Sno. | State Name | Proposal No. | RO/Ministry File Number | Proposal Name | Category | User Agency Name | Area (ha.) | Proposal Status | Important Dates | Allocation of Fresh forest land (Form-A) Part-I | View Report (Part-II to Part-V and Stage-I Clearances) | Stage-II Approval on |
1
|
Orissa
|
FP/OR/Others/23166/2016
|
5-ORC496/2022-BHU
|
: Kalamang (Sagasahi)-Dabuna Slurry& Water Pipelines Project of M/s Essar Steel India Ltd.
|
Others
|
ArcelorMittal Nippon Steel India Limited
|
16.466
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
20 Dec 2016
|
Stage-I Approval on
|
:
|
25 Jan 2022
|
Compliance Report Submitted by User Agency on
|
:
|
16 May 2025
|
|
|
|
27 May 2025
|
2
|
Orissa
|
FP/OR/TRANS/153797/2022
|
5-ORC576/2023-BHU
|
2X160 MVA ,220/132 KV & 2X20 MVA, 220/33KV Grid Substation with associated 220 KV DC line from 400/200 KV PGCIL Grid Substation, Keonjhar to Turumunga & 132 KV LILO line from 132 KV Polaspanga-Karanjia SC line to Turumunga, Keonjhar
|
Transmission Line
|
ODISHA POWER TRANSMISSION CORPORATION LIMITED
|
8.435
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
31 Mar 2022
|
Stage-I Approval on
|
:
|
14 Mar 2024
|
Compliance Report Submitted by User Agency on
|
:
|
29 Apr 2025
|
|
|
|
06 May 2025
|
3
|
Orissa
|
FP/OR/IND/12884/2015
|
5-ORC279/2016-BHU
|
NTPC LTD., DARLIPALI SUPER THERMAL POWER PROJECT
|
Industry
|
NTPC LTD DARLIPALI SUPER THERMAL POWER PROJECT
|
25.76
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
25 May 2015
|
Stage-I Approval on
|
:
|
01 Nov 2016
|
Compliance Report Submitted by User Agency on
|
:
|
11 Apr 2025
|
|
|
|
24 Apr 2025
|
4
|
Orissa
|
FP/OR/Others/147445/2021
|
5-ORC548/2023-BHU
|
Srikakulam - Angul Pipeline (SAPL)Project_Mainline
|
Others
|
GAIL INDIA LIMITED
|
6.1487
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
21 Sep 2021
|
Stage-I Approval on
|
:
|
17 Feb 2023
|
Compliance Report Submitted by User Agency on
|
:
|
03 Feb 2025
|
|
|
|
14 Feb 2025
|
5
|
Orissa
|
FP/OR/ROAD/150863/2022
|
5-ORC543/2022-BHU
|
Improvement of Road from Kharabhuin PWD road chhak to Khandahata P.S.road via-Sankulei, Ghantabania, Panasaputuli road for the year 2018-19
|
Road
|
EXECUTIVE ENGINEER RURAL WORKS DIVISION BOUDH
|
6.098
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
06 Jan 2022
|
Stage-I Approval on
|
:
|
18 Jan 2023
|
Compliance Report Submitted by User Agency on
|
:
|
16 Dec 2024
|
|
|
|
14 Jan 2025
|
6
|
Orissa
|
FP/OR/TRANS/119219/2021
|
5-ORC473/2021-BHU
|
33 K.V power line corridor on N.B.L.S tower from 220/33kV grid sub-station at Khairiput, Govindpalli of OPTCL to 33kV sub-station site near Saptadhara H.E.P of Avantika Power Projects
|
Transmission Line
|
SRI AVANTIKA POWER PROJECTS LIMITED
|
10.803
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
18 Jan 2021
|
Stage-I Approval on
|
:
|
03 Nov 2021
|
Compliance Report Submitted by User Agency on
|
:
|
28 Nov 2024
|
|
|
|
14 Jan 2025
|
7
|
Orissa
|
FP/OR/ROAD/52400/2020
|
5-ORB479/2021-BHU
|
