I Approval on : 10 Nov 2015
Compliance Report Submitted by User Agency on : 03 Mar 2016
01 Jan 2016
13 Rajasthan FP/RJ/ROAD/16289/2015 8B/RAJ/06/2016/FC “Construction of Approach Road for ESSAR OIL LTD. Proposed Retail Outlet along the Bikaner - Suratgarh Road (NH-15) between Chainage 91/961.00 – 92/006.00 at Murba No. 104/64, Killa No. 14/1, (Biswa 15/2, 16/1, 17/1, 23/1, 24/1 & 25), Village- Chak-1 BHD, Tehsil-Lunkaransar, District-Bikaner (Rajast Road ESSAR OIL LTD 0.126076 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 29 Oct 2015
Stage-I Approval on : 06 Jun 2017
Compliance Report Submitted by User Agency on : 20 Sep 2017
14 Uttar Pradesh FP/UP/ROAD/12507/2015 8B/UP/06/43/2015 The UPEIDA, Govt. of UP to develop 6 lanes expandable to 8 lanes Agra-Lucknow Expressway on EPC mode. Expressway is passing through 10 districts whereas diversion of forest land is involved in 09 divisions. Which are Agra, Firozabad, Mainpuri, Etawah, Auraiya, Kannauj, Kanpur, Unnao, Lucnow Road UTTAR PRADESH EXPRESSWAYS INDUSTRIAL DEVELOPMENT AUTHORITY (UPEIDA) 123.8253 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 26 Jun 2015
Stage-I Approval on : 12 Feb 2016
Compliance Report Submitted by User Agency on : 03 May 2016
15 Uttarakhand FP/UK/ROAD/8581/2014 1(305)/2015 Construction of Manau Kotli Sailakhan Chauna Motor Road (Length 3.00 KM) Road EXECUTIVE ENGINEER 0.801 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 17 Dec 2014
Stage-I Approval on : 19 Jan 2016
Compliance Report Submitted by User Agency on : 06 Apr 2017
16 Uttarakhand FP/UK/ROAD/10022/2015 1(547)/2015 The proposed road is for providing the connectivity to the village Manjuli with a population of 412. The road is located in Block Kirtinagar, District- Tehri (Uttarakhand). The total length of the road for fresh cutting is 5.825 Km. Road PMGSY PWD KIRTINAGAR 3.908 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 12 Feb 2015
Stage-I Approval on : 30 Oct 2015
Compliance Report Submitted by User Agency on : 19 May 2017
17 Uttarakhand FP/UK/ROAD/9436/2015 1(479)/2015 Connectivity of Kanda-Fafadiya Village Road PWD RAMNAGAR 1.05 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 22 Jan 2015
Stage-I Approval on : 30 Oct 2015
Compliance Report Submitted by User Agency on : 10 Aug 2017
18 Uttarakhand FP/UK/ROAD/12421/2015 1(489)/2015 under the state sector, in Atal Aadrarsh Gram Yojna, construction of new motor road from chattwapipal to jhirkoti of length 2 KM Road PUBLIC WORKS DEPARTMENT GOPESHWAR UTTARAKHAND 0.59 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 05 May 2015
Stage-I Approval on : 30 Oct 2015
Compliance Report Submitted by User Agency on : 28 Apr 2016
19 Uttarakhand FP/UK/ROAD/9967/2015 1(119)/2015 The praposed road is for providing the connectivity to the village Kimkhola and Gusain Gaon with a population of 448 and 272 respectively. The road is located in block Devprayag, District-Tehri (Uttarakhand).The total length of the road is 7.550 km. Road PMGSY PWD KIRTINAGAR 3.985 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 07 Feb 2015
Stage-I Approval on : 07 Nov 2015
Compliance Report Submitted by User Agency on : 14 Jun 2017
20 Uttarakhand FP/UK/ROAD/14233/2015 1(598)/2015 Proposed road is 1.75 Km.Beneficiary villag Sirsa provide connectivity to market place. Road PUBLIC WORK DEPARTMENT 0.9212 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 30 Jul 2015
Stage-I Approval on : 07 Nov 2015
Compliance Report Submitted by User Agency on : 03 Feb 2017
21 Uttarakhand FP/UK/ROAD/13812/2015 1(587)/2015 Construction of Devalidhar to Surang Motor Road Legislative Assembly Dhari at Nainital District Road PUBLIC WORKS DEPARTMENT 1.435 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 10 Jul 2015
