Sno. | State Name | Proposal No. | RO/Ministry File Number | Proposal Name | Category | User Agency Name | Area (ha.) | Proposal Status | Important Dates | Allocation of Fresh forest land (Form-A) Part-I | View Report (Part-II to Part-V and Stage-I Clearances) | Stage-II Approval on |
1
|
Bihar
|
FP/BR/TRANS/122227/2021
|
FP/BR/TRANS/122227/2021
|
LILO OF KISHANGANJ DARBHANGA 400KV D/C (QUAD) LINE OF POWERGRID AT SAHARSA (NEW) SUBSTATION
|
Transmission Line
|
POWERGRID MITHILANCHAL TRANSMISSION LIMITED SAHARSA
|
2.191
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
11 Feb 2021
|
Stage-I Approval on
|
:
|
24 Mar 2022
|
Compliance Report Submitted by User Agency on
|
:
|
30 Nov 2022
|
|
|
|
30 Jun 2025
|
2
|
Bihar
|
FP/BR/Others/46309/2020
|
FP/BR/Others/46309/2020
|
Diversion of 0.010725 ha of forest land for construction of approach road for opening retail outlet of BPCL on side of SH-49 in Vaishali district of Bihar.
|
Others
|
SAURABH KUMAR
|
0.01073
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
15 Jun 2020
|
Stage-I Approval on
|
:
|
14 Oct 2020
|
Compliance Report Submitted by User Agency on
|
:
|
12 Aug 2021
|
|
|
|
20 Jun 2025
|
3
|
Bihar
|
FP/BR/Approach/152066/2022
|
FP/BR/Approach/152066/2022
|
The proposal for establishment of retail out-let dealership of M/s NX100 PACIFIC BIOFUEL PVT Ltd.
|
Approach Access
|
AJIT KUMAR
|
0.015
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
07 Feb 2022
|
Stage-I Approval on
|
:
|
14 Feb 2025
|
Compliance Report Submitted by User Agency on
|
:
|
15 May 2025
|
|
|
|
16 Jun 2025
|
4
|
Bihar
|
FP/BR/Approach/125768/2021
|
FP/BR/Approach/125768/2021
|
The proposal for establishment of retail out-let dealership of M/s Indian Oil Corporation Ltd.
|
Approach Access
|
KAMINI KUMARI
|
0.018
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
05 Mar 2021
|
Stage-I Approval on
|
:
|
17 Sep 2024
|
Compliance Report Submitted by User Agency on
|
:
|
29 Apr 2025
|
|
|
|
02 May 2025
|
5
|
Bihar
|
FP/BR/Approach/48402/2020
|
FP/BR/Approach/48402/2020
|
The proposal for establishment of retail out-let dealership of M/s Hindustan Petroleum Corporation Ltd.
|
Approach Access
|
GAYATRI KUMARI
|
0.02124
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
06 Aug 2020
|
Stage-I Approval on
|
:
|
23 Feb 2023
|
Compliance Report Submitted by User Agency on
|
:
|
13 Dec 2024
|
|
|
|
06 Feb 2025
|
6
|
Bihar
|
FP/BR/Others/48533/2020
|
FP/BR/OTHERS/48533/2020
|
Diversion of 0.01275 ha of forest land for construction of approach road for opening retail outlet of BPCL on SH-60 Road in Purnea district of Bihar.
|
Others
|
PRADIP KUMAR SAH
|
0.01275
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
09 Aug 2020
|
Stage-I Approval on
|
:
|
20 May 2022
|
Compliance Report Submitted by User Agency on
|
:
|
23 Dec 2024
|
|
|
|
26 Jan 2025
|
7
|
Bihar
|
FP/BR/Others/46397/2020
|
FP/BR/Others/46397/2020
|
Diversion of 0.01245 ha of forest land for construction of approach road for opening retail outlet of BPCL on side of SH-75 in Darbhanga district of Bihar.
|
Others
|
KIRAN SINGH
|
0.01245
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
16 Jun 2020
|
Stage-I Approval on
|
:
|
19 Jan 2021
|
Compliance Report Submitted by User Agency on
|
:
|
23 Dec 2024
|
|
|
|
06 Jan 2025
|
8
|
Bihar
|
FP/BR/Others/39940/2019
|
FP/BR/Others/39940/2019
|
Diversion of 0.01215 ha of forest land for construction of approach road for opening retail outlet of BPCL on side of SH-47 Road in Gopalganj district of Bihar.
