Ministry of Environment,Forest and Climate Change
Government of India
Online Submission & Monitoring
of Forests and Wildlife Clearance Proposals
List of Proposals accorded Stage-II Clearance (Proposals received on or after 15th July 2014)
Help
Using this report, you can view details of proposals (Received on or after 15th July 2014) .Click on   to print
 
Proposal Year :
Region : State :
Category : Status of the Proposal :
Enter value for Search :
Note :-All areas are in Hectares(ha.)
Sno.State NameProposal No.RO/Ministry File NumberProposal NameCategoryUser Agency NameArea (ha.)Proposal StatusImportant DatesAllocation of Fresh forest land (Form-A) Part-IView Report (Part-II to Part-V and Stage-I Clearances)Stage-II Approval on
1 Bihar FP/BR/Others/141318/2021 FP/BR/Others/141318/2021 Diversion of 0.01275 ha of forest land for construction of approach road for opening retail outlet of HPCL on Mashrakh-Gauda Bazar SH-90 Road in Saran district of Bihar. Others ABHIMANYU KUMAR 0.01275 APPROVED
Proposal received(at Nodal Officer)electronically on : 15 Apr 2021
Stage-I Approval on : 21 Aug 2025
Compliance Report Submitted by User Agency on : 06 Oct 2025
28 Jan 2026
2 Bihar FP/BR/Others/44447/2020 FP/BR/Others/44447/2020 Diversion of 0.02025 ha of forest land for construction of approach road for opening retail outlet of HPCL on Samastipur-Patori Road in Samastipur district of Bihar. Others DINESH PASWAN 0.02025 APPROVED
Proposal received(at Nodal Officer)electronically on : 07 Feb 2020
Stage-I Approval on : 15 Jun 2020
Compliance Report Submitted by User Agency on : 20 Mar 2025
28 Jan 2026
3 Himachal Pradesh FP/HP/ROAD/37858/2018 8B/HP/06/90/2020/FC SLAPPER TATAPANI ROAD KM.8/500 TO 61/600 Road HIMACHAL PRADESH PUBLIC WORK DEPARTMENT 33.3292 APPROVED
Proposal received(at Nodal Officer)electronically on : 22 Mar 2019
Stage-I Approval on : 24 Feb 2025
Compliance Report Submitted by User Agency on : 10 Jan 2026
27 Jan 2026
4 Karnataka FP/KA/WATER/146299/2021 F.No.4-KRC1385/2022-BAN For construction New Tank with Check Dam & Connectivity Road at Sy No.17 (20 New) of Ittigehalli Village, Bhadravathi Division for recharge of Ground Water surrounding of Ittigehalli Villages in favour of EE, KNNL No.3, Bhadra Canal Division, Malebennur. Drinking Water CHIEF ENGINEER KARNATAKA NEERAVARI NIGAM LIMITED UPPER TUNGA PROJECT ZONE SHIVAMOGGA 12.1801 APPROVED
Proposal received(at Nodal Officer)electronically on : 24 Aug 2021
Stage-I Approval on : 03 Mar 2023
Compliance Report Submitted by User Agency on : 05 Nov 2025
23 Jan 2026
5 Karnataka FP/KA/Others/36295/2018 F.No.4-KRB1288/2021-BAN/ Construction of Solid Waste Unit and Faecal Sludge treatment Plant at Gokarna Others GRAMA PANCHAYAT GOKARNA 0.98 APPROVED
Proposal received(at Nodal Officer)electronically on : 02 Oct 2018
Stage-I Approval on : 25 Feb 2022
Compliance Report Submitted by User Agency on : 25 Jun 2024
23 Jan 2026