Stage-I Approval on : 06 Nov 2015
Compliance Report Submitted by User Agency on : 05 Nov 2016
22 Uttarakhand FP/UK/ROAD/14845/2015 1(571)/2015 This road connect the saknayana talla clustur of saknayana village. this is the only one solution of the village. And all the alignment goes for the village is also goes from the forest land hence the forest land is required for the scheme. Road PWD 3.95 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 21 Aug 2015
Stage-I Approval on : 07 Nov 2015
Compliance Report Submitted by User Agency on : 24 Mar 2017
23 Uttarakhand FP/UK/ROAD/12733/2015 1(555)/2015 This project provide the shortest rout to village kathyur. Road PWD 4.86 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 18 May 2015
Stage-I Approval on : 07 Nov 2015
Compliance Report Submitted by User Agency on : 24 Mar 2017
24 Uttarakhand FP/UK/ROAD/11010/2015 1(604)/2015 This Project is Comes under Pradhan mantari Gram Sadak Yogna Norms. There is no other alternates except Forest Land to Connect this (Balli) Village. Road EXECUTIVE ENGINEER 0.2925 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 17 Mar 2015
Stage-I Approval on : 07 Nov 2015
Compliance Report Submitted by User Agency on : 26 Apr 2016
25 Uttarakhand FP/UK/ROAD/11083/2015 1(185)/2015 Construction of Almora Sainar Chan Motor Road (Length 3.875 KM) Road EXECUTIVE ENGINEER 0.965 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 25 Mar 2015
Stage-I Approval on : 06 Nov 2015
Compliance Report Submitted by User Agency on : 06 Apr 2017
26 Uttarakhand FP/UK/ROAD/10398/2015 1(124)/15 Construction of Road from Chunakhan to Madanwell upto water tank under at Kaladhungi Road PWD RAMNAGAR 1.872 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 28 Feb 2015
Stage-I Approval on : 14 May 2015
Compliance Report Submitted by User Agency on : 07 Jul 2017
27 Uttarakhand FP/UK/ROAD/9539/2015 1(205)/2015 Raigalband to Bigrakot motor road Road PMGSY LOHAGHAT 3.39 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 23 Jan 2015
Stage-I Approval on : 15 Jun 2015
Compliance Report Submitted by User Agency on : 14 Dec 2016
28 Uttarakhand FP/UK/ROAD/9496/2015 1(221)/2015 Barakot to Kothera Motor Road Road PMGSY LOHAGHAT 2.24 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 21 Jan 2015
Stage-I Approval on : 01 Jul 2015
Compliance Report Submitted by User Agency on : 14 Dec 2016
29 Uttarakhand FP/UK/ROAD/9524/2015 1(206)/2015 khetikhan to bungabirora motor road Road PMGSY LOHAGHAT 3.169 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 22 Jan 2015
Stage-I Approval on : 09 Jul 2015
Compliance Report Submitted by User Agency on : 14 Dec 2016
30 Uttarakhand FP/UK/ROAD/10529/2015 1(301)/2015 Connecting of 250+ habitation to Motor Road Under PMGSY. Road PUBLIC WORKS DEPARTMENT 0.9 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 28 Feb 2015
Stage-I Approval on : 09 Jul 2015
Compliance Report Submitted by User Agency on : 09 Jun 2017
31 Uttarakhand FP/UK/ROAD/11635/2015 1(333)/2015 This Road is proposed to connect the unconnected habitation such as Talla Tajpur-236, Malla tajpur-283 and Sungari-486 Yet not connected. Road PMGSY 3.87 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 13 Apr 2015
Stage-I Approval on : 29 Jul 2015
Compliance Report Submitted by User Agency on : 02 Jun 2017
32 Uttarakhand FP/UK/ROAD/10500/2015 1(427)/2015 70 meter paidal marg needs to connect villagers of pangot to main road. Road GRAM VIKAS ADHIKARI GRAM SABHA PANGOT NAINITAL 0.0222 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 07 Mar 2015
Stage-I Approval on : 14 Aug 2015
Compliance Report Submitted by User Agency on : 19 Jun 2017