|
Others
|
RAJESH SINGH GOPALGANJ
|
0.006
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
22 Apr 2019
|
Stage-I Approval on
|
:
|
13 Apr 2020
|
Compliance Report Submitted by User Agency on
|
:
|
30 Oct 2024
|
|
|
|
30 Dec 2024
|
9
|
Bihar
|
FP/BR/Approach/49539/2020
|
FP/BR/Approach/49539/2020
|
The proposal for establishment of retail out-let dealership of M/s Bharat Petroleum Corporation Ltd.
|
Approach Access
|
GANESH KUMAR DAS
|
0.024
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
08 Sep 2020
|
Stage-I Approval on
|
:
|
09 Nov 2023
|
Compliance Report Submitted by User Agency on
|
:
|
07 Aug 2024
|
|
|
|
22 Oct 2024
|
10
|
Bihar
|
FP/BR/ROAD/143461/2021
|
FP/BR/ROAD/143461/2021
|
Construction of Four lane Inter corridor package-II from Shivrampur to Ramnagar in the state of Bihar under Bharatmala Pariyojna (Lot-5, Pkg-7) - NH-119D
|
Road
|
NATIONAL HIGHWAYS AUTHORITY OF INDIA, PROJECT IMPLEMENTATION UNIT - GAYA
|
3.142
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
15 Jun 2021
|
Stage-I Approval on
|
:
|
28 Nov 2022
|
Compliance Report Submitted by User Agency on
|
:
|
30 Jul 2024
|
|
|
|
10 Oct 2024
|
11
|
Bihar
|
FP/BR/ROAD/144718/2021
|
FP/BR/ROAD/144718/2021
|
Construction of four lane Inter corridor from Kalyanpur (Ch. Km – 0+000) to Tal Dashraha (Ch. Km - 47+500) with spur (Ch 0+000 Km to Ch 2+100 km) Package-IV in the state of Bihar under Bharatmala Pariyojna (Lot-5, Pkg-7) – NH-119D.
|
Road
|
National Highways Authority of India
|
3.042
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
20 Jul 2021
|
Stage-I Approval on
|
:
|
10 Feb 2023
|
Compliance Report Submitted by User Agency on
|
:
|
02 Aug 2024
|
|
|
|
10 Oct 2024
|
12
|
Bihar
|
FP/BR/Approach/100781/2020
|
FP/BR/Approach/100781/2020
|
The proposal for establishment of retail out-let dealership of M/s Bharat Petroleum Corporation Ltd.
|
Approach Access
|
SHRI SANJAY RAM
|
0.024
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
14 Dec 2020
|
Stage-I Approval on
|
:
|
10 Aug 2021
|
Compliance Report Submitted by User Agency on
|
:
|
05 Jun 2024
|
|
|
|
30 Sep 2024
|
13
|
Bihar
|
FP/BR/Approach/144768/2021
|
FP/BR/APPROACH/144768/2021
|
Diversion of 0.0105 ha of forest land for construction of approach road for opening retail outlet of BPCL on NH-527A Barhara-Mehat Road in Madhubani district of Bihar.
|
Approach Access
|
INTAKHAB ALAM
|
0.0105
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
14 Jul 2021
|
Stage-I Approval on
|
:
|
20 May 2022
|
Compliance Report Submitted by User Agency on
|
:
|
19 Apr 2024
|
|
|
|
23 Sep 2024
|
14
|
Bihar
|
FP/BR/Approach/145621/2021
|
FP/BR/Approach/145621/2021
|
The proposal for establishment of retail out-let dealership of M/s Bharat Petroleum Corporation Ltd. Location Between Chakai & Jharkhand Border on NH-333 District Jamui Bihar.
|
Approach Access
|
MANOJ UPADHYAY
|
0.0195
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
04 Aug 2021
|
Stage-I Approval on
|
:
|
13 Jul 2023
|
Compliance Report Submitted by User Agency on
|
:
|
19 Aug 2024
|
|
|
|
17 Sep 2024
|
15
|
Bihar
|
FP/BR/Approach/144719/2021
|
FP/BR/Approach/144719/2021
|
Diversion of 0.019125 ha of forest land for construction of approach road for opening retail outlet of BPCL on Akbarnagar-Shahkund SH-85 Road in Bhagalpur district of Bihar.