6 Karnataka FP/KA/IRRIG/35763/2018 4-KRB1221/2020 Laying of pipeline to fill 60 tanks of Harpanahalli Taluk from Tungabhadra River Irrigation EXECUTIVE ENGINEER KNNL BHADRA CANAL DIVISION DAVANGERE 0.54 APPROVED
Proposal received(at Nodal Officer)electronically on : 19 Sep 2018
Stage-I Approval on : 29 Jan 2020
Compliance Report Submitted by User Agency on : 22 Aug 2025
20 Jan 2026
7 Madhya Pradesh FP/MP/ROAD/149532/2021 6-MPR015/2022-BHO Constrcution of Bypass on WESTERN side of Gwalior City (design km 0.000 to 27.800) Road PDPIUGWALIOR 42.83 APPROVED
Proposal received(at Nodal Officer)electronically on : 23 Nov 2021
Stage-I Approval on : 07 May 2025
Compliance Report Submitted by User Agency on : 10 Oct 2025
20 Jan 2026
8 Jammu and Kashmir FP/JK/Approach/44582/2020 Fst/Land/Parivesh/38/2020 60 mtr single span major pmt bridge at chak nallah Approach Access HQ 56 ROAD CONSTRUCTION COY (BEACON-BRO)) 0.045 APPROVED
Proposal received(at Nodal Officer)electronically on : 15 Feb 2020
Stage-I Approval on : 17 Mar 2021
Compliance Report Submitted by User Agency on : 13 Nov 2025
15 Jan 2026
9 Madhya Pradesh FP/MP/IRRIG/33438/2018 6-MPC014/2019-BHO Prabhudhana Tank.. Irrigation EXECUTIVE ENGINEER WATER RESOURCES DIVISION NO II BETUL 7.002 APPROVED
Proposal received(at Nodal Officer)electronically on : 03 May 2018
Stage-I Approval on : 30 May 2025
Compliance Report Submitted by User Agency on : 21 Nov 2025
13 Jan 2026
10 Uttarakhand FP/UK/ROAD/24737/2017 8B/UCP/06/97/2017/FC Construction of 4.00Km long motor road for Kargil Martyr Sri Ramesh Parihar Village-Dungarpur from Amtora Village in District-Bageshwar Road PROVINCIAL DIVISION PWD BAGESHWAR 1.991 APPROVED
Proposal received(at Nodal Officer)electronically on : 02 Mar 2017
Stage-I Approval on : 11 May 2018
Compliance Report Submitted by User Agency on : 09 Dec 2024
13 Jan 2026
11 Uttarakhand FP/UK/ROAD/154869/2022 8B/UCP/06/40/2023/FC Construction of road from Km 15 of BaijnathBageshwar motor road to Udalgaon in District Bageshwar Road PROVINCIAL DIVISION PWD BAGESHWAR 0.261 APPROVED
Proposal received(at Nodal Officer)electronically on : 26 Apr 2022
Stage-I Approval on : 31 Aug 2023
Compliance Report Submitted by User Agency on : 09 Oct 2025
13 Jan 2026
12 Jharkhand FP/JH/TRANS/45077/2020 FP/JH/TRANS/45077/2020 132kV DC Jamua-Gawan Transmission Line (NIT-253) Transmission Line JUSNL 54.407 APPROVED
Proposal received(at Nodal Officer)electronically on : 18 Mar 2020
Stage-I Approval on : 09 Jan 2025
Compliance Report Submitted by User Agency on : 01 Jul 2025
13 Jan 2026
13 Uttarakhand FP/UK/ROAD/146204/2021 8b/UCP/06/17/2022/FC Sumalta to koladungri motor road Road TEMPORARY DIVISION PUBLIC WORKS DEPARTMENT GAUCHAR 0.861 APPROVED
Proposal received(at Nodal Officer)electronically on : 19 Aug 2021
Stage-I Approval on : 11 Dec 2023
Compliance Report Submitted by User Agency on : 23 Apr 2025
13 Jan 2026