Diversion of 2.62 Hectre forest land for Construction of 4 lane carriage way with service road of Belpahar bypass from Km 0/0 to Km 2/971 for the year 2019-20 Under MCL fund
|
Road
|
EXECUTIVE ENGINEER ROAD AND BUILDING DIVSION JHARSUGDA
|
2.622
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
03 Nov 2020
|
Stage-I Approval on
|
:
|
17 Mar 2022
|
Compliance Report Submitted by User Agency on
|
:
|
30 Dec 2024
|
|
|
|
14 Jan 2025
|
8
|
Orissa
|
FP/OR/RAIL/45694/2020
|
5-ORA528/2022-BHU
|
Khurda Road - Bolangir New BG Rail Link Project i.e. from Km112-180
|
Railway
|
EAST COAST RAILWAY
|
594.618
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
05 Jun 2020
|
Stage-I Approval on
|
:
|
13 Feb 2023
|
Compliance Report Submitted by User Agency on
|
:
|
18 Dec 2024
|
|
|
|
13 Jan 2025
|
9
|
Orissa
|
FP/OR/Pipeline/123665/2021
|
5-ORB549/2023-BHU
|
Paradip - Numaligarh Crude Oil Pipeline (PNCPL) Project
|
Pipeline
|
NUMALIGARH REFINERY LIMITED
|
3.347
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
23 Feb 2021
|
Stage-I Approval on
|
:
|
28 Mar 2023
|
Compliance Report Submitted by User Agency on
|
:
|
07 Dec 2024
|
|
|
|
18 Dec 2024
|
10
|
Orissa
|
FP/OR/ROAD/154639/2022
|
5-ORC627/2024-BHU
|
CONSTRUCTION OF PROPOSED APPROACH ROAD FROM JUMKA PAHAR BLOCK OF RUNGTA MINES LTD TO THE EXISTING KOIRA BELAKUDAR PATAMUNDA ROAD
|
Road
|
RUNGTA MINES LTD
|
13.077
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
20 Apr 2022
|
Stage-I Approval on
|
:
|
25 Jan 2024
|
Compliance Report Submitted by User Agency on
|
:
|
12 Nov 2024
|
|
|
|
30 Nov 2024
|
11
|
Orissa
|
FP/OR/Others/30598/2017
|
5-ORB539/2022-BHU
|
Underground Water Pipeline & 11KV Power line fro Karo River to Steel Plant of M/s SREE METALIKS LIMITED situated at Village Loidapada ,Dist Keonjhar,Odisha
|
Others
|
SREE METALIKS LTD
|
0.764
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
14 Dec 2017
|
Stage-I Approval on
|
:
|
17 Apr 2023
|
Compliance Report Submitted by User Agency on
|
:
|
25 Oct 2024
|
|
|
|
20 Nov 2024
|
12
|
Orissa
|
FP/OR/Others/149695/2021
|
5-ORA620/2023-BHU
|
NALCO Conveyor Cooridor System
|
Others
|
NALCO
|
41.297
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
29 Nov 2021
|
Stage-I Approval on
|
:
|
22 Dec 2023
|
Compliance Report Submitted by User Agency on
|
:
|
09 Jul 2024
|
|
|
|
23 Sep 2024
|
13
|
Orissa
|
FP/OR/IRRIG/12758/2015
|
5-ORC292/2016-BHU
|
SANDUL IRRIGATION PROJECT
|
Irrigation
|
KALAHANDI INVESTIGATION DIVISION
|
7.535
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
14 Sep 2015
|
Stage-I Approval on
|
:
|
18 Nov 2016
|
Compliance Report Submitted by User Agency on
|
:
|
20 Jul 2024
|
|
|
|
10 Sep 2024
|
14
|
Orissa
|
FP/OR/IND/45465/2020
|
5-ORC568/2023-BHU
|
3.00 MMTPA Alumina Refinery with 150 MW co-generation Power Plant at Kansariguda in Rayagada district, Odisha by M/s Hindalco Industries Limited-Aditya Alumina Refinery Project
|
Industry
|
ADITYA ALUMINIUM
|
38.062
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
26 May 2020
|
Stage-I Approval on
|
:
|
29 Dec 2023
|
Compliance Report Submitted by User Agency on