|
Approach Access
|
KUMARI LOVELY ANAND
|
0.01913
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
12 Jul 2021
|
Stage-I Approval on
|
:
|
01 Aug 2023
|
Compliance Report Submitted by User Agency on
|
:
|
01 Apr 2024
|
|
|
|
11 Aug 2024
|
16
|
Bihar
|
FP/BR/Others/50115/2020
|
FP/BR/Others/50115/2020
|
Diversion of 0.01425 ha of forest land for construction of approach road for opening retail outlet of HPCL on Manjhi-Darauli-Guthani Road in Siwan district of Bihar.
|
Others
|
BALI RAM SINGH
|
0.01425
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
26 Sep 2020
|
Stage-I Approval on
|
:
|
22 Mar 2022
|
Compliance Report Submitted by User Agency on
|
:
|
22 Apr 2024
|
|
|
|
26 Jul 2024
|
17
|
Bihar
|
FP/BR/Approach/144240/2021
|
FP/BR/Approach/144240/2021
|
Diversion of 0.005775 ha of forest land for construction of approach road for opening retail outlet of IOCL on SH-66 Road in Supaul district of Bihar.
|
Approach Access
|
JITENDRA KUMAR
|
0.00578
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
30 Jun 2021
|
Stage-I Approval on
|
:
|
13 Jan 2024
|
Compliance Report Submitted by User Agency on
|
:
|
01 Apr 2024
|
|
|
|
26 Jul 2024
|
18
|
Bihar
|
FP/BR/Others/140669/2021
|
FP/BR/Others/140669/2021
|
Diversion of 0.01425 ha of forest land for construction of approach road for opening retail outlet of HPCL on SH-4 Gaya-Daniyawan Road in Gaya district of Bihar.
|
Others
|
GAURAV RANA
|
0.01425
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
05 Apr 2021
|
Stage-I Approval on
|
:
|
13 Sep 2023
|
Compliance Report Submitted by User Agency on
|
:
|
19 Apr 2024
|
|
|
|
29 May 2024
|
19
|
Bihar
|
FP/BR/Others/50993/2020
|
FP/BR/Others/50993/2020
|
Diversion of 0.0210 ha of forest land for construction of approach road for opening retail outlet of BPCL on NH-80 Road in Bhagalpur district of Bihar.
|
Others
|
SUMIT KUMAR
|
0.021
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
13 Oct 2020
|
Stage-I Approval on
|
:
|
14 Aug 2023
|
Compliance Report Submitted by User Agency on
|
:
|
24 Jan 2024
|
|
|
|
01 May 2024
|
20
|
Bihar
|
FP/BR/Pipeline/38396/2019
|
FP/BR/Pipeline/38396/2019
|
Barouni-Guwahati Pipeline Project
|
Pipeline
|
GAIL INDIA LIMITED
|
0.6294
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
28 Jan 2019
|
Stage-I Approval on
|
:
|
07 Apr 2020
|
Compliance Report Submitted by User Agency on
|
:
|
23 Sep 2022
|
|
|
|
25 Apr 2024
|
21
|
Bihar
|
FP/BR/Others/120183/2021
|
FP/BR/Others/120183/2021
|
Diversion of 0.03975 ha of forest land for construction of approach road for opening retail outlet of IOCL on NH-333 Sono-Chakai Road in Jamui district of Bihar.