14 Jammu and Kashmir FP/JK/Approach/143480/2021 FST-Land/0FC/87/2021-02 Construction of 45 m span bridge over Gurai nallah Approach Access HQ 56 ROAD CONSTRUCTION COY (BEACON-BRO)) 0.25 APPROVED
Proposal received(at Nodal Officer)electronically on : 14 Jun 2021
Stage-I Approval on : 12 Nov 2021
Compliance Report Submitted by User Agency on : 13 Nov 2025
12 Jan 2026
15 Uttarakhand FP/UK/Others/150277/2021 8B/UCP/09/19/2022/FC Construction of judiciary building in Ranikhet Others CIVIL JUDGE (J.D.) RANIKHET 0.98 APPROVED
Proposal received(at Nodal Officer)electronically on : 16 Dec 2021
Stage-I Approval on : 26 Mar 2025
Compliance Report Submitted by User Agency on : 10 Dec 2025
12 Jan 2026
16 Uttarakhand FP/UK/ROAD/19460/2016 8B/UCP/06/166/2020/FC Construction of Motor Road for connecting of Nadgal Village under CM Scheme at District Nainital Road PUBLIC WORKS DEPARTMENT 1.33 APPROVED
Proposal received(at Nodal Officer)electronically on : 17 May 2016
Stage-I Approval on : 25 Oct 2023
Compliance Report Submitted by User Agency on : 07 May 2025
09 Jan 2026
17 Himachal Pradesh FP/HP/Others/14799/2015 8B/HP/09/90/2017 Development of Paragliding Site at Bir Billing in Tehsil Baijnath, District Kangra, Himachal Pradesh Others TOURISM AND CIVIL AVIATION DEPARTMENT 0.9925 APPROVED
Proposal received(at Nodal Officer)electronically on : 29 Aug 2015
Stage-I Approval on : 22 Jan 2025
Compliance Report Submitted by User Agency on : 03 Dec 2025
09 Jan 2026
18 Tamil Nadu FP/TN/ROAD/28608/2017 4-TNB075/2021-CHN L.Malaiyur Forest Road Road RURAL DEVELOPMENT DEPARTMENT 1.68 APPROVED
Proposal received(at Nodal Officer)electronically on : 10 Aug 2017
Stage-I Approval on : 17 Aug 2022
Compliance Report Submitted by User Agency on : 10 Dec 2025
02 Jan 2026
19 Tamil Nadu FP/TN/OFC/38837/2019 4-TNB121/2024-CHN BSNL Optical Fibre Cable BBHARAT SANCHAR NIGAM LIMITED 0.045 APPROVED
Proposal received(at Nodal Officer)electronically on : 17 Feb 2019
Stage-I Approval on : 04 Apr 2024
Compliance Report Submitted by User Agency on : 15 Jul 2025
02 Jan 2026
20 Karnataka FP/KA/WATER/48609/2020 F.No.4-KRB1481/2023-BAN Work of Construction of Kadugodi GLR (Ground Level Reservoir) in 2.4281 Hac of forest land at Kadugodi Plantation Village, Sy No. 1/P, Bidarahalli Hobali, Bangaluru East Taluk, Bangaluru Urban Dist, Under Contract Package-12 of Cauvery water supply scheme (CWSS) Stage-V Project, JICA Funded in favor of Bangalore Water Supply and Sewerage Board. Drinking Water BANGALORE WATER SUPPLY AND SEWERAGE BOARD 2.4281 APPROVED
Proposal received(at Nodal Officer)electronically on : 14 Aug 2020
Stage-I Approval on : 03 Apr 2024
Compliance Report Submitted by User Agency on : 22 Dec 2025
01 Jan 2026
21 Jammu and Kashmir FP/JK/Approach/125807/2021 9-JKA-074/2021-Jammu 70 mtr pmt br at km 66.95 on BG road (TOTA Br) Approach Access HQ 56 ROAD CONSTRUCTION COY (BEACON-BRO)) 0.45 APPROVED
Proposal received(at Nodal Officer)electronically on : 05 Mar 2021
Stage-I Approval on : 29 Sep 2021
Compliance Report Submitted by User Agency on : 13 Nov 2025