|
:
|
16 Jul 2024
|
|
|
|
28 Aug 2024
|
15
|
Orissa
|
FP/OR/TRANS/156567/2022
|
5-ORB589/2023-BHU
|
CONSTRUCTION OF 11KV OVERHEAD TRANSMISSION LINE FROM JALDIHI VILLAGE TO JUMKA PATHIRIPOSHI PAHAR IRON ORE BLOCK OF MS RUNGTA MINES LIMITED
|
Transmission Line
|
RUNGTA MINES LTD
|
3.104
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
08 Jun 2022
|
Stage-I Approval on
|
:
|
22 Dec 2023
|
Compliance Report Submitted by User Agency on
|
:
|
03 Aug 2024
|
|
|
|
23 Aug 2024
|
16
|
Orissa
|
FP/OR/RAIL/29907/2017
|
5-ORA374/2019-BHU
|
Khurda Road Bolangir New B.G. Raillink Project Phase-II i.e. from 238-289
|
Railway
|
EAST COAST RAILWAY
|
69.77
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
06 Nov 2017
|
Stage-I Approval on
|
:
|
20 Aug 2019
|
Compliance Report Submitted by User Agency on
|
:
|
30 Jul 2024
|
|
|
|
16 Aug 2024
|
17
|
Orissa
|
FP/OR/ROAD/23286/2016
|
5-ORC332/2017-BHU
|
Widening to two lane carriage way from 327/700 to 413/700km of NH-326 (erstwhile form 16/0 to 102/000 of SH-25) under Vijayawada – Ranchi corridor with state Koraput & Malkangiri district in the state of Odisha
|
Road
|
EXECUTIVE ENGINEER, NH DIVISION, JEYPORE
|
10.635
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
28 Dec 2016
|
Stage-I Approval on
|
:
|
05 Mar 2018
|
Compliance Report Submitted by User Agency on
|
:
|
27 Jun 2024
|
|
|
|
30 Jul 2024
|
18
|
Orissa
|
FP/OR/TRANS/33277/2018
|
5-ORC406/2020-BHU
|
Odisha Power Transmission Corporation Limited (OPTCL)
|
Transmission Line
|
OPTCL
|
7.184
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
23 Apr 2018
|
Stage-I Approval on
|
:
|
14 Sep 2020
|
Compliance Report Submitted by User Agency on
|
:
|
24 Jun 2024
|
|
|
|
25 Jul 2024
|
19
|
Orissa
|
FP/OR/RAIL/20055/2016
|
5-ORC349/2018-BHU
|
NTPC LTD,DARLIPALI SUPER THERMAL POWER PROJECT
|
Railway
|
NTPC LTD DARLIPALI SUPER THERMAL POWER PROJECT
|
19.43
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
20 Jun 2016
|
Stage-I Approval on
|
:
|
18 Jun 2018
|
Compliance Report Submitted by User Agency on
|
:
|
24 May 2024
|
|
|
|
26 Jun 2024
|
20
|
Orissa
|
FP/OR/Others/32590/2018
|
5-ORB399/2019-BHU
|
Installation of pipeline over a length 4.748 km for drawal of water from river Mahanadi to Boudh Distillery in Odisha
|
Others
|
BOUDH DISTILLERY PVT LTD
|
0.966
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
20 Mar 2018
|
Stage-I Approval on
|
:
|
04 Dec 2019
|
Compliance Report Submitted by User Agency on
|
:
|
25 Apr 2024
|
|
|
|
31 May 2024
|
21
|
Orissa
|
FP/OR/IRRIG/22787/2016
|
5-ORC345/2018-BHU
|
For Construction of Additional Spillway of Hirakud Dam Project, Burla
|
Irrigation
|
EXECUTIVE ENGGINEER MAIN DAM DIVISION BURLA
|
9.441
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
01 Dec 2016
|
Stage-I Approval on
|
:
|
01 May 2018
|
Compliance Report Submitted by User Agency on
|
:
|
14 May 2024
|
|
|
|
28 May 2024
|
22
|
Orissa
|
FP/OR/Others/31590/2018
|
5-ORC481/2021-BHU
|
Dabuna – Sankari Tailing & Water Pipelines Project of M/s Essar Steel India Limited.
