Ministry of Environment,Forest and Climate Change
Government of India
West Bengal
State Forest Department
List of Proposals accorded Stage-II Clearance (Proposals received on or after 15th July 2014)
Help
Using this report, you can view details of proposals (Received on or after 15th July 2014) .Click on   to print
 
Proposal Year :
Region : State :
Category : Status of the Proposal :
Enter value for Search :
Note :-All areas are in Hectares(ha.)
Sno.State NameProposal No.RO/Ministry File NumberProposal NameCategoryUser Agency NameArea (ha.)Proposal StatusImportant DatesAllocation of Fresh forest land (Form-A) Part-IView Report (Part-II to Part-V and Stage-I Clearances)Stage-II Approval on
1 West Bengal FP/WB/Others/43857/2020 WB/PFD-49/2021/FC Development of a Tourism Complex in Murguma Others DISTRICT MAGISTRATE, PURULIA 0.99 APPROVED
Proposal received(at Nodal Officer)electronically on : 10 Jan 2020
Stage-I Approval on : 04 Feb 2022
Compliance Report Submitted by User Agency on : 23 Mar 2022
27 Apr 2022
2 West Bengal FP/WB/ROAD/30060/2017 5-WBC101/2018-BHU Construction of twin 2-lane ROB and its approaches in replacement of existing Level Crossing Gate No.KA-38 (Railway Km.165/21-165/23) between Chandrakona Road and Garbeta Station in Kadamdiha at Km. 159.448 of NH-60 in the State of West Bengal. Road NH WING OF PUBLIC WORKS ROADS DIRECTORATE GOVT OF WEST BENGAL 9.533 APPROVED
Proposal received(at Nodal Officer)electronically on : 27 Nov 2017
Stage-I Approval on : 25 Jun 2018
Compliance Report Submitted by User Agency on : 23 Feb 2022
26 Apr 2022
3 West Bengal FP/WB/Others/42866/2019 5-WBB111/2020-BHU Jagdishpur-Haldia-Bokaro-Dhamra Pipeline (JHBDPL) Underground Project of GAIL- Others GAIL INDIA LIMITED 0.645 APPROVED
Proposal received(at Nodal Officer)electronically on : 23 Nov 2019
Stage-I Approval on : 07 Sep 2020
Compliance Report Submitted by User Agency on : 13 Sep 2021
13 Apr 2022
4 West Bengal FP/WB/Others/40606/2019 5-WBB105/2019-BHU Jagdishpur-Haldia-Bokaro-Dhamra Pipeline (JHBDPL) Underground Project of GAIL Others GAIL INDIA LIMITED 2.7279 APPROVED
Proposal received(at Nodal Officer)electronically on : 11 Jun 2019
Stage-I Approval on : 01 Jan 2020
Compliance Report Submitted by User Agency on : 18 Sep 2020
24 Dec 2020
5 West Bengal FP/WB/Others/26946/2017 5-WBB102/2018-BHU Augmentation of Paradip-Haldia-Durgapur LPG Pipeline and its extension up to Patna and Muzaffarpur Others Indian Oil Corporation Limited (Pipelines Division) 0.562 APPROVED
Proposal received(at Nodal Officer)electronically on : 04 Jul 2017
Stage-I Approval on : 05 Nov 2018
Compliance Report Submitted by User Agency on : 29 Mar 2019
07 Jun 2019
6 West Bengal FP/WB/ROAD/26127/2017 5-WBB096/2017-BHU Construction of twins 2-lane ROB and its approaches in replacement of level crossing at Km. 652.600 on NH-31 (Railway Km. 20/7-8) between Neora & Lataguri at Lataguri in the state of West Bengal. Road NH WING OF PUBLIC WORKS ROADS DIRECTORATE GOVT OF WEST BENGAL 4.031 APPROVED
Proposal received(at Nodal Officer)electronically on : 11 May 2017
Stage-I Approval on : 20 Sep 2017
Compliance Report Submitted by User Agency on : 26 Jun 2018
21 Dec 2018
7 West Bengal FP/WB/TRANS/16943/2015 5-WBC093/2016-BHU 400kV D/C PURULIA-RANCHI TRANSMISSION LINE (PURULIA & KHARAGPUR TRANSMISSION COMPANY LIMITED) Transmission Line PURULIA KHARAGPUR TRANSMISSION COMPANY LIMITED 12.288 APPROVED
Proposal received(at Nodal Officer)electronically on : 16 Dec 2015
Stage-I Approval on : 22 Sep 2016
Compliance Report Submitted by User Agency on : 16 Jul 2018
28 Sep 2018
8 West Bengal FP/WB/TRANS/9287/2015 5-WBC092/2016-BHU Construction of 400kv Punatsangchu Alipurduaraar transmission line Transmission Line POWERGRID CORPORATION OF INDIA LTD 16.39 APPROVED
Proposal received(at Nodal Officer)electronically on : 13 Jan 2015
Stage-I Approval on : 22 Jun 2016
Compliance Report Submitted by User Agency on : 16 Oct 2017
22 Nov 2017
Please wait ...