31 Dec 2025
22 Haryana FP/HR/TRANS/147539/2021 9-HRB162-2023-CHA Construction of 66KV Transmission line from 220 KV Sub Station Panchgaon to 66 KV sub station Farrukhnagar and Jamalpur district Gurugram Hayana. Transmission Line HVPNL MANESAR 0.1539 APPROVED
Proposal received(at Nodal Officer)electronically on : 28 Sep 2021
Stage-I Approval on : 30 Apr 2024
Compliance Report Submitted by User Agency on : 12 Nov 2025
31 Dec 2025
23 Uttarakhand FP/UK/ROAD/47038/2020 8B/UCP/06/121/2020/FC C/0 of Link Motor Road from kasardevi (Tiwarikhan) to village Math Road CONSTRUCTION DIVISION PWD ALMORA 2.565 APPROVED
Proposal received(at Nodal Officer)electronically on : 08 Jul 2020
Stage-I Approval on : 14 Oct 2020
Compliance Report Submitted by User Agency on : 06 Sep 2025
26 Dec 2025
24 Uttarakhand FP/UK/ROAD/12313/2015 8B/UCP/06/180/2016/FC Construction of Ghurshal to Saikot motor road. Under State Sector Road PUBLIC WORK DEPARTMENT 0.772 APPROVED
Proposal received(at Nodal Officer)electronically on : 30 Apr 2015
Stage-I Approval on : 17 Jan 2018
Compliance Report Submitted by User Agency on : 12 Jul 2024
23 Dec 2025
25 Bihar FP/BR/Others/42268/2019 FP/BR/Others/42268/2019 The Tourism Department , Govt. of Bihar has been promoting tourist for ritual worship in the Maa Mundeshwari Devi temple situated at the top of Mundeshwari Hill in Bhagwanpur Block under Kaimur Distri Others BIHAR RAJYA PUL NIRMAN NIGAM LTD WORKS DIVISION ARA 1.3094 APPROVED
Proposal received(at Nodal Officer)electronically on : 26 Sep 2019
Stage-I Approval on : 30 Aug 2024
Compliance Report Submitted by User Agency on : 01 Sep 2025
23 Dec 2025
26 Haryana FP/HR/TRANS/41327/2019 9-HRB001-2020-CHA Construction of 220 KV D/C Kaithal (PGCIL) Transmission Line HVPNL KAITHAL 0.457 APPROVED
Proposal received(at Nodal Officer)electronically on : 24 Jul 2019
Stage-I Approval on : 24 Jul 2020
Compliance Report Submitted by User Agency on : 14 Nov 2025
23 Dec 2025
27 Uttarakhand FP/UK/ROAD/48583/2020 8B/UCP/06/172/2020/FC Gauchar Sidoli to Panai M/R Road TEMPORARY DIVISION PUBLIC WORKS DEPARTMENT GAUCHAR 0.26 APPROVED
Proposal received(at Nodal Officer)electronically on : 10 Aug 2020
Stage-I Approval on : 31 Dec 2020
Compliance Report Submitted by User Agency on : 24 Sep 2025
23 Dec 2025
28 Haryana FP/HR/ROAD/48568/2020 9-HRB076-2021-CHA Construction of 6 Lane access controlled Highway from DND- Faridabad-Ballabhgarh Bypass Junction with Delhi-Vadodara Expressway KMP- Interchange (NH-148 NA) under Bharatmala Pariyojana (Lot-4/Pkg-I) Road CMU, MATHURA, NHAI 3.9 APPROVED
Proposal received(at Nodal Officer)electronically on : 10 Aug 2020
Stage-I Approval on : 22 Jun 2021
Compliance Report Submitted by User Agency on : 06 Nov 2025
23 Dec 2025