|
Others
|
ArcelorMittal Nippon Steel India Limited
|
12.728
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
03 Feb 2018
|
Stage-I Approval on
|
:
|
28 Dec 2021
|
Compliance Report Submitted by User Agency on
|
:
|
09 May 2024
|
|
|
|
28 May 2024
|
23
|
Orissa
|
FP/OR/TRANS/38533/2019
|
5-ORC416/2020-BHU
|
Construction of 220 KV Lilo Transmission line from LOC No. 331 of Existing 220 KV Rengali Tarkera Line to proposed 220/ 33 KV Grid Sub-station at Deogarh.
|
Transmission Line
|
OPTCL
|
21.159
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
23 Jan 2019
|
Stage-I Approval on
|
:
|
25 Jun 2020
|
Compliance Report Submitted by User Agency on
|
:
|
23 Apr 2024
|
|
|
|
21 May 2024
|
24
|
Orissa
|
FP/OR/Approach/64022/2020
|
5-ORB460/2021-BHU
|
CONSTRUCTION OF RESIDENTIAL AND SERVICE BUILDINGS AND ALLIED INFRASTRUCTURE FOR SHIFTING OF EXPLORATION CAMP FROM GOPALPUR, DIST-SUNDARGARH TO LAKHANPUR, DIST- JHARSUGUDA
|
Approach Access
|
CENTRAL MINE PLANNING AND DESIGN INSTITUTE LIMITED
|
0.047
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
27 Nov 2020
|
Stage-I Approval on
|
:
|
04 May 2021
|
Compliance Report Submitted by User Agency on
|
:
|
12 Mar 2024
|
|
|
|
21 May 2024
|
25
|
Orissa
|
FP/OR/Others/154167/2022
|
5-ORB530/2022-BHU
|
Proposal for Diversion of 0.700 hectares of forest area Proposed Water Conductor System from Mandira Dam to Power House Point of M/s. GEDCOL SAIL Power Corporation Limited near Laing village of Rajgan
|
Others
|
GEDCOL SAIL POWER CORPORATION LIMITED
|
0.7
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
10 Apr 2022
|
Stage-I Approval on
|
:
|
20 Apr 2023
|
Compliance Report Submitted by User Agency on
|
:
|
25 Mar 2024
|
|
|
|
24 Apr 2024
|
26
|
Orissa
|
FP/OR/TRANS/38561/2019
|
5-ORC417/2020-BHU
|
Construction of 132 KV Transmission Line from 400/220/132 KV Grid Sub-Station at- Lapanga to Proposed RTSS at- Rengali.
|
Transmission Line
|
OPTCL
|
6.278
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
25 Jan 2019
|
Stage-I Approval on
|
:
|
25 Jun 2020
|
Compliance Report Submitted by User Agency on
|
:
|
24 Jan 2024
|
|
|
|
15 Apr 2024
|
27
|
Orissa
|
FP/OR/ROAD/42674/2019
|
5-ORB414/2020-BHU
|
Approach Road
|
Road
|
INDIAN OIL, JAJPUR
|
0.04
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
29 Oct 2019
|
Stage-I Approval on
|
:
|
18 May 2020
|
Compliance Report Submitted by User Agency on
|
:
|
28 Mar 2024
|
|
|
|
13 Apr 2024
|
28
|
Orissa
|
FP/OR/ROAD/31054/2017
|
5-ORC463/2021-BHU
|
Widening of existing 2-lane to 2-lane with 1.5m. wide paved shoulder from Km 0/0 to 81/00 & 93/0 to 119/0 of N.H-157 on EPC mode.