|
Others
|
PRABHUNATH DAS
|
0.03975
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
20 Jan 2021
|
Stage-I Approval on
|
:
|
31 Aug 2022
|
Compliance Report Submitted by User Agency on
|
:
|
01 Apr 2024
|
|
|
|
25 Apr 2024
|
22
|
Bihar
|
FP/BR/Approach/154240/2022
|
FP/BR/Approach/154240/2022
|
Diversion of 0.02625 ha of forest land for construction of approach road for opening retail outlet of Reliance BP Mobility Ltd. on NH22 New NH77 Old Muzaffarpur Hajipur Road in Vaishali district of Bi
|
Approach Access
|
RAKESH SHARMA
|
0.02625
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
08 Apr 2022
|
Stage-I Approval on
|
:
|
09 Nov 2023
|
Compliance Report Submitted by User Agency on
|
:
|
12 Feb 2024
|
|
|
|
25 Apr 2024
|
23
|
Bihar
|
FP/BR/ROAD/155194/2022
|
FP/BR/ROAD/155194/2022
|
Construction of 4-lane green field alignment inter corridor from Balbhadrapur (Ch. Km -47+000) to Bela Nawada (Ch. Km 89+210) Section of NH-119D under Bharatmala Pariyojana (Lot-5 pkg-7) in the State
|
Road
|
NATIONAL HIGHWAYS AUTHORITY OF INDIA
|
3.2213
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
09 May 2022
|
Stage-I Approval on
|
:
|
06 Mar 2023
|
Compliance Report Submitted by User Agency on
|
:
|
26 Jun 2023
|
|
|
|
21 Mar 2024
|
24
|
Bihar
|
FP/BR/Approach/147531/2021
|
FP/BR/Approach/147531/2021
|
Diversion of 0.033 ha of forest land for construction of approach road for opening retail outlet of BPCL on SH-4 Khizersarai-Gaya Road in Gaya district of Bihar.
|
Approach Access
|
RANJEET MANDAL
|
0.033
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
21 Sep 2021
|
Stage-I Approval on
|
:
|
13 Jul 2023
|
Compliance Report Submitted by User Agency on
|
:
|
09 Jan 2024
|
|
|
|
02 Feb 2024
|
25
|
Bihar
|
FP/BR/TRANS/41417/2019
|
FP/BR/TRANS/41417/2019
|
Construction of 400 kV D/C North Karanpura to Gaya transmission line(Bihar portion)
|
Transmission Line
|
NORTH KARANPURA TRANSCO LIMITED
|
5.437
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
01 Aug 2019
|
Stage-I Approval on
|
:
|
02 Sep 2021
|
Compliance Report Submitted by User Agency on
|
:
|
10 Jul 2023
|
|
|
|
19 Jan 2024
|
26
|
Bihar
|
FP/BR/Approach/144024/2021
|
FP/BR/Approach/144024/2021
|
The proposal for establishment of retail out-let dealership of M/s Bharat Petroleum Corporation Ltd. Location Within 4 KM from Gulariya Ghat chowk towards Maker on Sonepur-Dharihara-Rewaghat Road Dist
|
Approach Access
|
ARUN KUMAR BPCL
|
0.02025
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
25 Jun 2021
|
Stage-I Approval on
|
:
|
07 Jul 2023
|
Compliance Report Submitted by User Agency on
|
:
|
12 Dec 2023
|
|
|
|
08 Jan 2024
|
27
|
Bihar
|
FP/BR/Approach/121525/2021
|
FP/BR/Approach/121525/2021
|
The proposal for establishment of retail out-let dealership of M/s Hindustan Petroleum Corporation Ltd.
|
Approach Access
|
AISHA KHATOON
|
0.015
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
03 Feb 2021
|
Stage-I Approval on
|
:
|
25 Jul 2022
|
Compliance Report Submitted by User Agency on
|
:
|
08 Dec 2023
|
|
|
|
05 Jan 2024
|
28
|
Bihar
|
FP/BR/Approach/155592/2022
|
FP/BR/Approach/155592/2022
|
Diversion of 0.0225 ha of forest land for construction of approach road for opening retail outlet of IOCL on NH84 Buxar-Ara Road in Bhojpur district of Bihar.