29 Andhra Pradesh FP/AP/RAIL/149334/2021 4-APB167/2022-VIJ Proposal for Diversion of 1.36 Ha. Forest Land for Construction of new double line and electrification of track between Guntur and Guntakal stations at Dhone (Rly Km.325/4 to 329/2) in Comp.No. 238 & 239 of North Dhone RF, in Dhone Range, Kurnool Division in favour of S.C. Railway, under FC Act 1980. Railway SOUTH CENTRAL RAILWAY,GUNTAKAL. 2.21 APPROVED
Proposal received(at Nodal Officer)electronically on : 15 Nov 2021
Stage-I Approval on : 21 Jun 2023
Compliance Report Submitted by User Agency on : 27 May 2025
18 Dec 2025
30 Maharashtra FP/MH/ROAD/118805/2021 FC-III/MH-51/2022-NGP Upgradation of NH 353 C From Ashti to Sironcha in Section Allaplli to Sironcha Road NATIONAL HIGHWAY DIVISION GADCHIROLI 132.102 APPROVED
Proposal received(at Nodal Officer)electronically on : 11 Jan 2021
Stage-I Approval on : 30 Jan 2023
Compliance Report Submitted by User Agency on : 09 Dec 2025
17 Dec 2025
31 Maharashtra FP/MH/ROAD/119248/2021 FC-III/MH-54/2022-NGP Up-gradation to2/4 lane with paved shoulder configuration of Gadichiroli-Sironcha of NH- 353 C in the State of Maharashtra by Ministry of Road Transport & Highways from Ashti to Sironcha in Gadhciroli Road NATIONAL HIGHWAY DIVISION GADCHIROLI 54.274 APPROVED
Proposal received(at Nodal Officer)electronically on : 12 Jan 2021
Stage-I Approval on : 21 Nov 2023
Compliance Report Submitted by User Agency on : 09 Dec 2025
17 Dec 2025
32 Madhya Pradesh FP/MP/IRRIG/150918/2022 6-MPR002/2024-BHO Kuwajhagar Tank Project Irrigation Madhya Pradesh Water Resources Department 20.512 APPROVED
Proposal received(at Nodal Officer)electronically on : 06 Jan 2022
Stage-I Approval on : 26 Jul 2025
Compliance Report Submitted by User Agency on : 20 Nov 2025
16 Dec 2025
33 Andhra Pradesh FP/AP/RAIL/154617/2022 4-APB213/2023-VIJ Proposal for Diversion of 3.21 Ha. Forest land for construction of New Double line and Electrification of track between Guntur and Guntakal stations at Konided & Panyam (Rly.Km.275-281 & 285-288) in Comp.No.145, 147, 137 & 138 of Panyam RF in Kurnool Range, Kurnool Division in favour of S.C.Railway under FC Act 1980. Railway SOUTH CENTRAL RAILWAY,GUNTAKAL. 3.21 APPROVED
Proposal received(at Nodal Officer)electronically on : 20 Apr 2022
Stage-I Approval on : 26 Jun 2023
Compliance Report Submitted by User Agency on : 27 May 2025
16 Dec 2025
34 Haryana FP/HR/ROAD/27251/2017 9-HRB062-2018-CHA construction of Ring road from Tauru road to Alwar road via Engineering College, Medical College and Navodaya School Bai in Nuh Distt. (C.M. Announcement 15242) Road PWD BANDR MEWAT 1.8239232 APPROVED
Proposal received(at Nodal Officer)electronically on : 02 Aug 2017
Stage-I Approval on : 20 Aug 2018
Compliance Report Submitted by User Agency on : 01 Sep 2025
16 Dec 2025
35 Karnataka FP/KA/TRANS/152682/2022 F. No.4-KRC1468/2023-BAN Construction of 137.701 Kms of 400 KV Quad D/C Koppal PS- Narendra (New) Transmission Line passing through forest land in Sy No. 50/1 Mannerala Village and Sy No. 70/1,70/2, 70/3, 71, 73 and 89 of Mavinaitagi Village, Hanamasagara Hobli, Kushtagi Taluk, Koppal District for a length of 1.644 Kms (7.562 Ha.) by Koppal-Narendra Transmission Limited Transmission Line KOPPAL-NARENDRA TRANSMISSION LIMITED 7.562 APPROVED