|
Road
|
EXECUTIVE ENGINEER NH DIVISION SAMBALPUR
|
27.343
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
30 Dec 2017
|
Stage-I Approval on
|
:
|
28 Dec 2021
|
Compliance Report Submitted by User Agency on
|
:
|
19 Feb 2024
|
|
|
|
14 Mar 2024
|
29
|
Orissa
|
FP/OR/SCH/26930/2017
|
5-ORB425/2020
|
Kalinga Institute of Social Sciences, a sister concern of KIIT
|
School
|
KALINGA INSTITUTE SOCIAL SCIENCES
|
4.032
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
03 Jul 2017
|
Stage-I Approval on
|
:
|
17 Sep 2021
|
Compliance Report Submitted by User Agency on
|
:
|
15 Feb 2024
|
|
|
|
21 Feb 2024
|
30
|
Orissa
|
FP/OR/ROAD/154500/2022
|
5-ORB540/2022-BHU
|
Proposed Approach Road
|
Road
|
TATA STEEL LIMITED KHONDBOND IRON AND MN MINES
|
0.051
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
15 Apr 2022
|
Stage-I Approval on
|
:
|
31 Jan 2023
|
Compliance Report Submitted by User Agency on
|
:
|
05 Feb 2024
|
|
|
|
20 Feb 2024
|
31
|
Orissa
|
FP/OR/IND/16543/2015
|
5-ORB477/2021-BHU
|
Expansion of Line-II at Jharsuguda Cement Works (JCW)
|
Industry
|
ULTRATECH CEMENT LIMITED
|
0.799
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
25 Nov 2015
|
Stage-I Approval on
|
:
|
03 Dec 2021
|
Compliance Report Submitted by User Agency on
|
:
|
27 Dec 2023
|
|
|
|
25 Jan 2024
|
32
|
Orissa
|
FP/OR/MIN/149706/2021
|
5-ORB552/2023-BHU
|
Diversion of 0.03 Ha forest land involved in Safety Zone Area of Roida II Iron Ore Block for passing through of approach road into the mine
|
Mining
|
NARBHERAM POWER AND STEEL PRIVATE LIMITED
|
0.03
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
02 Dec 2021
|
Stage-I Approval on
|
:
|
28 Mar 2023
|
Compliance Report Submitted by User Agency on
|
:
|
06 Oct 2023
|
|
|
|
23 Jan 2024
|
33
|
Orissa
|
FP/OR/TRANS/37011/2018
|
5-ORC448/2021-BHU
|
220 KV TRANSMISSION LINE FROM EXISTING 220/132/33KV GRID SUBSTATION AT SADEIPALI,BOLANGIR TO PROPOSED 220/132 KV GRID SUB-STATION AT KESINGA.
|
Transmission Line
|
ODISHA POWER TRANSMISSION CORPORATION LIMITED
|
39.196
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
20 Nov 2018
|
Stage-I Approval on
|
:
|
16 Mar 2021
|
Compliance Report Submitted by User Agency on
|
:
|
28 Nov 2023
|
|
|
|
02 Jan 2024
|
34
|
Orissa
|
FP/OR/TRANS/37011/2018
|
5-ORC448/2021-BHU
|
220 KV TRANSMISSION LINE FROM EXISTING 220/132/33KV GRID SUBSTATION AT SADEIPALI,BOLANGIR TO PROPOSED 220/132 KV GRID SUB-STATION AT KESINGA.
|
Transmission Line
|
ODISHA POWER TRANSMISSION CORPORATION LIMITED
|
39.196
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
20 Nov 2018
|
Stage-I Approval on
|
:
|
16 Mar 2021
|
Compliance Report Submitted by User Agency on
|
:
|
28 Nov 2023
|
|
|
|
02 Jan 2024
|
35
|
Orissa
|
FP/OR/IND/40650/2019
|
5-ORC469/2021-BHU
|
Establishment of Industries i.e. Expansion of Existing Red Mud Pond.
|
Industry
|
IDCO
|
15.265
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
20 Jun 2019
|
Stage-I Approval on
|
:
|
17 Nov 2021
|
Compliance Report Submitted by User Agency on
|
:
|
06 Nov 2023
|
|
|
|
29 Dec 2023
|
36
|
Orissa
|
FP/OR/MIN/150051/2021
|
5-ORC545/2023-BHU
|
Diversion of 34.162 Ha virgin forest land under section 2(ii) of Forest Conservation Act, 1980 for Mining and ancillary activities within Pureibahal Iron ore block of M/s Rungta Mines Limited.