|
Approach Access
|
BIRABAL YADAV
|
0.0225
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
27 May 2022
|
Stage-I Approval on
|
:
|
13 Sep 2023
|
Compliance Report Submitted by User Agency on
|
:
|
13 Nov 2023
|
|
|
|
05 Jan 2024
|
29
|
Bihar
|
FP/BR/Approach/150433/2021
|
FP/BR/Approach/150433/2021
|
The proposal for establishment of retail out-let dealership of M/s Hindustan Petroleum Corporation Ltd. Location Within 5 KM From from Baniyapur Block office Towards Chhapara on NH-101 in Saran Distri
|
Approach Access
|
SHAILENDRA KUMAR
|
0.01875
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
22 Dec 2021
|
Stage-I Approval on
|
:
|
29 Aug 2023
|
Compliance Report Submitted by User Agency on
|
:
|
28 Oct 2023
|
|
|
|
25 Dec 2023
|
30
|
Bihar
|
FP/BR/Approach/146697/2021
|
FP/BR/Approach/146697/2021
|
The proposal for establishment of retail out-let dealership of M/s Hindustan Petroleum Corporation Ltd. Location Within 4 KM From Sangrampur Police Station Towards Sultanganj on Deoghar Sultanganj Roa
|
Approach Access
|
REETA BHAGAT
|
0.02025
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
01 Sep 2021
|
Stage-I Approval on
|
:
|
28 Aug 2023
|
Compliance Report Submitted by User Agency on
|
:
|
26 Oct 2023
|
|
|
|
20 Dec 2023
|
31
|
Bihar
|
FP/BR/Approach/156610/2022
|
FP/BR/Approach/156610/2022
|
Diversion of 0.036 ha of forest land for construction of approach road for opening retail outlet of IOCL on NH-333 Jamui-Chakai Road in Jamui district of Bihar.
|
Approach Access
|
RAM YADAV
|
0.036
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
09 Jun 2022
|
Stage-I Approval on
|
:
|
13 Sep 2023
|
Compliance Report Submitted by User Agency on
|
:
|
08 Nov 2023
|
|
|
|
20 Dec 2023
|
32
|
Bihar
|
FP/BR/Approach/143991/2021
|
FP/BR/Approach/143991/2021
|
The proposal for establishment of retail out-let dealership of M/s Bharat Petroleum Corporation Ltd. Location 5 KM from Brahmpur Bridge towards Siwan on NH-85 (New-NH-531) Chapra-Siwan Road on Either
|
Approach Access
|
AJAY KUMAR AKELA
|
0.021
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
24 Jun 2021
|
Stage-I Approval on
|
:
|
18 Oct 2022
|
Compliance Report Submitted by User Agency on
|
:
|
07 Nov 2023
|
|
|
|
12 Dec 2023
|
33
|
Bihar
|
FP/BR/Others/120193/2021
|
FP/BR/Others/120193/2021
|
Diversion of 0.036 ha of forest land for construction of approach road for opening retail outlet of BPCL on NH-140 (Old) 227 (New) Road in Madhubani district of Bihar.
|
Others
|
ARVIND KUMAR GUPTA
|
0.036
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
20 Jan 2021
|
Stage-I Approval on
|
:
|
13 Feb 2023
|
Compliance Report Submitted by User Agency on
|
:
|
23 Mar 2023
|
|
|
|
28 Nov 2023
|
34
|
Bihar
|
FP/BR/Approach/148100/2021
|
FP/BR/Approach/148100/2021
|
Diversion of 0.01125 ha of forest land for construction of approach road for opening retail outlet of IOCL on Maker-Sitalpur PWD Road in Saran district of Bihar.
|
Approach Access
|
SITA KUMARI
|
0.01125
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
06 Oct 2021
|
Stage-I Approval on
|
:
|
21 Aug 2023
|
Compliance Report Submitted by User Agency on
|
:
|
04 Oct 2023
|
|
|
|
28 Nov 2023
|
35
|
Bihar
|
FP/BR/Approach/154926/2022
|
FP/BR/Approach/154926/2022
|
Diversion of 0.00975 ha of forest land for construction of approach road for opening retail outlet of NX100 Pacific Biofuel Pvt. Ltd. on SH-102 Piro-Jagdishpur Road in Bhojpur district of Bihar.
|
Approach Access
|
NIRMAL SINGH
|
0.00975
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
27 Apr 2022
|
Stage-I Approval on
|
:
|
21 Aug 2023
|
Compliance Report Submitted by User Agency on
|
:
|
04 Oct 2023
|
|
|
|
28 Nov 2023
|
36
|
Bihar
|
FP/BR/Approach/155066/2022
|
FP/BR/Approach/155066/2022
|
Diversion of 0.01515 ha of forest land for construction of approach road for opening retail outlet of HPCL on Mohamadpur-Malmaliya-Chapra Road in Siwan district of Bihar.