Proposal received(at Nodal Officer)electronically on : 22 Feb 2022
Stage-I Approval on : 02 Aug 2023
Compliance Report Submitted by User Agency on : 13 Sep 2025
15 Dec 2025
36 Telangana FP/TG/ROAD/47266/2020 4-TSB226/2021-HYD Improvement of existing road from earthen road to BT standards from Laxmipur to Baddampally in Mancherial District - 4.8408 Ha Road PANCHAYAT RAJ ENGINEERING DEPARTMENT 4.8408 APPROVED
Proposal received(at Nodal Officer)electronically on : 10 Jul 2020
Stage-I Approval on : 15 Nov 2021
Compliance Report Submitted by User Agency on : 03 Jul 2023
15 Dec 2025
37 Orissa FP/OR/IRRIG/12731/2015 5-ORC307/2017-BHU Sono Barrage Project Irrigation MAYURBHANJ INVESTIGATION DIVISION DEPARTMENT OF WATER RESOURCES ODISHA 14.928 APPROVED
Proposal received(at Nodal Officer)electronically on : 29 Oct 2015
Stage-I Approval on : 04 Aug 2017
Compliance Report Submitted by User Agency on : 24 Nov 2025
10 Dec 2025
38 Madhya Pradesh FP/MP/IRRIG/38634/2019 6-MPB005/2022-BHO Bahuti Canal Scheme Irrigation Madhya Pradesh Water Resources Department 1.4002 APPROVED
Proposal received(at Nodal Officer)electronically on : 13 Mar 2019
Stage-I Approval on : 05 Jul 2022
Compliance Report Submitted by User Agency on : 09 Sep 2022
09 Dec 2025
39 Madhya Pradesh FP/MP/Others/38197/2019 6-MPB060/2020-BHO Neoteric Education Society Institute & Rehabilitation Center for Paralysis & Paraplegic Others NEOTERIC EDUCATION AND SERVICE SOCIETY 0.99 APPROVED
Proposal received(at Nodal Officer)electronically on : 31 Jan 2019
Stage-I Approval on : 18 Nov 2021
Compliance Report Submitted by User Agency on : 20 Aug 2025
09 Dec 2025
40 Himachal Pradesh FP/HP/HYD/37189/2018 8B/HP/01/71/2020/FC Kasol Hydro Power Project Hydel MS BEENA BUTAIL PALMPUR 1.496448 APPROVED
Proposal received(at Nodal Officer)electronically on : 22 Nov 2018
Stage-I Approval on : 12 Dec 2024
Compliance Report Submitted by User Agency on : 14 Nov 2025
05 Dec 2025
41 Uttarakhand FP/UK/ROAD/9480/2015 8B/UCP/06/85/2016/FC Constt. of Bagdawar Bend to Duni Veer Singgiya Motor Road Road PUBLIC WORKS DEPARTMENT 3.78 APPROVED
Proposal received(at Nodal Officer)electronically on : 22 Jan 2015
Stage-I Approval on : 19 Jul 2018
Compliance Report Submitted by User Agency on : 13 Oct 2025
04 Dec 2025
42 Uttarakhand FP/UK/ROAD/38366/2019 8B/UCP/06/85/2020/FC Construction of Dewal kheta MR Km-10(suyalkot) to Mopata Link motor road under PMGSY. Road RES PMGSY KARANPERAYAG 3.008 APPROVED
Proposal received(at Nodal Officer)electronically on : 24 Feb 2019
Stage-I Approval on : 14 Oct 2020
Compliance Report Submitted by User Agency on : 18 Jul 2025
04 Dec 2025
43 Madhya Pradesh FP/MP/ROAD/152685/2022 6-MPB015/2022-BHO Suktanawad-Jhirpanjariya road Road PWD DIVISION BURHANPUR 2.38 APPROVED
Proposal received(at Nodal Officer)electronically on : 24 Feb 2022