|
Mining
|
RUNGTA MINES LTD
|
34.162
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
10 Dec 2021
|
Stage-I Approval on
|
:
|
11 May 2023
|
Compliance Report Submitted by User Agency on
|
:
|
08 Dec 2023
|
|
|
|
18 Dec 2023
|
37
|
Orissa
|
FP/OR/TRANS/38138/2019
|
5-ORC421/2020-BHU
|
33 KV Power Transmission overhead line from NTPC, Darlipali to OCPL Sub-Station
|
Transmission Line
|
ODISHA COAL AND POWER LIMITED
|
5.777
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
11 Jan 2019
|
Stage-I Approval on
|
:
|
31 Jul 2020
|
Compliance Report Submitted by User Agency on
|
:
|
14 Nov 2023
|
|
|
|
18 Dec 2023
|
38
|
Orissa
|
FP/OR/RAIL/37351/2018
|
5-ORC405/2020-BHU
|
SAMBALPUR-TITLAGARH DOUBLING RAILWAY PROJECT
|
Railway
|
EAST COAST RAILWAY
|
10.42
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
03 Dec 2018
|
Stage-I Approval on
|
:
|
17 Apr 2020
|
Compliance Report Submitted by User Agency on
|
:
|
27 Sep 2023
|
|
|
|
13 Oct 2023
|
39
|
Orissa
|
FP/OR/ROAD/138455/2021
|
5-ORB535/2022-BHU
|
For construction of road & 33 KV Transmission Line connecting Roida-II Iron Ore Block of M/s. Narbheram Power And Steel Private Limited to NH- 215 Keonjhar District
|
Road
|
NARBHERAM POWER AND STEEL PRIVATE LIMITED
|
0.978
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
19 Mar 2021
|
Stage-I Approval on
|
:
|
03 Feb 2023
|
Compliance Report Submitted by User Agency on
|
:
|
22 Aug 2023
|
|
|
|
12 Oct 2023
|
40
|
Orissa
|
FP/OR/ROAD/51264/2020
|
5-ORC459/2021-BHU
|
Widening & Strengthening of 2 lane to 2 lane with paved shoulder from Km 58/100 to 116/100 Km of Nh-153 (B) in the State of Odisha on EPC mode
|
Road
|
EXECUTIVE ENGINEER NH DIVISION SAMBALPUR
|
6.754
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
19 Oct 2020
|
Stage-I Approval on
|
:
|
22 Sep 2021
|
Compliance Report Submitted by User Agency on
|
:
|
08 Jul 2023
|
|
|
|
29 Sep 2023
|
41
|
Orissa
|
FP/OR/TRANS/124910/2021
|
5-ORB501/2022-BHU
|
132KV UNDERGROUND POWER CABLE TRANSMISSION LINE OF M/s RUNGTA MINES LIMITED
|
Transmission Line
|
RUNGTA MINES LTD
|
0.181
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
02 Mar 2021
|
Stage-I Approval on
|
:
|
22 Apr 2022
|
Compliance Report Submitted by User Agency on
|
:
|
31 Aug 2023
|
|
|
|
18 Sep 2023
|
42
|
Orissa
|
FP/OR/IRRIG/13439/2015
|
5-ORC304
|
Jeera Irrigation Project
|
Irrigation
|
PADAMPUR INVESTIGATION DIVISION,PADAMPUR
|
5.391
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
01 Sep 2015
|
Stage-I Approval on
|
:
|
04 Aug 2017
|
Compliance Report Submitted by User Agency on
|
:
|
29 Jul 2023
|
|
|
|
18 Aug 2023
|
43
|
Orissa
|
FP/OR/Others/30494/2017
|
5-ORC470/2021-BHU
|
Construction of Air Strip at Malkangiri in Malkangiri District
|
Others
|
EXECUTIVE ENGINEER RB
|
13.233
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
01 Dec 2017
|
Stage-I Approval on
|
:
|
02 Dec 2021
|
Compliance Report Submitted by User Agency on
|
:
|
03 Aug 2023
|
|
|
|
04 Aug 2023
|
44
|
Orissa
|
FP/OR/Pipeline/45293/2020
|
5-ORB457/2021-BHU
|