|
Approach Access
|
ABHISHEK TIWARI
|
0.01515
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
02 May 2022
|
Stage-I Approval on
|
:
|
30 Nov 2022
|
Compliance Report Submitted by User Agency on
|
:
|
04 Oct 2023
|
|
|
|
28 Nov 2023
|
37
|
Bihar
|
FP/BR/Approach/151337/2022
|
FP/BR/Approach/151337/2022
|
The proposal for establishment of retail out-let dealership of M/s Indian Oil Corporation Ltd. Location Within 4 KMS From Kajghosa Towards Banka (on Banka-Katoria Road) in Banka District Bihar.
|
Approach Access
|
SANJAY KUMAR YADAV
|
0.01278
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
19 Jan 2022
|
Stage-I Approval on
|
:
|
14 Jun 2023
|
Compliance Report Submitted by User Agency on
|
:
|
11 Oct 2023
|
|
|
|
09 Nov 2023
|
38
|
Bihar
|
FP/BR/Others/64004/2020
|
FP/BR/Others/64004/2020
|
Diversion of 0.012 ha of forest land for construction of approach road for opening retail outlet of IOCL on SH-99 Road in Purnea district of Bihar.
|
Others
|
ZEBA PARWEEN ABDUL BARI
|
0.012
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
25 Nov 2020
|
Stage-I Approval on
|
:
|
18 Oct 2022
|
Compliance Report Submitted by User Agency on
|
:
|
23 Aug 2023
|
|
|
|
17 Oct 2023
|
39
|
Bihar
|
FP/BR/Approach/143989/2021
|
FP/BR/APPROACH/143989/2021
|
Diversion of 0.01425 ha of forest land for construction of approach road for opening retail outlet of IOCL on Manjhi-Darauli-Guthani Road in Siwan district of Bihar.
|
Approach Access
|
AMIT KUMAR SINGH
|
0.01425
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
24 Jun 2021
|
Stage-I Approval on
|
:
|
29 Jun 2022
|
Compliance Report Submitted by User Agency on
|
:
|
22 Aug 2023
|
|
|
|
17 Oct 2023
|
40
|
Bihar
|
FP/BR/Approach/155848/2022
|
FP/BR/Approach/155848/2022
|
Diversion of 0.03975 ha of forest land for construction of approach road for opening retail outlet of IOCL on NH-107 Bnmankhi-Sarsi Road in Purnea district of Bihar.
|
Approach Access
|
RITA BHARTI
|
0.03975
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
26 May 2022
|
Stage-I Approval on
|
:
|
28 Jul 2023
|
Compliance Report Submitted by User Agency on
|
:
|
08 Sep 2023
|
|
|
|
17 Oct 2023
|
41
|
Bihar
|
FP/BR/Others/44411/2020
|
FP/BR/Others/44411/2020
|
Diversion of 0.01575 ha of forest land for construction of approach road for opening retail outlet of BPCL on Sasaram-Chausa Road in Rohtas district of Bihar.
|
Others
|
SHIBBU SAHIBA
|
0.01575
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
05 Feb 2020
|
Stage-I Approval on
|
:
|
22 Sep 2020
|
Compliance Report Submitted by User Agency on
|
:
|
01 Jul 2023
|
|
|
|
27 Sep 2023
|
42
|
Bihar
|
FP/BR/TRANS/152127/2022
|
FP/BR/TRANS/152127/2022
|
33 KV Transmission line from Shree Bihar Solar Project to 132/33 KV GSS Banka (New)
|
Transmission Line
|
SHREE CEMENT LIMITED
|
0.84
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
08 Feb 2022
|
Stage-I Approval on
|
:
|
29 Nov 2022
|
Compliance Report Submitted by User Agency on
|
:
|
17 Aug 2023
|
|
|
|
13 Sep 2023
|
43
|
Bihar
|
FP/BR/Others/141322/2021
|
FP_BR_OTHERS_141322_2021
|
Diversion of 0.013875 ha of forest land for construction of approach road for opening retail outlet of HPCL on Khaira chowk-Marhora Road in Saran district of Bihar.
