Ministry of Environment,Forest and Climate Change
Government of India
Karnataka
State Forest Department
List of Proposals accorded Stage-II Clearance (Proposals received on or after 15th July 2014)
Help
Using this report, you can view details of proposals (Received on or after 15th July 2014) .Click on   to print
 
Proposal Year :
Region : State :
Category : Status of the Proposal :
Enter value for Search :
Note :-All areas are in Hectares(ha.)
Sno.State NameProposal No.RO/Ministry File NumberProposal NameCategoryUser Agency NameArea (ha.)Proposal StatusImportant DatesAllocation of Fresh forest land (Form-A) Part-IView Report (Part-II to Part-V and Stage-I Clearances)Stage-II Approval on
1 Karnataka FP/KA/WATER/27450/2017 No.4-KRB1168/2018-BAN The project involves permanent water supply facility to Alnavar town and also 14 en-route villages which is very much essential to the people of the Town and villages. The land which is coming under the forest is topo-graphically suited to provide Water Treatment Plant and Pump House. Drinking Water CHIEF OFFICER TOWN PANCHAYAT ALNAVAR 2.114 APPROVED
Proposal received(at Nodal Officer)electronically on : 19 Aug 2017
Stage-I Approval on : 16 Jan 2019
Compliance Report Submitted by User Agency on : 16 Mar 2019
30 Jul 2019
2 Karnataka FP/KA/Others/19136/2016 4-KRB1151/2018-BAN JSW Steel Ltd. has been declared the preferred bidder for 5 C-Category Mining Leases through the recent C- Category Mines auction held on 01st October to 7th October. M/s. JSW Steel Ltd. has been issued the Letter of Intent from DMG vide letter No: DMG/MLS/CCA/12/ML No./2016-17 dated 26.10.2016 and Others JSW Steel Limited 1.645 APPROVED
Proposal received(at Nodal Officer)electronically on : 29 Nov 2016
Stage-I Approval on : 28 May 2018
Compliance Report Submitted by User Agency on : 06 Dec 2018
25 Jun 2019
3 Karnataka FP/KA/TRANS/23066/2016 4-KRB1157/2018-BAN Project is a part of the transmission system associated with Independent Power Producers Generation projects in Nagapattinam / Cuddalore area. Its a part of the high capacity transmission corridor being planned & part of national grid transmitting power across the nation. Transmission Line POWERGRID NM TRANSMISSION LTD 1.75 APPROVED
Proposal received(at Nodal Officer)electronically on : 22 Dec 2016
Stage-I Approval on : 29 Aug 2018
Compliance Report Submitted by User Agency on : 01 Oct 2018
21 Jun 2019
4 Karnataka FP/KA/ROAD/7076/2014 4-KRB1096/2016-BAN Diversion of 1.135 Ha of Forest Land for Existing Approach Road for mining project in Donimalai Block, Narayanpur Village, Sandur Taluk, Bellary District in favour of M/s M.HANUMANTHA RAO,ML No.2505, Bellary District. Road Ms M HANUMANTHA RAO 1.135 APPROVED
Proposal received(at Nodal Officer)electronically on : 05 Mar 2015
Stage-I Approval on : 29 Aug 2017
Compliance Report Submitted by User Agency on : 19 Mar 2018
19 Sep 2018
5 Karnataka FP/KA/WIND/13893/2015 4-KRB 1105/2017-BAN Diversion of 0.94 ha of forestland for improvement of existing road passing through R.S.No.176 of Bendavada, R.S.No.148 of Katakbhavi and R.S.No.191 of Bykud village, Raybagh Taluk, Gokak Divison for carrying WTGs, cranes and allied components required for development of wind power project. Wind Power KARNATAKA RENEWABLE ENERGY DEVELOPMENT LIMITED 0.94 APPROVED
Proposal received(at Nodal Officer)electronically on : 14 Jul 2015
Stage-I Approval on : 13 Mar 2017
Compliance Report Submitted by User Agency on : 30 Oct 2017
07 Nov 2017
6 Karnataka FP/KA/TRANS/10659/2015 4-KRB 1068/ 2015-BAN Forest land is required for Construction of 66KV SC link line from existing 66/33/11KV Madikeri Substation to 66/33/11KV Virajapete Substation to a distance of 1.569 KMs. In the existing idle 33KV line corridor passing through in the Madikeri East Reserve Forest Area with COYOTE ACSR Conductor. Transmission Line EXECUTIVE ENGINEER 2.3535 APPROVED
Proposal received(at Nodal Officer)electronically on : 04 Mar 2015
Stage-I Approval on : 12 Oct 2015
Compliance Report Submitted by User Agency on : 03 Mar 2017
11 Aug 2017
7 Karnataka FP/KA/WATER/20456/2016 FEE 18 FLL 2017 For Construction of Bridge cum Barrage across Ghataprabha river near Herkal village in Bilagi taluka and Bagalkot District. The main purpose of construction of Barrage is Drinking Water Supply to Navanagar Bagalkot and Herkal LIS Schemes. The forest land required for and extent of 0.98 Hectare on Ri Drinking Water ASSISTANT EXECUTIVE ENGINEER DAM GATE SUB DIVISION ALMATTI 0.98 APPROVED
Proposal received(at Nodal Officer)electronically on : 14 Jul 2016
Stage-I Approval on : 07 Mar 2017
Compliance Report Submitted by User Agency on : 22 Apr 2017
23 May 2017
8 Karnataka FP/KA/TRANS/6512/2014 4-KRB 1062/2015-BAN NMDC Limited, a PSU under Ministry of Steel, GOI is constructing 1.2MTPA Pellet Plant at Donimalai.The proposal was initiated to provide power supply to the Pellet Plant for which KPTCL directed NMDC to construct the line on self-execution under the supervision of KPTCL who is the owner of the line Transmission Line NMDC LIMITED DONIMALAI 2.884 APPROVED
Proposal received(at Nodal Officer)electronically on : 14 Aug 2014
Stage-I Approval on : 22 Sep 2015
Compliance Report Submitted by User Agency on : 08 Sep 2016
01 Feb 2017
9 Karnataka FP/KA/QRY/7549/2014 4-KRB 551/2008-BAN There is no other quarry land available. So 0.5 hectares of forest land diverted in the year 2011.No quarry in and arround Quarrying PADMA CRUSHERS 1.78 APPROVED
Proposal received(at Nodal Officer)electronically on : 30 Oct 2014
Stage-I Approval on : 31 Dec 2015
Compliance Report Submitted by User Agency on : 08 Sep 2016
09 Nov 2016
10 Karnataka FP/KA/HYD/7231/2014 4-KRB 1050/2015-BAN Aniyur Mini Hydel Scheme of 24 MW capacity with an annual energy generation of 70 Mu is proposed across Aniyur Stream in Neriya Village, Belthangady Taluk , Dakshina Kannada District, as a run of the river scheme. The project is located in private land bearing Survey No. 146/57 A1 E1 in Neriya Villa Hydel SLV POWER PRIVATE LIMITED 1.5383 APPROVED
Proposal received(at Nodal Officer)electronically on : 29 Sep 2014
Stage-I Approval on : 30 Sep 2015
Compliance Report Submitted by User Agency on : 29 Mar 2016
14 Jan 2016