33 Uttarakhand FP/UK/ROAD/7782/2014 1(461)/2015 A 300mtr span double lane RCC bridge is proposed to be constructed across the rawasan river on Laldhang-Mithiberi road. Road EXECUTIVE ENGINEER, PD PWD HARIDWAR 0.75 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 15 Nov 2014
Stage-I Approval on : 07 Sep 2015
Compliance Report Submitted by User Agency on : 08 Mar 2017
34 Uttarakhand FP/UK/ROAD/10888/2015 1(437)/2015 Connecting 250+ Habitation for Motor Road. Road PUBLIC WORKS DEPARTMENT 0.995 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 16 Mar 2015
Stage-I Approval on : 27 Aug 2015
Compliance Report Submitted by User Agency on : 02 Aug 2017
35 Uttarakhand FP/UK/ROAD/9323/2015 1(18)/2016 This bridge will be constructed for village khadrasi over Mandal river which will link to Km 174 of SH 9 under state sector. Road ENGINEER IN CHIEF, PUBLIC WORK DEPARTMENT, DEHRADUN 0.504 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 14 Jan 2015
Stage-I Approval on : 31 Mar 2016
Compliance Report Submitted by User Agency on : 22 Feb 2017
36 Uttarakhand FP/UK/ROAD/13888/2015 8B/UCP/06/251/2015/FC The village situated at a distance of 8 km from NH 121. there are no other option to conect this village by road witout goining in forest land. hence this proposal prepared in this regard. Road PWD 4.34 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 14 Jul 2015
Stage-I Approval on : 04 Apr 2016
Compliance Report Submitted by User Agency on : 24 Mar 2017
37 Uttarakhand FP/UK/ROAD/16876/2015 1(117)/2016 Construction Of Kheti Randoli Benital Motor Road Under State Sector. Proposed road providing connectivity to Kheti Randoli and incidentally other surrounding villages also get the benefit of this road having approximate population is 235. Road PWD CD GAIRSAIN 0.595 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 05 Dec 2015
Stage-I Approval on : 21 Apr 2016
Compliance Report Submitted by User Agency on : 15 Sep 2016
38 Uttarakhand FP/UK/ROAD/16105/2015 1(92)/2016 The new road of 03 km length (Actual length 2.75KM) is sanction to connect Sher inter college in Shomeshwar constituency under C.M.Ghosna no 261/2015. Road EXECUTIVE ENGINEER 0.405 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 11 Feb 2016
Stage-I Approval on : 26 May 2016
Compliance Report Submitted by User Agency on : 22 Apr 2017
39 Uttarakhand FP/UK/ROAD/10755/2015 1(152)/2016 Construction of motor road from Bungidhar-Mehalchori-Bachuwaban motor road to Hargad Road PWD GAIRSAIN 0.228 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 08 Mar 2015
Stage-I Approval on : 10 Jun 2016
Compliance Report Submitted by User Agency on : 15 Sep 2016
40 Uttarakhand FP/UK/ROAD/16278/2015 1(270)/2016 Improvement and construction of roads and road links brings multiple socio-economic benefits to the rural areas and results in forming a strong backbone for the agro-based economy. It will serve better connectivity in nearby villages. Road EECDPWDUKM 0.448 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 29 Oct 2015
Stage-I Approval on : 12 Aug 2016
Compliance Report Submitted by User Agency on : 08 May 2017
41 Uttarakhand FP/UK/ROAD/16280/2015 1(269)/2016 Improvement and construction of roads and road links brings multiple socio-economic benefits to the rural areas and results in forming a strong backbone for the agro-based economy. It will serve better connectivity in nearby villages. Road EECDPWDUKM 0.133 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 29 Oct 2015
Stage-I Approval on : 12 Aug 2016
Compliance Report Submitted by User Agency on : 08 May 2017