|
Others
|
NISHI KUMARI
|
0.01388
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
15 Apr 2021
|
Stage-I Approval on
|
:
|
22 Mar 2023
|
Compliance Report Submitted by User Agency on
|
:
|
04 Aug 2023
|
|
|
|
11 Sep 2023
|
44
|
Bihar
|
FP/BR/Others/56158/2020
|
FP/BR/Others/56158/2020
|
Diversion of 0.01995 ha of forest land for construction of approach road for opening retail outlet of IOCL on SH-99 Road in Purnea district of Bihar.
|
Others
|
MD ANWAR ANSARI
|
0.01995
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
13 Nov 2020
|
Stage-I Approval on
|
:
|
01 Jun 2023
|
Compliance Report Submitted by User Agency on
|
:
|
04 Aug 2023
|
|
|
|
28 Aug 2023
|
45
|
Bihar
|
FP/BR/Approach/144838/2021
|
FP/BR/Approach/144838/2021
|
The proposal for establishment of retail out-let dealership of M/s Hindustan Petroleum Corporation Ltd. Location Within 5 KM from Intersection of SH-85 and NH-80 Towards Shahkhund on SH-85 District Bh
|
Approach Access
|
MAINTU KUMAR
|
0.02025
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
15 Jul 2021
|
Stage-I Approval on
|
:
|
22 Jun 2023
|
Compliance Report Submitted by User Agency on
|
:
|
08 Aug 2023
|
|
|
|
24 Aug 2023
|
46
|
Bihar
|
FP/BR/Approach/143693/2021
|
FP/BR/Approach/143693/2021
|
The proposal for establishment of retail out-let dealership of M/s Indian Oil Corporation Ltd. for Approach Road Project
|
Approach Access
|
SATYAM KUMAR SINGH
|
0.006405
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
18 Jun 2021
|
Stage-I Approval on
|
:
|
14 Jun 2023
|
Compliance Report Submitted by User Agency on
|
:
|
08 Aug 2023
|
|
|
|
17 Aug 2023
|
47
|
Bihar
|
FP/BR/Others/50277/2020
|
FP/BR/Others/50277/2020
|
Diversion of 0.01275 ha of forest land for construction of approach road for opening retail outlet of IOCL on Narayanpur-Agwani Road in Begusarai district of Bihar.
|
Others
|
MANJESH KUMAR
|
0.01275
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
30 Sep 2020
|
Stage-I Approval on
|
:
|
26 Jun 2023
|
Compliance Report Submitted by User Agency on
|
:
|
04 Aug 2023
|
|
|
|
16 Aug 2023
|
48
|
Bihar
|
FP/BR/Approach/154565/2022
|
FP/BR/Approach/154565/2022
|
Diversion of 0.015 ha of forest land for construction of approach road for opening retail outlet of HPCL on SH 102 Bihia Chaurasta Jagdishpur Road in Bhojpur district of Bihar.
|
Approach Access
|
DIPIKA KUMARI
|
0.015
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
18 Apr 2022
|
Stage-I Approval on
|
:
|
07 Mar 2023
|
Compliance Report Submitted by User Agency on
|
:
|
01 Jul 2023
|
|
|
|
16 Aug 2023
|
49
|
Bihar
|
FP/BR/Others/50537/2020
|
FP/BR/Others/50537/2020
|
Diversion of 0.0135 ha of forest land for construction of approach road for opening retail outlet of HPCL on SH-69 Road in Gaya district of Bihar.
|
Others
|
GANESH PRASAD
|
0.0135
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
06 Oct 2020
|
Stage-I Approval on
|
:
|
12 Apr 2022
|
Compliance Report Submitted by User Agency on
|
:
|
15 May 2023
|
|
|
|
28 Jul 2023
|
50
|
Bihar
|
FP/BR/Approach/49711/2020
|
FP/BR/Approach/49711/2020
|
The proposal for establishment of retail out-let dealership of M/s Bharat Petroleum Corporation Ltd.
|
Approach Access
|
MS. LADLEE SINGH
|
0.02124
|
APPROVED
|
Proposal received(at Nodal Officer)electronically on
|
:
|
27 Feb 2021
|
Stage-I Approval on
|
:
|
25 Jul 2022
|
Compliance Report Submitted by User Agency on
|
:
|
08 Nov 2022
|
|
|
|
24 Jul 2023
|
|