Execution of 02 Nos. of Individual Rural Piped Water Supply Projects pertaining to Jharsuguda district including five years of
|
Pipeline
|
RURAL WATER SUPPLY & SANITATION KEONJHAR
|
4.046
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
26 Apr 2020
|
Stage-I Approval on
|
:
|
06 Apr 2021
|
Compliance Report Submitted by User Agency on
|
:
|
20 Jul 2023
|
|
|
|
31 Jul 2023
|
45
|
Orissa
|
FP/OR/Others/36587/2018
|
5-ORC474/2021-BHU
|
UTILITY CORRIDOR FOR KHONDBOND PROJECT
|
Others
|
TATA STEEL LIMITED KHONDBOND IRON AND MN MINES
|
17.836
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
19 Oct 2018
|
Stage-I Approval on
|
:
|
25 Nov 2021
|
Compliance Report Submitted by User Agency on
|
:
|
29 May 2023
|
|
|
|
31 Jul 2023
|
46
|
Orissa
|
FP/OR/Others/38875/2019
|
5-ORC434/2020-BHU
|
Jagdishpur-Haldia-Bokaro-Dhamra Pipeline (JHBDPL), Odisha Phase-I Project of GAIL
|
Others
|
GAIL INDIA LIMITED
|
12.2282
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
12 Feb 2019
|
Stage-I Approval on
|
:
|
03 Nov 2020
|
Compliance Report Submitted by User Agency on
|
:
|
09 May 2023
|
|
|
|
28 Jun 2023
|
47
|
Orissa
|
FP/OR/MIN/35900/2018
|
8(21)28/2003-FCE
|
Forest Diversion Proposal over 1.81 ha in addition to the earlier diversion over 23.581 ha within the mining lease area of Patabeda Iron Ore Mines over 28.397 ha in village Patabeda under Koira Tahas
|
Mining
|
MGM MINERAL LTD
|
1.81
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
15 Sep 2018
|
Stage-I Approval on
|
:
|
04 Mar 2020
|
Compliance Report Submitted by User Agency on
|
:
|
22 May 2023
|
|
|
|
14 Jun 2023
|
48
|
Orissa
|
FP/OR/TRANS/39618/2019
|
5-ORC426/2020-BHU
|
For construction of a 132 KV 2 phase Transmission line from exiting 220/132/33 KV Grid sub-station at Therubali to proposed 132/25 KV switch yard of RTSS Bhalumaska of Odisha Power Transmission Corpor
|
Transmission Line
|
ODISHA POWER TRANSMISSION CORPORATION LIMITED
|
14.661
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
30 Mar 2019
|
Stage-I Approval on
|
:
|
10 Sep 2020
|
Compliance Report Submitted by User Agency on
|
:
|
27 Apr 2023
|
|
|
|
23 May 2023
|
49
|
Orissa
|
FP/OR/ROAD/14688/2015
|
5-ORB273/2016-BHU
|
Widening and strengthening of existing SL/IL to double lane Lane with paved shoulder from 140/900 to 162/01 km of NH-57 in Boudh District.
|
Road
|
NH DIVISION SAMBALPUR
|
3.544
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
19 Oct 2015
|
Stage-I Approval on
|
:
|
26 Feb 2016
|
Compliance Report Submitted by User Agency on
|
:
|
18 Apr 2023
|
|
|
|
17 May 2023
|
50
|
Orissa
|
FP/OR/THE/12401/2015
|
5-ORB327/2017-BHU
|
Proposal for diversion of 2.337 acre of forest land for construction of intake water pump house at Samal, Talcher, Odisha for the proposed expansion of Talcher Thermal Power Station (2X660MW).
|
Thermal
|
CHITTARANJAN BARIK
|
0.95
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
05 May 2015
|
Stage-I Approval on
|
:
|
12 Jun 2018
|
Compliance Report Submitted by User Agency on
|
:
|
28 Mar 2023
|
|
|
|
01 May 2023
|
|