42 Uttarakhand FP/UK/ROAD/16276/2015 1(266)/2016 Improvement and construction of roads and road links brings multiple socio-economic benefits to the rural areas and results in forming a strong backbone for the agro-based economy. It will serve better connectivity in nearby villages. Road EECDPWDUKM 0.698 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 29 Oct 2015
Stage-I Approval on : 12 Aug 2016
Compliance Report Submitted by User Agency on : 08 May 2017
43 Uttarakhand FP/UK/ROAD/16840/2015 1(300)/2016 Improvement and construction of roads and road links brings multiple socio-economic benefits to the rural areas and results in forming a strong backbone for the agro-based economy. It will serve better connectivity in nearby villages. Road EECDPWDUKM 0.445 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 09 Dec 2015
Stage-I Approval on : 16 Sep 2016
Compliance Report Submitted by User Agency on : 04 May 2017
44 Uttarakhand FP/UK/ROAD/17937/2016 8B/UCP/06/141/2016 Ganiadoli Pali Naduli motor road Km 3 to Dholadhar motor road is sanction vide Uttarakhand Govt order no 4287/III(2)/15-06(CM.Ghosna)/2008 T.C. dated 18-05-2015. The length of the proposed road is 4.00 Km. The sanction cost of the project is Rs 140 Lacs. This road will provide road connectivity to M Road EXECUTIVE ENGINEER 0.405 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 10 Feb 2016
Stage-I Approval on : 23 Sep 2016
Compliance Report Submitted by User Agency on : 15 Jul 2017
45 Uttarakhand FP/UK/ROAD/18403/2016 1(170)/2016 A new road of 3.00 Km length is sanction to connect Village Bayedi vide Uttarakhand Govt G.O. No 743/III(2)/15-46(Pra Aa)/2013 dated 31-01-2015. Road EXECUTIVE ENGINEER 0.945 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 10 Mar 2016
Stage-I Approval on : 30 Sep 2016
Compliance Report Submitted by User Agency on : 16 Jul 2017
46 Uttarakhand FP/UK/ROAD/7806/2014 8B/UCP/06/16/2016/FC Construction of Deman to desau Motor Road Under PMGSY scheme of length 12.675.This road will connect the villages Desau and Ataliyo of having population more than 563 . Road EXECUTIVE ENGINEER 5.868 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 31 Oct 2014
Stage-I Approval on : 25 Nov 2016
Compliance Report Submitted by User Agency on : 29 Aug 2017
47 Uttarakhand FP/UK/ROAD/18567/2016 1(291)/2016 Road construction for the caring farmers crop-products from their village to mandi for gaining good prices of their crops & become a Economically strong as well Road UTTARAKHAND KIRSHI UTPADAN MARKETING BOARD HALDWANI 0.98 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 09 Apr 2016
Stage-I Approval on : 29 Nov 2016
Compliance Report Submitted by User Agency on : 22 Feb 2017
48 Uttarakhand FP/UK/ROAD/9910/2015 1162/x-4-15/1(165)/2015 Construction of kujyari to dilkot motor road (length 1.00 Km.) Road EXECUTIVE ENGINEER 0.308 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 06 Feb 2015
Stage-I Approval on : 06 Nov 2015
Compliance Report Submitted by User Agency on : 03 Aug 2017
49 Uttarakhand FP/UK/ROAD/21566/2016 1(387)/2016 An approach road from gujjarbasti existing road to basaochandpur village is to be constructed under Chief Minister's declaration Road EXECUTIVE ENGINEER, PD PWD HARIDWAR 0.675 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 24 Sep 2016
Stage-I Approval on : 28 Dec 2016
Compliance Report Submitted by User Agency on : 29 Jun 2017
50 Uttarakhand FP/UK/ROAD/21733/2016 1(01)/2017 Construction of 21 Mtr Span Bridge at Km 173 on NH-94 Road NATIONAL HIGHWAY AUTHORTY OF INDIA PIU DEHRADUN 0.036 Pending With-SG for verifying Compliance of Conditions
Proposal received(at Nodal Officer)electronically on : 04 Oct 2016
Stage-I Approval on : 25 Jan 2017
Compliance Report Submitted by User Agency on : 19 Jun 2017