Sno. | State Name | Proposal No. | RO/Ministry File Number | Proposal Name | Category | User Agency Name | Area (ha.) | Proposal Status | Important Dates | Allocation of Fresh forest land (Form-A) Part-I | View Report (Part-II to Part-V and Stage-I Clearances) | Stage-II Approval on |
1
|
Delhi
|
FP/DL/RAIL/146349/2021
|
8B/DLI012/2022-JPR
|
Aerocity to Tughlakabad MRTS Corridor
|
Railway
|
DELHI METRO RAIL CORP LTD
|
14.15
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
29 Aug 2021
|
Stage-I Approval on
|
:
|
13 Apr 2022
|
Compliance Report Submitted by User Agency on
|
:
|
05 May 2022
|
|
|
|
29 Dec 2023
|
2
|
Delhi
|
FP/DL/TRANS/39469/2019
|
8B/DLI/04/02/2020
|
LILO of 400 KV Bamnauli-Jhatikara Line at Dwarka
|
Transmission Line
|
POWERGRID CORPORATION OF INDIA LIMITED
|
10.9736
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
23 Mar 2019
|
Stage-I Approval on
|
:
|
07 Dec 2020
|
Compliance Report Submitted by User Agency on
|
:
|
30 Sep 2021
|
|
|
|
27 Dec 2023
|
3
|
Delhi
|
FP/DL/RAIL/152208/2022
|
8B/DLI011/2022-JPR
|
Construction of Elevated viaduct of length 12.1 kms from Maujpur to Majilis Park
|
Railway
|
DELHI METRO RAIL CORPORATION
|
0.57435
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
12 Feb 2022
|
Stage-I Approval on
|
:
|
13 Apr 2022
|
Compliance Report Submitted by User Agency on
|
:
|
10 May 2022
|
|
|
|
10 Nov 2023
|
4
|
Delhi
|
FP/DL/TRANS/46658/2020
|
8B/DLI/04/4/2021/FC
|
Construction of 765 kV D/C Khetri-Jhatikra Transmission Line under Transmission System Associated with LTA Applications for Rajasthan Solar Energy Zone, Part –C
|
Transmission Line
|
POWERGRID KHETRI TRANSMISSION SYSTEM LIMITED
|
4.89
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
24 Jun 2020
|
Stage-I Approval on
|
:
|
18 Jun 2021
|
Compliance Report Submitted by User Agency on
|
:
|
23 Feb 2022
|
|
|
|
29 Aug 2023
|
5
|
Delhi
|
FP/DL/RAIL/149368/2021
|
8B/DLI013/2022-JPR
|
Delhi-Gurugram-SNB RRTS Corridor
|
Railway
|
NATIONAL CAPITAL REGION TRANSPORT CORPORATION LIMITED
|
1.282
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
16 Nov 2021
|
Stage-I Approval on
|
:
|
22 Mar 2022
|
Compliance Report Submitted by User Agency on
|
:
|
28 Dec 2022
|
|
|
|
22 Jun 2023
|
6
|
Delhi
|
FP/DL/ROAD/49252/2020
|
8B/DLI/06/6/2021
|
Development of Urban Extension Road-II NH-344M from Design Km 0+000 at NH-1 Intersection (Km 23+800, near Bankoli village) to Design Km 38+111 near Sector 24, Dwarka in the state of NCT Delhi
|
Road
|
MINISTRY OF ROAD TRANSPORT & HIGHWAYS
|
54.8724
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
02 Sep 2020
|
Stage-I Approval on
|
:
|
28 Sep 2021
|
Compliance Report Submitted by User Agency on
|
:
|
01 Nov 2021
|
|
|
|
22 Feb 2023
|
7
|
Delhi
|
FP/DL/Others/38156/2019
|
8B/DLI/09/03/2019/FC
|
CONSTRUCTION OF CLUSTER BUS DEPOT
|
Others
|
TRANSPORT DEPARTMENT GNCTD
|
1.84
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
09 Jan 2019
|
Stage-I Approval on
|
:
|
19 Jul 2019
|
Compliance Report Submitted by User Agency on
|
:
|
16 Jun 2022
|
|
|
|
30 Aug 2022
|
8
|
Delhi
|
FP/DL/RAIL/49037/2020
|
8B/DLI/07/03/2021/FC
|
DELHI-GHAZIABAD-MEERUT RRTS CORRIDOR
|
Railway
|
NATIONAL CAPITAL REGION TRANSPORT CORPORATION LIMITED
|
4.19
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
29 Aug 2020
|
Stage-I Approval on
|
:
|
30 Jun 2021
|
Compliance Report Submitted by User Agency on
|
:
|
31 Aug 2021
|
|
|
|
30 Aug 2022
|
9
|
Delhi
|
FP/DL/RAIL/145310/2021
|
8B/DLI/07/7/2021
|
Raising of Guide Bund of existing Railway Bridge over river Yamuna
|
Railway
|
NORTHERN RAILWAY,CONSTRUCTION
|
2.396
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
03 Aug 2021
|
Stage-I Approval on
|
:
|
14 Oct 2021
|
Compliance Report Submitted by User Agency on
|
:
|
22 Mar 2022
|
|
|
|
12 May 2022
|
10
|
Delhi
|
FP/DL/Others/50743/2020
|
8B/Delhi/09/01/2021
|
Construction of Guru Ravidas Temple as per order dated 21/10/2019 by Hon'ble Supreme Court of India.
|
Others
|
DELHI DEVELOPMENT AUTHORITY DDA
|
0.124
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
12 Oct 2020
|
Stage-I Approval on
|
:
|
01 Jun 2021
|
Compliance Report Submitted by User Agency on
|
:
|
10 Sep 2021
|
|
|
|
20 Jan 2022
|
11
|
Delhi
|
FP/DL/Others/124256/2021
|
8B/DLI/09/5/2021/FC
|
:- Common Central Secretariat 1, 2 & 3
|
Others
|
CPWD NEW DELHI
|
8.11
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
11 Mar 2021
|
Stage-I Approval on
|
:
|
06 Sep 2021
|
Compliance Report Submitted by User Agency on
|
:
|
22 Nov 2021
|
|
|
|
11 Jan 2022
|
12
|
Delhi
|
FP/DL/TRANS/36614/2018
|
8B/DLI/04/1/2020
|
CONSTRUCTION OF LILO OF BOTH CIRCUIT OF BAWANA – MANDOLA 400 KV TRANSMISSION LINE AT MAHARANIBAGH
|
Transmission Line
|
POWERGRID CORPORATION OF INDIA LIMITED
|
13.5165
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
17 Dec 2018
|
Stage-I Approval on
|
:
|
19 Oct 2020
|
Compliance Report Submitted by User Agency on
|
:
|
22 Jul 2021
|
|
|
|
19 Aug 2021
|