SI No. File no. Name of the Proposal / Agenda Item State Area (ha) Category View Documents
1 8-58/2017-FC BAINIBASA GRAPHITE MINES ORISSA 44.038 MINING Click On
2 7-79/2017-FC REQUEST FOR EXEMPTION OF NPV AS PER ORDER DATED 05.10.2015 PASSED BY HON’BLE SUPREME COURT OF INDIA IN I. A NO. 2666/2009 IN W. P (C) NO. 2002/1995 TITLED T. N. GODAVARMAN THIRUMALPAD VS. UNION OF INDIA AND OTHERS-REG. NIL NIL POLICY MATTER
3 7-78/2017-FC REQUEST FOR EXEMPTION OF NPV AS PER ORDER DATED 05.10.2015 PASSED BY HON’BLE SUPREME COURT OF INDIA IN I. A NO. 2863-64/2010 IN W. P (C) NO. 2002/1995 TITLED T. N. GODAVARMAN THIRUMALPAD VS. UNION OF INDIA AND OTHERS-REG. NIL NIL POLICY MATTER
4 7-80/2017-FC REQUEST FOR EXEMPTION OF NPV AS PER ORDER DATED 05.10.2015 PASSED BY HON’BLE SUPREME COURT OF INDIA IN I. A NO. 2388/2008 IN W. P (C) NO. 2002/1995 TITLED T. N. GODAVARMAN THIRUMALPAD VS. UNION OF INDIA AND OTHERS-REG. NIL NIL POLICY MATTER
2 8-412/1989-FC DIVERSION OF 146.31 HA OF FOREST LAND FOR CONSTRUCTION OF RIHAND SUPER THERMAL POWER PROJECT STAGE-III (2X500 MW) ASH DAM AND ASH PIPE LINE IN FAVOUR OF NTPC IN THE SONEBHADRA DISTRICT OF UTTAR PRADESH. UTTAR PRADESH 146.31 THERMAL Click On
3 8-49/2017-FC PROPOSAL FOR ACCORDING PERMISSION FOR USE OF 4.62 HA. OF FOREST LAND WITHIN TOTAL MINING LEASE AREA OF 192.81 HA. IN ROIDA-C IRON AND MANGANESE MINING LEASE LOCATED ENTIRELY INSIDE SIDHAMATH RF OF KEONJHAR FOREST DIVISION IN KEONJHAR DISTRICT FOR UNDERTAKING EXPLORATORY DRILLING OF 83 NO. OF BOREHOLES OF 4” DIA (83 BOREHOLES @ 0.02 HA EACH TOTALLING 1.66HA AND 2.96HA. FOR CONSTRUCTION OF ROAD) BY M/S ODISHA MINING CORPORATION LTD. FOR PROSPECTING OF MINERALS. ORISSA 192.81 MINING Click On
4 8-82/2014-FC DIVERSION OF 1,038.187 HECTARES OF REVENUE AND DLC FOREST LAND INCLUDING 4.051 HECTARES UNDER SAFETY ZONE WITHIN THE LEASE HOLD AREA OF 1,914.063 HECTARES ALLOCATED FOR OPENCAST COAL PROJECT (OCP) BY M/S. MNH SHAKTI LTD. (TALABIRA II AND III OCP) IN JHARSUGUDA AND SAMBALPUR FOREST DIVISION WITHIN THE JURISDICTION OF JHARSUGUDA DISTRICT AND SAMBALPUR DISTRICT OF ODISHA- SUBSEQUENT RE-ALLOTMENT OF TALABIRA II AND III OCP COAL BLOCKS IN FAVOUR OF M/S. NEYVELI LIGNITE CORPORATION (NLC) INDIA LIMITED FOLLOWING CANCELLATION OF ALLOTMENT THE SAID COAL BLOCKS TO THE PRIOR ALLOTTEE I.E. M/S. MNH SHAKTI LTD.AS PER HON’BLE SUPREME COURT’S ORDER ORISSA 1038.187 MINING Click On
5 8-27/2016-FC DIVERSION OF BALANCE FOREST LAND 401.7824 HA. INCLUDING 7.2807 HA OF SAFETY ZONE OUT OF TOTAL FOREST LAND OF 519.7472 HA WITHIN TOTAL MINING LEASE AREA OF 618.576 HA FOR IRON ORE MINING IN GANDHAMARDAN (BLOCK-A) MINING LEASE IN KEONJHAR DISTRICT, ODISHA OF M/S ODISHA MINING CORPORATION LTD. DURING 2ND RENEWAL OF MINING LEASE PERIOD (LIKELY TO EXTENDED UP TO 31.03.2020 AS PER AMENDED PROVISION OF MMDR ACT, 2015 ORISSA 401.7824 MINING Click On
6 8-62/2017-FC PROPOSAL FOR ACCORDING PERMISSION FOR USE OF 8.2276 HA OF FOREST LAND WITHIN TOTAL MINING LEASE BLOCK AREA OF 256.304 HA FOR MANGANESE MINING LEASE LOCATED IN VILLAGES DHANURJOYAPUR, KANARDA, LASERDA AND KARO RF WITHIN THE JURISDICTION OF KEONJHAR FOREST DIVISION UNDER BARBIL, TAHASIL OF KEONJHAR DISTRICT, ODISHA FOR UNDERTAKING EXPLORATORY DRILLING OF 250 NO. OF BOREHOLES OF 4” DIA (250 BOREHOLES@0.02 HA EACH TOTALING 5.0 HA 2 NO. OF TRAIL PITS @0.025 HA TOTALING 0.05 HA AND 3.1776 HA FOR CONSTRUCTION OF ROAD/PATH) FOR PROSPECTING OF MINERALS BY THE PREFERRED BIDDER M/S TRIVENI EARTH MOVERS PRIVATE LTD. ORISSA 8.2276 MINING Click On
7 5-3/2007-FC DISCUSSION OF GUIDELINES FOR STIPULATING THE NORMS FOR SURVEY AND INVESTIGATION (PROSPECTING OF ORES) ON FOREST LAND. NIL NIL POLICY MATTER
8 8-47/2005-FC PT DIVERSION OF FOREST LAND OVER 360.90 HA. (INCLUDING 8.65 HA. OF SAFETY ZONE} OF SULAIPAT IRON ORE MINES OF MAYURBHANJ DISTRICT, ODISHA. ORISSA 360.9 MINING