Stage-I Approval on : 01 Mar 2023
Compliance Report Submitted by User Agency on : 11 Jul 2023
04 Dec 2025
44 Haryana FP/HR/Approach/149450/2021 9-HRB154-2023-CHA M/s Panchkula Foils Approach Access M/S PANCHKULA FOILS 0.0084 APPROVED
Proposal received(at Nodal Officer)electronically on : 20 Nov 2021
Stage-I Approval on : 10 Oct 2023
Compliance Report Submitted by User Agency on : 04 Oct 2024
04 Dec 2025
45 Uttarakhand FP/UK/ROAD/11292/2015 8B/UCP/06/222/2015 Construction of Farsali Palli To Kharkanatoli Road PMGSY 8.931 APPROVED
Proposal received(at Nodal Officer)electronically on : 26 Mar 2015
Stage-I Approval on : 14 Mar 2017
Compliance Report Submitted by User Agency on : 26 Sep 2025
04 Dec 2025
46 Uttarakhand FP/UK/ROAD/21140/2016 8B/UCP/06/118/2018/FC Sahid Hari Singh Tuolbudhand to Ratkhal Motor Road Sanction Under CM Ghosana no. 492/201 Road EXECUTIVE ENGINEER 2.52 APPROVED
Proposal received(at Nodal Officer)electronically on : 29 Aug 2016
Stage-I Approval on : 29 Sep 2020
Compliance Report Submitted by User Agency on : 27 Aug 2025
02 Dec 2025
47 Karnataka FP/KA/ROAD/142140/2021 F.No.4-KRB1347/2022-BAN/ Dviersion of 0.06 Ha of forest land in sy no 14 of Benavalli, Village, Kerehalli Hobali, Hosanagara taluk Shivamogga dist, (Shivamogga forest division) for construction of low cost ROB and Birur-Talguppa section great seperator at Km 105/100-200 and Km 133/700-800 in favour of Assistant divisional engineer, Shivmaogga Road ASSISTANT DIVISIONAL ENGINEER SHIVAMOGGA 0.06 APPROVED
Proposal received(at Nodal Officer)electronically on : 07 May 2021
Stage-I Approval on : 24 Mar 2022
Compliance Report Submitted by User Agency on : 07 Aug 2025
02 Dec 2025
48 Rajasthan FP/RJ/ROAD/149560/2021 8B/RAJ017/2023-JPR “Construction of Widening ,Strengthening on SH-32A From Jhameshwarji to Jagat Road KM Stone No-67/0 to 80/0, Tehsil–Girwa, District -Udaipur (Rajasthan)” Road PUBLIC WORKS DEPARTMENT RAJASTHAN 6.75 APPROVED
Proposal received(at Nodal Officer)electronically on : 11 Dec 2021
Stage-I Approval on : 30 Aug 2023
Compliance Report Submitted by User Agency on : 08 Jan 2025
01 Dec 2025
49 Kerala FP/KL/ROAD/38879/2019 F.No.4-KLB1255/2020-BAN/ REHABILITATION & UPGRADATION of NH 85 from Km 119/017 to 161/300(Design chainage Km 119/017 to 160/800) Bodimettu to Munnar on EPC mode in the State of Kerala Road ASSISTANT EXECUTIVE ENGINEER NH SUBDIVISION 1.495 APPROVED
Proposal received(at Nodal Officer)electronically on : 03 Sep 2019
Stage-I Approval on : 09 Apr 2021
Compliance Report Submitted by User Agency on : 25 Aug 2025
01 Dec 2025
50 Madhya Pradesh FP/MP/ROAD/155399/2022 6-MPB031/2023-BHO Construction of road from KM28 of T01 to Banjaritola under RCPLWEA scheme Road MPRRDA PIU-1 BALAGHAT 1.523 APPROVED
Proposal received(at Nodal Officer)electronically on : 14 May 2022
Stage-I Approval on : 22 Nov 2023
Compliance Report Submitted by User Agency on : 20 Jan 2024
30 Nov 2025